A firm with a WACC of 10% is considering the following mutually exclusive projects:
0 1 2 3 4 5
Project 1 | -$450 | $40 | $40 | $40 | $190 | $190 |
Project 2 | -$500 | $250 | $250 | $150 | $150 | $150 |
Which project would you recommend?
Select the correct answer.
|
|||
|
|||
|
|||
|
|||
|
1:
Present value of inflows=cash inflow*Present value of discounting factor(rate%,time period)
=40/1.1+40/1.1^2+40/1.1^3+190/1.1^4+190/1.1^5
=347.22
NPV=Present value of inflows-Present value of outflows
=347.22-450
=-102.78(Approx)(Negative)
2:
Present value of inflows=cash inflow*Present value of discounting factor(rate%,time period)
=250/1.1+250/1.1^2+150/1.1^3+150/1.1^4+150/1.1^5
=742.17
NPV=Present value of inflows-Present value of outflows
=742.17-500
=$242.17(Approx)
Hence project 2 must be selected having higher and positive NPV.
Hence the correct option is:
Project 2, since the NPV2 > NPV1.
Get Answers For Free
Most questions answered within 1 hours.