In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,581,000 $ 2,347,000 $ 3,049,200 Estimated costs to complete as of year-end 6,319,000 2,772,000 0 Billings during the year 2,090,000 2,838,000 5,072,000 Cash collections during the year 1,845,000 2,900,000 5,255,000 Westgate recognizes revenue over time according to percentage of completion.
1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. (Do not round intermediate calculations. Loss amounts should be indicated with a minus sign.)
Total Estimated Revenue = 10000000
2017 |
2018 |
2019 |
|
Cost incurred to date (A) |
2581000 |
(2581000 + 2347000) =4928000 |
(3049200 + 4928000) =7977200 |
Estimated cost (B) |
6319000 |
2772000 |
0 |
Estimated Total cost (C = A+B) |
8902017 |
7700000 |
7977200 |
% complete (D=A/C) |
29% |
64% |
100% |
Billings |
2090000 |
2838000 |
5072000 |
Cash collected |
1845000 |
2900000 |
5255000 |
Revenue Recognised (E) |
(10000000 * 29%) 2900000 |
(10000000 * 64%) 6400000 |
(10000000 * 100%) 10000000 |
Total Income/Loss recognized (E – A) |
319000 |
1472000 |
2022800 |
Income/Loss recognized this year |
319000 |
(1472000 – 319000) =1153000 |
(2022800 – 319000 – 1153000) =550800 |