Question

In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:

2021 2022 2023
Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600
Estimated costs to complete as of year-end 5,810,000 1,826,000 0
Billings during the year 2,030,000 4,444,000 3,526,000
Cash collections during the year 1,815,000 3,900,000 4,285,000


Westgate recognizes revenue over time according to percentage of completion.

Required:
1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. (Do not round intermediate calculations. Loss amounts should be indicated with a minus sign.)

Homework Answers

Answer #1

Solution:

Computation of % of completion, revenue recognition and Gross Profit - Westgate Construction Company
Year Actual cost incurred (A) Total cost incurred till date (B) Total estimated Cost ( C ) % of completion (D) (B/C) Contract Price
(E)
Total Revenue to be recoganized (F) (E * D) Revenue for current period (G) Gross Profit (H)
2021 $24,90,000 $24,90,000 $83,00,000 30.00% $1,00,00,000 $30,00,000 $30,00,000 $5,10,000
2022 $39,84,000 $64,74,000 $83,00,000 78.00% $1,00,00,000 $78,00,000 $48,00,000 $8,16,000
2023 $20,08,600 $84,82,600 $84,82,600 100.00% $1,00,00,000 $1,00,00,000 $22,00,000 $1,91,400
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600 Estimated costs to complete as of year-end 5,810,000 1,826,000 0 Billings during the year 2,030,000 4,444,000 3,526,000 Cash collections during the year 1,815,000 3,900,000 4,285,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600 Estimated costs to complete as of year-end 5,810,000 1,826,000 0 Billings during the year 2,030,000 4,444,000 3,526,000 Cash collections during the year 1,815,000 3,900,000 4,285,000 Westgate recognizes revenue over time according to...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600 Estimated costs to complete as of year-end 5,810,000 1,826,000 0 Billings during the year 2,030,000 4,444,000 3,526,000 Cash collections during the...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600 Estimated costs to complete as of year-end 5,810,000 1,826,000 0 Billings during the year 2,030,000 4,444,000 3,526,000 Cash collections during the...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600 Estimated costs to complete as of year-end 5,810,000 1,826,000 0 Billings during the year 2,030,000 4,444,000 3,526,000 Cash collections during the...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,072,000 $ 2,738,000 $ 2,849,000 Estimated costs to complete as of year-end 5,328,000 2,590,000 0 Billings during the year 2,160,000 2,650,000 5,190,000 Cash collections during the year 1,880,000 2,700,000 5,420,000 Westgate recognizes revenue over time according to...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,604,000 $ 4,032,000 $ 1,940,400 Estimated costs to complete as of year-end 5,796,000 1,764,000 0 Billings during the year 2,040,000 4,596,000 3,364,000 Cash collections during the year 1,820,000 4,000,000 4,180,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year 1,830,000 4,200,000 3,970,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,581,000 $ 2,347,000 $ 3,049,200 Estimated costs to complete as of year-end 6,319,000 2,772,000 0 Billings during the year 2,090,000 2,838,000 5,072,000 Cash collections during the year 1,845,000 2,900,000 5,255,000 Westgate recognizes revenue over time according to...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,400,000 $ 3,600,000 $ 2,200,000 Estimated costs to complete as of year-end 5,600,000 2,000,000 0 Billings during the year 2,000,000 4,000,000 4,000,000 Cash collections during the year 1,800,000 3,600,000 4,600,000 Westgate recognizes revenue over time according to...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT