Question

A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1...

A firm with a WACC of 10% is considering the following mutually exclusive projects:

0 1 2 3 4 5
Project 1 -$300 $45 $45 $45 $200 $200
Project 2 -$650 $250 $250 $45 $45 $45

Which project would you recommend?

Select the correct answer.

a. Neither Project 1 nor 2, since each project's NPV < 0.
b. Both Projects 1 and 2, since both projects have NPV's > 0.
c. Both Projects 1 and 2, since both projects have IRR's > 0.
d. Project 2, since the NPV2 > NPV1.
e. Project 1, since the NPV1 > NPV2.

Homework Answers

Answer #1

1:

Present value of inflows=cash inflow*Present value of discounting factor(rate%,time period)

=45/1.1+45/1.1^2+45/1.1^3+200/1.1^4+200/1.1^5

=$372.70

NPV=Present value of inflows-Present value of outflows

=$372.70-$300

=$72.70(Approx).

2:

Present value of inflows=cash inflow*Present value of discounting factor(rate%,time period)

=250/1.1+250/1.1^2+45/1.1^3+45/1.1^4+45/1.1^5

=$526.37

NPV=Present value of inflows-Present value of outflows

=$526.37-$650

=$(123.63)(Approx).

Hence Project 1 must be selected having higher NPV.(Option E).

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1...
A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$300 $40 $40 $40 $165 $165 Project 2 -$400 $200 $200 $60 $60 $60 Which project would you recommend? Select the correct answer. a. Project 1, since the NPV1 > NPV2. b. Neither Project 1 nor 2, since each project's NPV < 0. c. Both Projects 1 and 2, since both projects have IRR's > 0. d. Project...
A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1...
A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$250 $40 $40 $40 $210 $210 Project 2 -$500 $250 $250 $145 $145 $145 Which project would you recommend? Select the correct answer. a. Both Projects 1 and 2, since both projects have NPV's > 0. b. Project 2, since the NPV2 > NPV1. c. Both Projects 1 and 2, since both projects have IRR's > 0. d....
A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1...
A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$500 $70 $70 $70 $235 $235 Project 2 -$400 $250 $250 $140 $140 $140 Which project would you recommend? Select the correct answer. a. Project 2, since the NPV2 > NPV1. b. Neither Project 1 nor 2, since each project's NPV < 0. c. Project 1, since the NPV1 > NPV2. d. Both Projects 1 and 2, since...
A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1...
A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$450 $40 $40 $40 $190 $190 Project 2 -$500 $250 $250 $150 $150 $150 Which project would you recommend? Select the correct answer. a. Neither Project 1 nor 2, since each project's NPV < 0. b. Project 2, since the NPV2 > NPV1. c. Both Projects 1 and 2, since both projects have IRR's > 0. d. Both...
A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1...
A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$350 $55 $55 $55 $165 $165 Project 2 -$600 $250 $250 $60 $60 $60 Which project would you recommend? Select the correct answer. a. Project 2, since the NPV2 > NPV1. b. Both Projects 1 and 2, since both projects have NPV's > 0. c. Neither Project 1 nor 2, since each project's NPV < 0. d. Project...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$500 $45 $45 $45 $160 $160 Project 2 -$450 $300 $300 $60 $60 $60 Which project would you recommend? Select the correct answer. a. Both Projects 1 and 2, since both projects have NPV's > 0. b. Project 1, since the NPV1 > NPV2. c. Both Projects 1 and 2, since both...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$350 $40 $40 $40 $215 $215 Project 2 -$650 $200 $200 $70 $70 $70 Which project would you recommend? Select the correct answer. a. Project 1, since the NPV1 > NPV2. b. Both Projects 1 and 2, since both projects have IRR's > 0. c. Project 2, since the NPV2 > NPV1....
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$250 $75 $75 $75 $170 $170 Project 2 -$700 $200 $200 $50 $50 $50 Which project would you recommend? Select the correct answer. a. Neither Project 1 nor 2, since each project's NPV < 0. b. Both Projects 1 and 2, since both projects have NPV's > 0. c. Project 1, since...
Dudley firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1...
Dudley firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$400 $55 $55 $55 $175 $175 Project 2 -$450 $350 $350 $105 $105 $105 Which project would you recommend? Select the correct answer. a. Project 1, since the NPV1 > NPV2. b. Neither Project 1 nor 2, since each project's NPV < 0. c. Project 2, since the NPV2 > NPV1. d. Both Projects 1 and 2, since...
A firm with a WACC of 10% is considering the following mutually exclusive projects:    Year...
A firm with a WACC of 10% is considering the following mutually exclusive projects:    Year 0 Year 1    Year 2    Year 3    Year 4    Year 5 Project 1 -$400 $40 $40 $40 $240 $240 Project 2 -$550 $200 $200 $105 $105 $105 Which project would you recommend? Select the correct answer. a. Both Projects 1 and 2, since both projects have NPV's > 0. b. Project 1, since the NPV1 > NPV2. c. Project 2,...