Dudley firm with a WACC of 10% is considering the following mutually
exclusive projects: 0 1 2 3 4 5
Project 1 -$400 $55 $55 $55 $175 $175
Project 2 -$450 $350 $350 $105 $105 $105
Which project would you recommend? Select the correct answer.
a. Project 1, since the NPV1 > NPV2.
b. Neither Project 1 nor 2, since each project's NPV < 0.
c. Project 2, since the NPV2 > NPV1.
d. Both Projects 1 and 2, since both projects have IRR's > 0.
e. Both Projects 1 and 2, since both projects have NPV's > 0.
The NPV is computed as shown below:
= Initial investment + Present value of future cash flows
Present value is computed as follows:
= Future value / (1 + r)n
So, the NPV of project 1 is computed as follows:
= - $ 400 + $55 / 1.101 + $55 / 1.102 + $55 / 1.103 + $175 / 1.104 + $175 / 1.105
= - $ 35.03 Approximately
The NPV of project 2 is computed as follows:
= - $450 + $350 / 1.10 + $350 / 1.102 + $105 / 1.103 + $105 / 1.104 + $105 /1.105
= $ 373.24 Approximately
Since the NPV of project 2 is greater than the NPV of project 1, hence the correct answer is option c i.e. Project 2, since the NPV2 > NPV1.
Feel free to ask in case of any query relating to this question
Get Answers For Free
Most questions answered within 1 hours.