If a company selects either of Project 1 or Project 2 (or both), then either Project 3 or Project 4 (or both) must also be selected. Which of the following constraints enforce this condition?
a. X1 + X2 ≤ 2(X3 + X4)
b. X1 + X2 ≤ X3 + X4
c. X1 − X3 = X2 − X4
d. X1 + X2 + X3 + X4 ≤ 2
Select - Option - A ......... X1+ X2 ≤ 2(X3 + X4)
Explanation.
The company select project - 1 only when Project - 3 and Project - 4 are individually or collectively better than or equal to it.
Hence ............. X1 ≤ (X3 + X4)
The company select project - 2 only when Project - 3 and Project - 4 are individually or collectively better than or equal to it.
Hence ............. X2 ≤ (X3 + X4)
Now X1 or X2 or Both implies .............
X1 + X2 = (X3 + X4) + (X3 + X4)
X1 + X2 = 2X3 + 2X4
X1 + X2 = 2(X3 +X4)