Using gross labour rates of R5,00 per hour for craftsmen and R2,00 per hour for labourers, and the prices of materials given below, work up the following rates:
1. Cement mortar (1:4) hand-mixed …per cubic metre.
2. Cement lime mortar (1:2:9), machine-mixed …per cubic metre.
3. (a) Half-brick wall in common bricks in
mortar (1:4) …per square metre.
(b) Ditto fair-faced and pointed both sides …per square metre.
4. Bituminous felt DPC 115mm wide …per linear metre.
5. Clinker concrete hollow block partition 225mm
thick in cement lime mortar (1:2:9) …per square metre.
6. (a) Hole for 25mm pipe through 225mm brick
wall …each.
(b) Hole for 100mm pipe through 115mm brick
wall and make good facings both sides …each.
(c) Hole for 150mm pipe through 225mm
concrete block …each.
7. Extra over common brickwork for 70mm facing
bricks in Flemish bond, the joint raked out and
pointed with coloured cement mortar …per square metre.
8. One-brick wall in 75 mm facing bricks in English
bond in cement mortar (1:4), fair-faced and pointed
both sides as the work proceeds …per square metre.
PRICE OF MATERIALS (for tuition purposes only) R C