Question

What should be the first step a team should take to feed potential problems into the...

  1. What should be the first step a team should take to feed potential problems into the Problem Solving Workshop?
    1. Identify the enablers needed to build out the Architectural Runway
    2. Conduct a short term retrospective
    3. Analyze quantitative and qualitative metrics
    4. Review feedback from System Demo
  2. What are the two purposes of the Scrum of Scrums? (choose two)
    1. Discuss program backlog priority changes
    2. Review solution architecture
    3. Facilitate cross team collaboration
    4. Collaborate release details with Systems team
    5. Identify impediments
  3. Why is the program predictability measure the primary Metric used during the quantitative measurement part of the Inspect and Adapt event?
    1. To predict the scope of the remaining requirements in the program backlog
    2. To forecast when remaining features could be delivered to customers
    3. To measure the predictability of business value delivered in the PI timebox
    4. To match customer demand to the Agile Release Train’s velocity
  4. what are the three opportunities for creating collaboration on a team (Choose Three)
    1. Communities of Practice
    2. Inspect and Adapt
    3. Backlog Refinement
    4. Pair work
    5. Hackathons
    6. Iteration Planning

Homework Answers

Answer #1

Answer 1 : The first step a team should take to feed potential problems into the Problem Solving Workshop should be (1) Identify the enablers needed to build out the Architectural Runway.

Answer 2 : The two purposes of the Scrum of Scrums are (3) Facilitate cross team collaboration and (5) Identify impediments.

Answer 3 : The program predictability measure the primary Metric used during the quantitative measurement part of the Inspect and Adapt event (4) To match customer demand to the Agile Release Train’s velocity.

Answer 4 : The three opportunities for creating collaboration on a team are (3) Backlog Refinement (4) Pair work (6) Iteration Planning.

PLEASE GIVE POSITIVE FEEDBACK AND UP RATE MY ANSWER, THANK YOU.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT