Question

Sparkling Water Inc. (SWI) has just completed minor renovations to the CEOs office at a cost...

Sparkling Water Inc. (SWI) has just completed minor renovations to the CEOs office at a cost of $50,000. Originally, SWI planned to spend only $25,000 for this renovation. In a memo, the accounting group suggests allocating the cost over-run to the next project SWI will undertake.

As the next project, Sparkling Water Inc. is evaluating an investment in a new mineral water bottling plant. The required investment for the new bottling plant is $700,000 (at t = 0). The useful economic life of the plant is ten years. The salvage value of the plant in ten years is zero (at t = 10).

SWI hired PV Consultants for a market study. In their final report, the consultants estimate that SWI’s annual sales less expenses (before tax and not including depreciation) will increase from currently $350,000/year to $550,000/year (at t = 1 to t = 10). The consultants also estimate that net working capital will increase by $50,000 today (at t = 0) to meet increased demand and will be recaptured completely at the end of the project (at t = 10). The fee for this study amounts to $30,000 and SWI is required to pay this fee in one year (at t = 1)

The new mineral water bottling plant belongs to asset class 43 with a CCA rate of 30%. SWI will have other class 43 assets in ten years. SWI’s tax rate is 35% and it uses a required rate of return of 15% (EAR) to evaluate this project.

What is the CCA tax shield in year 2 (at t = 2)?

a) $51,450

b) $178,500

c) $62,475

d) $147,000 e) $111,475

What is the present value of CCA tax shields today (at t = 0)? a) $31,957

b) $152,681

c) $160,315
d) $163,587
e) $0, because the plant has a zero salvage value.

Suppose you find out that at the end of the project (at t = 10), to demolish the bottling plant and clean up the production site, SWI would incur additional before-tax clean-up costs of $25,000. By how much would the NPV of the project change based on this new information?
a) -$4,017

b) -$25,000
c) -$16,250
d) This information would not affect the NPV because it does not affect the project’s sales or expenses. e) The NPV would not change because the clean-up costs are sunk costs.

Suppose based on all the above information, SWI’s project team has calculated:

10∑t=0 CFt/ (1+RRR)^t =$67,480
CFt includes all project-relevant cash flows (including CCA tax shields). Based on this number, would you accept the project? Assume that for this project, a decision can be made using the IRR rule.
a) Yes, because the IRR > required rate of return (RRR).
b) No, because the IRR > required rate of return (RRR).

c) Yes, because the NPV = 0.
d) Yes, because the NPV < 0.
e) No, because the project’s payback period is greater than the project’s life (i.e., 10 years).

Homework Answers

Answer #1

Solution:

CCA tax shield in year 2 (at t = 2)?

The answer is c) $62,475. Explation provided below:

Cost of the bottling plant is $700,000 at t=0. CCA is 30%; so first year depreciation will be $700000 * 0.3 * 0.5 = $105,000 since only 50% depreciation can be claimed. Second year t=2 depreciation is (700,000 - 105,000)*0.3 = $178,500

Tax rate is 35%

Hence, tax shield from CCA is $178,000 * 0.35 = $62,475.

Annual sales less expenses (before tax and not including depreciation) is $550,000/year. So same would apply to t=2. Cost over run is $ (50,000 - 25,000) = $ 25,000 which is to be allocated over the life of the bottling project. So $25,000 /10 years = $2,500. Same applies to t=2

Present value of CCA tax shields today (at t = 0)?

The solution is b) $152,681 as it is closest to our calculation done below:

Year 1 2 3 4 5 6 7 8 9 10
CCA deduction ** -105000 -178500 -124950 -87465 -61225.5 -42857.9 -30000.5 -21000.3 -14700.2 -10290.2
Tax shield @ 35% -36750 -62475 -43732.5 -30612.8 -21428.9 -15000.2 -10500.2 -7350.12 -5145.08 -3601.56
Discount factors (1/1.15^n) 0.87 0.756 0.658 0.572 0.497 0.432 0.376 0.327 0.284 0.247
Tax shield * Discount rate -31972.5 -47231.1 -28776 -17510.5 -10650.2 -6480.11 -3948.07 -2403.49 -1461.2 -889.585
Total of all the above present values (in the last row above) -151323
** CCA deduction for t=1 & 2 calculated above for rest it is 30% of balance of $ 700,000 after previous deductions

Hence present value of CCA tax shield is $152,681

By how much would the NPV of the project change based on additional before tax clean up cost of $25,000 at t=10?

The answer is a) -$4,017. Explation provided below

Cash flows in t=10 without the additional before tax clean up cost of $25,000 would be:

a) Net income of $550,000

b) Recovery of working capital of $50,000

c) Amortization of cost over run of renovations to the CEOs office of (-) $2,500 (Non cash flow expense)

d) CCA deduction of (-) $10,290.20 according to our calculation in the previous answer. (Non cash flow expense)

So the net income by adding all the above values would be $587,209.80. Tax shield is $587,209.80* (-)0.35 = (-) $ 205,523.43 and Net income after tax $ 381,686.37. Add back CCA deduction & cost over run amortization as these are not cash flows to get pure cash inflow of $381686.37 + $10290.2 + $2500 = $394,476.57. Present value by multiplying discount factor 0.247 * $394,476.57 = $ 97,435.71

Had the clean up cost be considered the net income by adding all the above values would be $587,209.80 - $ 25,000 = $562,209.80. Tax shield is $562,209.80* (-)0.35 = (-) $ 196,773.43 and Net income after tax $ 365,436.37. Add back CCA deduction & cost over run amortization as these are not cash flows to get pure cash inflow of $365,436.37 + $10290.2 + $2500 = $378,226.57. Present value by multiplying discount factor 0.247 * $378,226.57 = $ 93421.96

Difference between the above two present values would be the difference in the NPV. So,  $ 97,435.71 - $ 93421.96 = 4013.75 which is the closest answer.

Based on 10∑t=0 CFt/ (1+RRR)^t =$67,480, would you accept the project?

The answer is a) Yes, because the IRR > required rate of return (RRR).

The required rate of return (RRR) is 15%. The above formula denotes that SWI's project team has calculated the NPV applying RRR = 15% and NPV is positive implying that the present value of all net cash flows is positive. This means that if we discount the net cash flows gradually by increasing the required rates of return above 15%, the net cash flows would be discounted more heavily bringing down $ 67,480 to 0 at some point. The rate that discounts the net cash flows or NPV to 0 is the Internal Rate of Return (IRR) of the project. Thus the reason for accepting the project assume that for this project, a decision can be made using the IRR rule is that the IRR would be greater than RRR.  The project generates higher return at the IRR than 15% expected of it.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
J. Morgan of SparkPlug Inc. has been approached to take over a production facility from B.R....
J. Morgan of SparkPlug Inc. has been approached to take over a production facility from B.R. Machine Company. The acquisition will cost $1,960,000, and the after-tax net cash inflow will be $330,000 per year for 12 years. SparkPlug currently uses 10% for its after-tax cost of capital. Tom Morgan, production manager, is very much in favor of the investment. He argues that the total after-tax net cash inflow is more than the cost of the investment, even if the demand...
Specter Ind. is considering a new project involving the acquisition of a new machine that would...
Specter Ind. is considering a new project involving the acquisition of a new machine that would replace an older machine currently in use. The new machine costs $650,000 (at t=0) and can be sold at the end of its expected 4-year operating life for $380,000 (at t=4). The old machine was bought 5 years ago for $500,000 and can be sold for $220,000 today or for $120,000 in 4 years. Both, the old and the new machine belong to asset...
Garage, Inc., has identified the following two mutually exclusive projects:     Year Cash Flow (A) Cash...
Garage, Inc., has identified the following two mutually exclusive projects:     Year Cash Flow (A) Cash Flow (B) 0 –$ 28,000 –$ 28,000 1 13,400 3,800 2 11,300 9,300 3 8,700 14,200 4 4,600 15,800    a-1 What is the IRR for each of these projects? (Do not round intermediate calculations. Enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.)    IRR   Project A %   Project B %    a-2 Using the IRR decision rule, which...
Your boss, the chief financial officer (CFO) for Southern Textiles, has just handed you the estimated...
Your boss, the chief financial officer (CFO) for Southern Textiles, has just handed you the estimated cash flows for two proposed projects. Project L involves adding a new item to the firm’s fabric line. It would take some time to build up the market for this product, so the cash inflows would increase over time. Project S involves an add-on to an existing line, and its cash flows would decrease over time. Both projects have 3-year lives because Southern is...
1. Newex, Inc. has a capital investment opportunity with the following cash flows: Year cash flow...
1. Newex, Inc. has a capital investment opportunity with the following cash flows: Year cash flow 0 (100,000) 1 45,000 2 35,000 3 30,000 4 20,000 Which of the following is closest to the project’s payback period? a) 4 years b) 2 years c) 3.7 years d) 3.5 years e) 2.7 years 2. Zoomit Corporation has a capital investment opportunity that will cost $250,000. The cash inflows from year 1 through year 10 will be $40,000 each year. The firm’s...
Roberts Fabrication and Automation, Inc. (RFA) just completed its Capital Budgeting analysis for a new metallic...
Roberts Fabrication and Automation, Inc. (RFA) just completed its Capital Budgeting analysis for a new metallic 3D printing machine that will aid in the design and production of new “classic” and customautomotive components. The NPV is positive and significant, the IRR is well above the 12% project hurdle rate (required return), and RFA has decided to move forward with the project. The next part of their analysis involves the financing of the machine, that is, whether to purchase, or to...
4. Alyeska Salmon Inc., a large salmon canning firm operating out of Valdez, Alaska, has a...
4. Alyeska Salmon Inc., a large salmon canning firm operating out of Valdez, Alaska, has a new automated production line project it is considering. The project has a cost of $275,000 and has an expected life of eight years. The project provides after-tax annual cash flows of $73,306 per year for the first five years. In year 6, there is cash OUTFOW of $100,000. For years 7-8, the net cash flows will be $89,000 per year. The firm’s management is...
1. Fast Machines Inc. must decide whether to upgrade its production facilities, at a cost of...
1. Fast Machines Inc. must decide whether to upgrade its production facilities, at a cost of $35,770,000. Doing so will allow it to bring several exciting new products to the market. The following table presents the estimated incremental cash flows that would result from the upgrade, over the expected 10-year life of the project: Years 1-9 $5,750,000 Year 10 $12,000,000 What is the NPV of the project, given that Fast Machines' required rate of return for a project of this...
Napier Paper Inc. is deciding whether to build a new manufacturing plant. The proposed project would...
Napier Paper Inc. is deciding whether to build a new manufacturing plant. The proposed project would have an upfront cost (at t = 0) of $30 million. The project's cost can be depreciated on a straight-line basis over three years. Consequently, the depreciation expense will be $10 million in each of the first three years, t = 1, 2, and 3. Even though the project is depreciated over three years, the project has an economic life of five years. The...
Which of the following distinguishes scenario analysis from sensitivity analysis? a. Scenario analysis only applies to...
Which of the following distinguishes scenario analysis from sensitivity analysis? a. Scenario analysis only applies to new product development projects. b. Sensitivity analysis only applies to new product development projects c. Sensitivity analysis involves changing one project variable at a time while scenario analysis involves changing more than one project variable at the same time d. Sensitivity analysis only applies when projects are mutually exclusive. 3. Which of the following statements is true regarding the internal rate of return (IRR)?...