A company has a capital budget of $300 and is evaluating the following projects capital projects. What should the company do?
Project |
Initial Investment ($ millions) |
PV(NCF) ($ millions) |
A |
200 |
420 |
B |
300 |
660 |
C |
200 |
380 |
D |
200 |
330 |
E |
100 |
250 |
SEE THE IMAGE. ANY DOUBTS, FEEL FREE TO ASK. THUMBS UP PLEASE