Question

Dudley firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1...

Dudley firm with a WACC of 10% is considering the following mutually

exclusive projects: 0 1 2 3 4 5

Project 1 -$400 $55 $55 $55 $175 $175

Project 2 -$450 $350 $350 $105 $105 $105

Which project would you recommend? Select the correct answer.

a. Project 1, since the NPV1 > NPV2.

b. Neither Project 1 nor 2, since each project's NPV < 0.

c. Project 2, since the NPV2 > NPV1.

d. Both Projects 1 and 2, since both projects have IRR's > 0.

e. Both Projects 1 and 2, since both projects have NPV's > 0.

Homework Answers

Answer #1

The NPV is computed as shown below:

= Initial investment + Present value of future cash flows

Present value is computed as follows:

= Future value / (1 + r)n

So, the NPV of project 1 is computed as follows:

= - $ 400 +  $55 / 1.101 + $55 / 1.102 +  $55 / 1.103 + $175 / 1.104 + $175 / 1.105

= - $ 35.03 Approximately

The NPV of project 2 is computed as follows:

= - $450 + $350 / 1.10 + $350 / 1.102 + $105 / 1.103 +  $105 / 1.104 + $105 /1.105

= $ 373.24 Approximately

Since the NPV of project 2 is greater than the NPV of project 1, hence the correct answer is option c i.e. Project 2, since the NPV2 > NPV1.

Feel free to ask in case of any query relating to this question

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1...
A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$350 $55 $55 $55 $165 $165 Project 2 -$600 $250 $250 $60 $60 $60 Which project would you recommend? Select the correct answer. a. Project 2, since the NPV2 > NPV1. b. Both Projects 1 and 2, since both projects have NPV's > 0. c. Neither Project 1 nor 2, since each project's NPV < 0. d. Project...
A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1...
A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$450 $40 $40 $40 $175 $175 Project 2 -$650 $350 $350 $40 $40 $40 Which project would you recommend? Select the correct answer. a. Both Projects 1 and 2, since both projects have NPV's > 0. b. Project 2, since the NPV2 > NPV1. c. Both Projects 1 and 2, since both projects have IRR's > 0. d....
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$250 $50 $50 $50 $175 $175 Project 2 -$700 $350 $350 $80 $80 $80 Which project would you recommend? Select the correct answer. a. Project 2, since the NPV2 > NPV1. b. Project 1, since the NPV1 > NPV2. c. Both Projects 1 and 2, since both projects have NPV's > 0....
A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1...
A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$450 $40 $40 $40 $190 $190 Project 2 -$500 $250 $250 $150 $150 $150 Which project would you recommend? Select the correct answer. a. Neither Project 1 nor 2, since each project's NPV < 0. b. Project 2, since the NPV2 > NPV1. c. Both Projects 1 and 2, since both projects have IRR's > 0. d. Both...
A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1...
A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$500 $70 $70 $70 $235 $235 Project 2 -$400 $250 $250 $140 $140 $140 Which project would you recommend? Select the correct answer. a. Project 2, since the NPV2 > NPV1. b. Neither Project 1 nor 2, since each project's NPV < 0. c. Project 1, since the NPV1 > NPV2. d. Both Projects 1 and 2, since...
A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1...
A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$300 $40 $40 $40 $165 $165 Project 2 -$400 $200 $200 $60 $60 $60 Which project would you recommend? Select the correct answer. a. Project 1, since the NPV1 > NPV2. b. Neither Project 1 nor 2, since each project's NPV < 0. c. Both Projects 1 and 2, since both projects have IRR's > 0. d. Project...
A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1...
A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$300 $45 $45 $45 $200 $200 Project 2 -$650 $250 $250 $45 $45 $45 Which project would you recommend? Select the correct answer. a. Neither Project 1 nor 2, since each project's NPV < 0. b. Both Projects 1 and 2, since both projects have NPV's > 0. c. Both Projects 1 and 2, since both projects have...
A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1...
A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$250 $40 $40 $40 $210 $210 Project 2 -$500 $250 $250 $145 $145 $145 Which project would you recommend? Select the correct answer. a. Both Projects 1 and 2, since both projects have NPV's > 0. b. Project 2, since the NPV2 > NPV1. c. Both Projects 1 and 2, since both projects have IRR's > 0. d....
A firm with a WACC of 10% is considering the following mutually exclusive projects:    Year...
A firm with a WACC of 10% is considering the following mutually exclusive projects:    Year 0 Year 1    Year 2    Year 3    Year 4    Year 5 Project 1 -$400 $40 $40 $40 $240 $240 Project 2 -$550 $200 $200 $105 $105 $105 Which project would you recommend? Select the correct answer. a. Both Projects 1 and 2, since both projects have NPV's > 0. b. Project 1, since the NPV1 > NPV2. c. Project 2,...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$500 $45 $45 $45 $160 $160 Project 2 -$450 $300 $300 $60 $60 $60 Which project would you recommend? Select the correct answer. a. Both Projects 1 and 2, since both projects have NPV's > 0. b. Project 1, since the NPV1 > NPV2. c. Both Projects 1 and 2, since both...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT