Question

Question 1 Part A and B A. On July 1, 2018, Apache Company, a real estate...

Question 1 Part A and B

A.

On July 1, 2018, Apache Company, a real estate developer, sold a parcel of land to a construction company for $3,080,000. The book value of the land on Apache’s books was $1,320,000. Terms of the sale required a down payment of $220,000 and 13 annual payments of $220,000 plus interest at an appropriate interest rate due on each July 1 beginning in 2019.

How much revenue will Apache recognize for the sale (ignoring interest), assuming that it recognizes revenue at the point in time at which it transfers the land to the construction company? (Leave no cells blank - be certain to enter "0" wherever required.)

2018 Revenue=

2019 revenue=

B. Tulane Tires wrote a contract for a $104,000 sale to the new Garden District Tour Company. Tulane only anticipates a slightly greater than fifty percent chance that Garden will be able to pay the amounts that Tulane is entitled to receive under the contract. Upon delivery of the tires, assuming no payment has yet been made by Garden, how much revenue should Tulane recognize under U.S. IFRS?

Revenue under IFRS=

Homework Answers

Answer #1

Ans.

Part A

In the given case, revenue is recognized at a point when the parcel of land is transferred to the construction company.

Therefore, full revenue should be recognized in 2018 because transfer of land to construction company is made in 2018.

And no revenue will be recognized in the year 2019.

2018 Revenue = $ 3,080,000

2019 revenue = $ 0

Part B

Revenue under IFRS = $ 104,000

Under IFRS, this contract would qualify for revenue recognition as “probable” is defined as a likelihood which is greater than 50%.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
On July 1, 2021, Apache Company, a real estate developer, sold a parcel of land to...
On July 1, 2021, Apache Company, a real estate developer, sold a parcel of land to a construction company for $3,080,000. The book value of the land on Apache’s books was $1,320,000. Terms of the sale required a down payment of $220,000 and 13 annual payments of $220,000 plus interest at an appropriate interest rate due on each July 1 beginning in 2022. How much revenue will Apache recognize for the sale (ignoring interest), assuming that it recognizes revenue at...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
Colah Company purchased $2.3 million of Jackson, Inc. 6% bonds at par on July 1, 2018,...
Colah Company purchased $2.3 million of Jackson, Inc. 6% bonds at par on July 1, 2018, with interest paid semi-annually. When the bonds were acquired Colah decided to elect the fair value option for accounting for its investment. At December 31, 2018, the Jackson bonds had a fair value of $2.63 million. Colah sold the Jackson bonds on July 1, 2019 for $2,070,000. The purchase of the Jackson bonds on July 1. Interest revenue for the last half of 2018....
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
Multiple Choice Question 103 Oriole Construction is constructing an office building under contract for Cannon Company...
Multiple Choice Question 103 Oriole Construction is constructing an office building under contract for Cannon Company and uses the percentage-of-completion method. The contract calls for progress billings and payments of $1100000 each quarter. The total contract price is $13200000 and Oriole estimates total costs of $17300000. Oriole estimates that the building will take 3 years to complete, and commences construction on January 2, 2018. At December 31, 2019, Oriole Construction estimates that it is 75% complete with the building; however,...
Crane Landscaping began construction of a new plant on December 1, 2017. On this date, the...
Crane Landscaping began construction of a new plant on December 1, 2017. On this date, the company purchased a parcel of land for $140,400 in cash. In addition, it paid $2,640 in surveying costs and $3,840 for a title insurance policy. An old dwelling on the premises was demolished at a cost of $3,120, with $1,200 being received from the sale of materials. Architectural plans were also formalized on December 1, 2017, when the architect was paid $34,800. The necessary...
Culver Landscaping began construction of a new plant on December 1, 2017. On this date, the...
Culver Landscaping began construction of a new plant on December 1, 2017. On this date, the company purchased a parcel of land for $148,800 in cash. In addition, it paid $1,920 in surveying costs and $3,840 for a title insurance policy. An old dwelling on the premises was demolished at a cost of $3,360, with $960 being received from the sale of materials. Architectural plans were also formalized on December 1, 2017, when the architect was paid $39,600. The necessary...
On January 1, 2018, the San Marcos Company issues, $300,000 of 8% bonds due in 10...
On January 1, 2018, the San Marcos Company issues, $300,000 of 8% bonds due in 10 years. These were issued for $280,488 to yield a 9% rate. Instructions 1. Prepare a bond interest expense and discount amortization schedule using the effective interest method for the first two years of the life of the bond. 2. Prepare a bond interest expense and discount amortization schedule assuming the company followed the straight-line method of discount amortization first two years of the life...
Question 1 Part A and B A. The following is a partial year-end adjusted trial balance....
Question 1 Part A and B A. The following is a partial year-end adjusted trial balance. Account Title Debits Credits Sales revenue 420,000 Loss on sale of investments 46,000 Interest revenue 4,500 Cost of goods sold 220,000 General and administrative expenses 52,000 Restructuring costs 62,000 Selling expenses 31,000 Income tax expense 0 Income tax expense has not yet been recorded. The income tax rate is 40%. a. Determine the operating income (loss). b. Determine the income (loss) before income taxes....
The following transactions occurred during December 31, 2018, for the Falwell Company. 1. A three-year fire...
The following transactions occurred during December 31, 2018, for the Falwell Company. 1. A three-year fire insurance policy was purchased on July 1, 2018, for $14,760. The company debited insurance expense for the entire amount. 2. Depreciation on equipment totaled $14,000 for the year. 3. Employee salaries of $20,500 for the month of December will be paid in early January 2019. 4. On November 1, 2018, the company borrowed $270,000 from a bank. The note requires principal and interest at...