questions 1b). the workers in your company produced 25, 000GH cedis work of products this month, spending a total of 1,000 man-hours to do it, what is your company's labor productivity?
Given that 25,000 GH cedis worth of products we're produced using 1000 man hours.
Therefore, labour productivity. = GHC 25,000 / 1000
=GHC 25 per man hour