Question

Company X makes 2 products: Product A and Product B. Annual production and sales are 375...

Company X makes 2 products: Product A and Product B. Annual production and sales are 375 units of Product A and 400 units of Product B. The company has traditionally used direct labor-hours as the basis for applying all manufacturing overhead to products. Product A requires 0.8 direct labor-hours per unit and Product B requires 0.5 direct labor-hours per unit. The total estimated overhead for next period is $80,500.

The company is considering switching to an activity-based costing system for the purpose of computing unit product costs for external reports. The new activity-based costing system would have three overhead activity cost pools--Activity 1, Activity 2, and General Factory--with estimated overhead costs and expected activity as follows:

Expected Activity
Activity Cost Pool Estimated Overhead Costs Product A Product B Total
Activity 1 $ 45,600 1,300 700 2,000
Activity 2 19,800 1,000 500 1,500
General Factory 15,100 300 200 500
Total $ 80,500

(Note: The General Factory activity cost pool's costs are allocated on the basis of direct labor-hours.)

The overhead cost per unit of Product B under the activity-based costing system is closest to:

Multiple Choice

  • $36.00

  • $71.50

  • $19.10

  • $76.30

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Adelberg Corporation makes two products: Product A and Product B. Annual production and sales are 1,000...
Adelberg Corporation makes two products: Product A and Product B. Annual production and sales are 1,000 units of Product A and 800 units of Product B. The company has traditionally used direct labor-hours as the basis for applying all manufacturing overhead to products. Product A requires 0.8 direct labor-hours per unit and Product B requires 0.5 direct labor-hours per unit. The total estimated overhead for next period is $125,320. The company is considering switching to an activity-based costing system for...
Jake Inc manufactures two products: A and B. The annual production and sales of Product A...
Jake Inc manufactures two products: A and B. The annual production and sales of Product A is 500 units and of Product B is 1,000 units. The company currently uses Direct Labor Hours as the basis for applying all Manufacturing Overhead to products. Product A requires 0.4 Direct Labor Hours per unit and Product B requires 0.2 Direct Labor Hours per unit (direct labor is $20 per hour). Also, direct materials is $5 for Product A and $10 for Product...
Adelberg Company has two products: A and B. The annual production and sales of Product A...
Adelberg Company has two products: A and B. The annual production and sales of Product A is 2,300 units and of Product B is 1,700 units. The company has traditionally used direct labor-hours as the basis for applying all manufacturing overhead to products. Product A requires 0.3 direct labor-hours per unit and Product B requires 0.6 direct labor-hours per unit. The total estimated overhead for next period is $105,475. The company is considering switching to an activity-based costing system for...
Adelberg Company has two products: A and B. The annual production and sales of Product A...
Adelberg Company has two products: A and B. The annual production and sales of Product A is 1,800 units and of Product B is 1,200 units. The company has traditionally used direct labor-hours as the basis for applying all manufacturing overhead to products. Product A requires 0.5 direct labor-hours per unit and Product B requires 0.8 direct labor-hours per unit. The total estimated overhead for next period is $99,975. The company is considering switching to an activity-based costing system for...
Which of the following would probably be the least appropriate allocation base for allocating overhead in...
Which of the following would probably be the least appropriate allocation base for allocating overhead in a highly automated manufacturer of specialty valves? A. machine-hours B. power consumption C. direct labor-hours D. machine setups 1 points QUESTION 6 In a job-order costing system, the amount of overhead cost that has been applied to a job that remains incomplete at the end of a period: A. is deducted on the Income Statement as overapplied overhead. B. is closed to Cost of...
Boahn, Inc., manufactures and sells two products: Product B6 and Product W8. Data concerning the expected...
Boahn, Inc., manufactures and sells two products: Product B6 and Product W8. Data concerning the expected production of each product and the expected total direct labor-hours (DLHs) required to produce that output appear below: Expected Production Direct Labor-Hours Per Unit Total Direct Labor-Hours Product B6 200 7.0 1,400 Product W8 100 9.0   900 Total direct labor-hours 2,300 The company is considering adopting an activity-based costing system with the following activity cost pools, activity measures, and expected activity: Estimated Expected Activity...
Contrasting ABC and Conventional Product Costs Rocky Mountain Corporation makes two types of hiking boots—Xactive and...
Contrasting ABC and Conventional Product Costs Rocky Mountain Corporation makes two types of hiking boots—Xactive and Pathbreaker, Data concerning these two product lines appear below: Xactive Pathbreaker Direct materials per unit $64.80 $51.00 Direct labor costs per unit $18.20 $13.00 Direct labor -hours per unit 1.4 DLHs 1.0 DLHs Estimated annual production and sales 25,000 units 75,000 units The company has a conventional costing system in which manufacturing overhead is applied to units based on direct labor-hours. Data concerning manufacturing...
Rocky Mountain Corporation makes two types of hiking boots—Xactive and Pathbreaker. Data concerning these two product...
Rocky Mountain Corporation makes two types of hiking boots—Xactive and Pathbreaker. Data concerning these two product lines appear below: Xactive Pathbreaker Direct materials per unit $ 65.20 $ 51.40 Direct labor cost per unit $ 18.60 $ 13.40 Direct labor-hours per unit 1.4 DLHs 1 DLHs Estimated annual production and sales 29,000 units 79,000 units The company has a conventional costing system in which manufacturing overhead is applied to units based on direct labor-hours. Data concerning manufacturing overhead and direct...
Arntson, Inc., manufactures and sells two products: Product R3 and Product N0. The annual production and...
Arntson, Inc., manufactures and sells two products: Product R3 and Product N0. The annual production and sales of Product of R3 is 1,200 units and of Product N0 is 200 units. Data concerning the expected production of each product and the expected total direct labor-hours (DLHs) required to produce that output appear below: Expected Production Direct Labor-Hours Per Unit Total Direct Labor-Hours Product R3 1,200 8.0 9,600 Product N0 200 4.0 800 Total direct labor-hours 10,400 The direct labor rate...
Vandalay Industries manufactures two​ products: toasters and blenders. The annual production and sales of toasters is...
Vandalay Industries manufactures two​ products: toasters and blenders. The annual production and sales of toasters is 2,400 ​units, while 1,300 units of blenders are produced and sold. The company has traditionally used direct labor hours to allocate its overhead to products. Toasters require 1.25 direct labor hours per​ unit, while blenders require 1 direct labor hours per unit. The total estimated overhead for the period is $146,215. The company is looking at the possibility of changing to an activityminus−based costing...