Question

On June 1, 2021, Emmet Property Management entered into a 2-year contract to oversee leasing and...

On June 1, 2021, Emmet Property Management entered into a 2-year contract to oversee leasing and maintenance for an apartment building. The contract starts on July 1, 2021. Under the terms of the contract, Emmet will be paid a fixed fee of $51,000 per year and will receive an additional 10% of the fixed fee at the end of each year provided that building occupancy exceeds 80%. Emmet estimates a 25% chance it will exceed the occupancy threshold, and concludes the revenue recognition over time is appropriate for this contract. Assume that Emmet accrues revenue each month, and estimates varlable consideration as the most likely amount. On November 1, Emmet revises its estimate of the chance the building will exceed the 80% occupancy threshold to a 60% chance. What is the total amount of revenue Emmet should recognize this contract in November of 2021
6375
725
5651
6276

please show steps and explanation

Homework Answers

Answer #1
Answer
The correct option is A : $ 6,375
Explanation
Emmet should recognize $7291 on this contract in November of 2021.
Revenue to be recognised for 4 months July to October : 51000*4/12 $         17,000
From november most likely (70% chance) amount : 51000*110% $         56,100
Amount to be recognized for 5 months July to November: 56100*5/12 $         23,375
Amount to be recognized in november 23375-17000 $           6,375
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
On June 1, 2021, Royal Property Management entered into a one-year contract to oversee leasing and...
On June 1, 2021, Royal Property Management entered into a one-year contract to oversee leasing and maintenance for an apartment building. The contract starts on July 1, 2021. Under the terms of the contract, Royal will be paid a fixed fee of $60,000 and will receive an additional 10% of the fixed fee at the end of the contract provided that building occupancy exceeds 80%. Royal estimates a 25% chance it will exceed the occupancy threshold, and concludes the revenue...
Ejaaz enters into a contract offering variable consideration. The contract pays him $2000/month for six months...
Ejaaz enters into a contract offering variable consideration. The contract pays him $2000/month for six months of continuous consulting services. In addition, there is a 80% chance the contract will pay an additional $4800 and a 20% chance the contract will pay an additional $1200, depending on the outcome of the consulting contract. Ejaaz concludes that this contract qualifies for revenue recognition over time. Assume Ejaaz estimates variable consideration as the most likely amount. What is the amount of revenue...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,225,000. During 2021, costs of $2,090,000 were incurred, with estimated costs of $4,090,000 yet to be incurred. Billings of $2,608,000 were sent, and cash collected was $2,340,000. In 2022, costs incurred were $2,608,000 with remaining costs estimated to be $3,735,000. 2022 billings were $2,858,000, and $2,565,000 cash was collected. The project was completed in 2023 after additional costs of...
On January 1, Revis Consulting entered into a contract to complete a cost reduction program for...
On January 1, Revis Consulting entered into a contract to complete a cost reduction program for Green Financial over a six-month period. Revis will receive $51,200 from Green at the end of each month. If total cost savings reach a specific target, Revis will receive an additional $25,600 from Green at the end of the contract, but if total cost savings fall short, Revis will refund $25,600 to Green. Revis estimates an 80% chance that cost savings will reach the...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
On January 1, Revis Consulting entered into a contract to complete a cost reduction program for...
On January 1, Revis Consulting entered into a contract to complete a cost reduction program for Green Financial over a six-month period. Revis will receive $51,200 from Green at the end of each month. If total cost savings reach a specific target, Revis will receive an additional $25,600 from Green at the end of the contract, but if total cost savings fall short, Revis will refund $25,600 to Green. Revis estimates an 80% chance that cost savings will reach the...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,210,000. During 2021, costs of $2,070,000 were incurred with estimated costs of $4,070,000 yet to be incurred. Billings of $2,570,000 were sent, and cash collected was $2,320,000. In 2022, costs incurred were $2,570,000 with remaining costs estimated to be $3,705,000. 2022 billings were $2,820,000 and $2,545,000 cash was collected. The project was completed in 2023 after additional costs of...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
1. On November 1, 2021, Taylor signed a one-year contract to provide handyman services on an...
1. On November 1, 2021, Taylor signed a one-year contract to provide handyman services on an as-needed basis to King Associates, with the contract to start immediately. King agreed to pay Taylor $6,000 for the one-year period. Taylor is confident that King will pay that amount, but payment is not scheduled to occur until 2022. Taylor should recognize revenue in 2021 in the amount of a.$0. b. $3,000. c. $6,000. d. $1,000. 2. Harvey's Wholesale Company sold supplies of $46,000...
On 1 July 2019, Entity A entered into the Contract X with a customer, Entity B,...
On 1 July 2019, Entity A entered into the Contract X with a customer, Entity B, to sell Product A for $300 per unit. If Entity B purchases more than 1,000 units of Product A in a 12-month period, Contract X specifies that the price will be reduced to $250 per unit. Entity B agreed to settle all outstanding amount of Contract X in July 2020 when both Entities agreed with the total units of sales on 30 June 2020....