Question

Consider a capital budgeting problem with seven projects represented by binary (0 or 1) variables X1,...

Consider a capital budgeting problem with seven projects represented by binary (0 or 1) variables X1, X2, X3, X4, X5, X6, X7.

  1. Write a constraint modeling the situation in which only 2 of the projects from 1, 2, 3, and 4 must be selected.
  2. Write a constraint modeling the situation in which at least 2 of the project from 1, 3, 4, and 7 must be selected.
  3. Write a constraint modeling the situation project 3 or 6 must be selected, but not both.
  4. Write a constraint modeling the situation in which at most 4 projects from the 7 can be selected.

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
There are three projects.  Binary variablesX1, X2, and X3are defined as follows: Xi=     1 if project i is...
There are three projects.  Binary variablesX1, X2, and X3are defined as follows: Xi=     1 if project i is selected, and Xi=     0 if project i is not selected,           for i = 1, 2, 3. 5. Write a constraint to represent: “Project 2 and project 3 must go together.  That is, it is not allowed to select one while deselect the other”. 6. Write a constraint to represent: “The three projects can not be all selected.  There must be at least one that is not selected”. 7....
SHOW ALL WORK! Consider a capital budgeting example with five projects from which to select. Let...
SHOW ALL WORK! Consider a capital budgeting example with five projects from which to select. Let xi = 1 if project i is selected, 0 if not, for i = 1,...,5. Write the appropriate constraint(s) for each condition. Conditions are independent. a. Choose no fewer than four projects. b. If project 2 is chosen, project 3 must be chosen. c. If project 5 is chosen, project 4 must not be chosen. d. Projects cost 130, 220, 150, 75, and 300...
5.8 Explain how the following conditions can be represented as linear constraints using binary variables. (a)...
5.8 Explain how the following conditions can be represented as linear constraints using binary variables. (a) Either x1 + x2 ? 3 or 3x1 + 4x2 ? 10 (b) Variable x2 can assume values 0, 4, 7, 10, and 12 only (c) If x2 ? 3, then x3 ? 6; Otherwise x3 ? 4 (assume x2 and x3 are integers) (d) At least 2 out of the following 5 constraints must be satisfied: x1 + x2 <=7 x1 ? x2...
Consider the following linear program Max 5x1+5x2+3x3 St x1+3x2+x3<=3 -x1+ 3x3<=2 2x1-x2 +2x3<=4 2x1+3x2-x3<=2 xi>=0 for...
Consider the following linear program Max 5x1+5x2+3x3 St x1+3x2+x3<=3 -x1+ 3x3<=2 2x1-x2 +2x3<=4 2x1+3x2-x3<=2 xi>=0 for i=1,2,3 Suppose that while solving this problem with Simplex method, you arrive at the following table: z x1 x2 x3 x4 x5 x6 x7 rhs Row0 1 0 -29/6 0 0 0 11/6 2/3 26/3 Row1 0 0 -4/3 1 0 0 1/3 -1/3 2/3 Row2 0 1 5/6 0 0 0 1/6 1/3 4/3 Row3 0 0 7/2 0 1 0 -1/2 0...
If a company selects either of Project 1 or Project 2 (or both), then either Project...
If a company selects either of Project 1 or Project 2 (or both), then either Project 3 or Project 4 (or both) must also be selected. Which of the following constraints enforce this condition? a. X1 + X2 ≤ 2(X3 + X4) b. X1 + X2 ≤ X3 + X4 c. X1 − X3 = X2 − X4 d. X1 + X2 + X3 + X4 ≤ 2
Qualis Investments is a private limited business that manages personal financial portfolios. The company manages six...
Qualis Investments is a private limited business that manages personal financial portfolios. The company manages six mutual funds and has a client that has acquired $750,000 from an inheritance. Characteristics of the funds are given in the table below. Qualis Mutual Fund Data Expected Annual Return Risk Measure 1 Qualis Low-priced Stock Fund 7.23% 11.87 2 Qualis Multinational Fund 8.42% 12.62 3 Qualis Mid-cap Stock Fund 6.66% 13.72 4 Qualis Mortgage Fund 2.72% 3.37 5 Qualis Income Equity Fund 8.89%...
Brooks Development Corporation (BDC) faces the following capital budgeting decision. Six real estate projects are available...
Brooks Development Corporation (BDC) faces the following capital budgeting decision. Six real estate projects are available for investment. The net present value and expenditures required for each project (in millions of dollars) are as follows: Project    1    2    3    4 5    6 Net Present value ($Millions) $15 $5    $13 $14    $20    $9 Expedature required ($Millions) $90 $34    $81 $70    $114    $50 There are conditions that limit the investment alternatives:...
9.  Problem 11.10 (Capital Budgeting Criteria: Mutually Exclusive Projects) eBook A firm with a WACC of 10%...
9.  Problem 11.10 (Capital Budgeting Criteria: Mutually Exclusive Projects) eBook A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$300 $65 $65 $65 $230 $230 Project 2 -$550 $200 $200 $135 $135 $135 Which project would you recommend? Select the correct answer. a. Neither Project 1 nor 2, since each project's NPV < 0. b. Both Projects 1 and 2, since both projects have IRR's > 0. c....
An analyst is running a regression model using the following data: Y x1 x2 x3 x4...
An analyst is running a regression model using the following data: Y x1 x2 x3 x4 x5 x6 4 1 5 0 -95 17 12 10 5 8 1 -27 7 10 32 1 7 0 -82 0 9 2 2 7 0 17 5 10 9 3 9 1 -46 5 11 Excel performs the regression analysis, but the output looks all messed up: For example the F statistic cannot be computed, standard errors are all zero, etc etc....
1.Capital budgeting is for situations in which managers must plan significant outlays for projects that have...
1.Capital budgeting is for situations in which managers must plan significant outlays for projects that have long term implications. T F 2.Capital budgeting is for situations in which large amounts of money usually involved. T F 3.One of the considerations in investment decision considerations is choosing the project with the most profitable return on available funds. T F