Scenario Analysis
Shao Industries is considering a proposed project for its capital budget. The company estimates the project's NPV is $12 million. This estimate assumes that the economy and market conditions will be average over the next few years. The company's CFO, however, forecasts there is only a 50% chance that the economy will be average. Recognizing this uncertainty, she has also performed the following scenario analysis:
Economic Scenario | Probability of Outcome | NPV |
Recession | 0.05 | -$82 million |
Below average | 0.20 | -24 million |
Average | 0.50 | 12 million |
Above average | 0.20 | 20 million |
Boom | 0.05 | 34 million |
What are the project's expected NPV, standard deviation, and coefficient of variation? Enter your answers for the NPV and standard deviation in millions. For example, an answer of $1.24 million should be entered as 1.24, not 1,240,000. Do not round intermediate calculations. Round your answers to two decimal places.
E(NPV) | $ million |
σNPV | $ million |
CVNPV |
Expected NPV = 0.05 * (-82) + 0.20 * (-24) + 0.50 * 12 + 0.20 *
20 + 0.05 * 34
Expected NPV = 2.80
So, Expected NPV is $2.80 million
Variance = 0.05 * (-82 - 2.80)^2 + 0.20 * (-24 - 2.80)^2 + 0.50
* (12 - 2.80)^2 + 0.20 * (20 - 2.80)^2 + 0.05 * (34 - 2.80)^2
Variance = 653.36
Standard Deviation = (653.36)^(1/2)
Standard Deviation = 25.56
Standard Deviation in NPV = $25.56 million
Coefficient of Variation = Standard Deviation in NPV / Expected
NPV
Coefficient of Variation = $25.56 million / $2.80 million
Coefficient of Variation = 9.13
Get Answers For Free
Most questions answered within 1 hours.