Question

The following information is available for Pharoah Company. April 1 April 30 Raw materials inventory $10,900...

The following information is available for Pharoah Company.

April 1

April 30

Raw materials inventory

$10,900 $14,500

Work in process inventory

5,360 3,170

Materials purchased in April

$97,900

Direct labor in April

79,700

Manufacturing overhead in April

160,000


Prepare the cost of goods manufactured schedule for the month of April.

PHAROAH COMPANY
Cost of Goods Manufactured Schedule

choose the accounting period                                                          For the Month Ended April 30For the Quarter Ended April 30April 30

select an item                                                          Cost of Goods ManufacturedDirect LaborDirect MaterialsDirect Materials UsedRaw Materials, April 1Raw Materials, April 30Raw Materials PurchasesTotal Cost of Work in ProcessTotal Manufacturing CostsTotal Raw Materials Available for UseWork in process, April 1Work in process, April 30

$enter a dollar amount

select an opening name for subsection one                                                          Cost of Goods ManufacturedDirect LaborDirect MaterialsDirect Materials UsedRaw Materials, April 1Raw Materials, April 30Raw Materials PurchasesTotal Cost of Work in ProcessTotal Manufacturing CostsTotal Raw Materials Available for UseWork in process, April 1Work in process, April 30

select an item                                                          Cost of Goods ManufacturedDirect LaborDirect MaterialsDirect Materials UsedRaw Materials, April 1Raw Materials, April 30Raw Materials PurchasesTotal Cost of Work in ProcessTotal Manufacturing CostsTotal Raw Materials Available for UseWork in process, April 1Work in process, April 30

$enter a dollar amount

select an item                                                          Cost of Goods ManufacturedDirect LaborDirect MaterialsDirect Materials UsedRaw Materials, April 1Raw Materials, April 30Raw Materials PurchasesTotal Cost of Work in ProcessTotal Manufacturing CostsTotal Raw Materials Available for UseWork in process, April 1Work in process, April 30

enter a dollar amount

select an item                                                          Cost of Goods ManufacturedDirect LaborDirect MaterialsDirect Materials UsedRaw Materials, April 1Raw Materials, April 30Raw Materials PurchasesTotal Cost of Work in ProcessTotal Manufacturing CostsTotal Raw Materials Available for UseWork in process, April 1Work in process, April 30

enter a subtotal of the two previous amounts

select between addition and deduction                                                          AddLess: select an item                                                           Cost of Goods ManufacturedDirect LaborDirect MaterialsDirect Materials UsedRaw Materials, April 1Raw Materials, April 30Raw Materials PurchasesTotal Cost of Work in ProcessTotal Manufacturing CostsTotal Raw Materials Available for UseWork in process, April 1Work in process, April 30

enter a dollar amount

select a closing name for subsection one                                                          Cost of Goods ManufacturedDirect LaborDirect MaterialsDirect Materials UsedRaw Materials, April 1Raw Materials, April 30Raw Materials PurchasesTotal Cost of Work in ProcessTotal Manufacturing CostsTotal Raw Materials Available for UseWork in process, April 1Work in process, April 30

$enter a total amount for subsection one

select an item                                                          Cost of Goods ManufacturedDirect LaborDirect MaterialsDirect Materials UsedRaw Materials, April 1Raw Materials, April 30Raw Materials PurchasesTotal Cost of Work in ProcessTotal Manufacturing CostsTotal Raw Materials Available for UseWork in process, April 1Work in process, April 30

enter a dollar amount

select an item                                                          Cost of Goods ManufacturedDirect LaborDirect MaterialsDirect Materials UsedManufacturing OverheadRaw Materials, April 1Raw Materials, April 30Raw Materials PurchasesTotal Cost of Work in ProcessTotal Manufacturing CostsTotal Raw Materials Available for UseWork in process, April 1Work in process, April 30

enter a dollar amount

select a closing name for section one                                                          Cost of Goods ManufacturedDirect LaborDirect MaterialsDirect Materials UsedManufacturing OverheadRaw Materials, April 1Raw Materials, April 30Raw Materials PurchasesTotal Cost of Work in ProcessTotal Manufacturing CostsTotal Raw Materials Available for UseWork in process, April 1Work in process, April 30

enter a total amount for section one

select a summarizing line for this part of the statement                                                          Cost of Goods ManufacturedDirect LaborDirect MaterialsDirect Materials UsedManufacturing OverheadRaw Materials, April 1Raw Materials, April 30Raw Materials PurchasesTotal Cost of Work in ProcessTotal Manufacturing CostsTotal Raw Materials Available for UseWork in process, April 1Work in process, April 30

enter a subtotal for this part of the statement

select between addition and deduction                                                          AddLess: select an item                                                           Cost of Goods ManufacturedDirect LaborDirect MaterialsDirect Materials UsedManufacturing OverheadRaw Materials, April 1Raw Materials, April 30Raw Materials PurchasesTotal Cost of Work in ProcessTotal Manufacturing CostsTotal Raw Materials Available for UseWork in process, April 1Work in process, April 30

enter a dollar amount

select a closing name for this statement                                                          Cost of Goods ManufacturedDirect LaborDirect MaterialsDirect Materials UsedManufacturing OverheadRaw Materials, April 1Raw Materials, April 30Raw Materials PurchasesTotal Cost of Work in ProcessTotal Manufacturing CostsTotal Raw Materials Available for UseWork in process, April 1Work in process, April 30

$enter a total amount for this statement

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The following information is available for Rolen Manufacturing Company. April 1 April 30 Raw materials inventory...
The following information is available for Rolen Manufacturing Company. April 1 April 30 Raw materials inventory $10,000 $14,000 Work in process inventory 5,000 3,500 Materials purchased in April $98,000 Direct labour in April 60,000 Manufacturing overhead in April 180,000 Prepare the cost of goods manufactured schedule for the month of April. ROLEN MANUFACTURING COMPANY Cost of Goods Manufactured Schedule For the Month Ended April 30 select an item                                       ...
The following information is available for Sunland Company. April 1 April 30 Raw materials inventory $10,300...
The following information is available for Sunland Company. April 1 April 30 Raw materials inventory $10,300 $14,100 Work in process inventory 4,950 3,740 Materials purchased in April $98,000 Direct labor in April 79,800 Manufacturing overhead in April 160,000 Prepare the cost of goods manufactured schedule for the month of April. SUNLAND COMPANY Cost of Goods Manufactured Schedule For the Quarter Ended April 30For the Month Ended April 30April 30 Cost of Goods ManufacturedDirect LaborDirect MaterialsDirect Materials UsedRaw Materials, April 1Raw...
Inventory Beginning Ending Raw materials $9,110 $14,750 Work in process 6,800 8,470 Finished goods 9,350 6,700...
Inventory Beginning Ending Raw materials $9,110 $14,750 Work in process 6,800 8,470 Finished goods 9,350 6,700 Costs incurred: raw materials purchases $55,260, direct labor $48,920, manufacturing overhead $23,050. The specific overhead costs were: indirect labor $6,340, factory insurance $4,510, machinery depreciation $4,900, machinery repairs $1,930, factory utilities $3,610, and miscellaneous factory costs $1,760. Assume that all raw materials used were direct materials. (a) Prepare the cost of goods manufactured schedule for the month ended June 30, 2020. ROBERTS COMPANY Cost...
The following information is available for Tomlin Company. April 1 April 30 Raw materials inventory $10,000...
The following information is available for Tomlin Company. April 1 April 30 Raw materials inventory $10,000 $13,500 Work in process inventory 4,500 3,000 Materials purchased in April $97,500 Direct labor in April 79,500 Manufacturing overhead in April 155,000 Prepare the cost of goods manufactured schedule for the month of April.
The following information is available for Tomlin Company. April 1 April 30 Raw materials inventory $10,300...
The following information is available for Tomlin Company. April 1 April 30 Raw materials inventory $10,300 $13,900 Work in process inventory 4,930 3,850 Materials purchased in April $98,500 Direct labor in April 79,900 Manufacturing overhead in April 162,000 Prepare the cost of goods manufactured schedule for the month of April.
Gundy Company expects to produce 1,275,600 units of Product XX in 2020. Monthly production is expected...
Gundy Company expects to produce 1,275,600 units of Product XX in 2020. Monthly production is expected to range from 84,000 to 122,000 units. Budgeted variable manufacturing costs per unit are: direct materials $5, direct labor $8, and overhead $10. Budgeted fixed manufacturing costs per unit for depreciation are $5 and for supervision are $1. In March 2020, the company incurs the following costs in producing 103,000 units: direct materials $544,000, direct labor $815,000, and variable overhead $1,038,000. Actual fixed costs...
Gundy Company expects to produce 1,220,400 units of Product XX in 2020. Monthly production is expected...
Gundy Company expects to produce 1,220,400 units of Product XX in 2020. Monthly production is expected to range from 73,000 to 115,000 units. Budgeted variable manufacturing costs per unit are: direct materials $4, direct labor $7, and overhead $9. Budgeted fixed manufacturing costs per unit for depreciation are $5 and for supervision are $3. In March 2020, the company incurs the following costs in producing 94,000 units: direct materials $400,000, direct labor $652,000, and variable overhead $850,000. Actual fixed costs...
Do it! Review 14-3 The following information is available for Tomlin Company. April 1 April 30...
Do it! Review 14-3 The following information is available for Tomlin Company. April 1 April 30 Raw materials inventory $10,000 $14,000 Work in process inventory 5,000 3,500 Materials purchased in April $98,000 Direct labor in April 80,000 Manufacturing overhead in April 160,000 Prepare the cost of goods manufactured schedule for the month of April. TOMLIN COMPANY Cost of Goods Manufactured Schedule $ $ : $ : $
The following information is available for Murray Manufacturing at year-end: Beginning raw materials inventory 6,000 Ending...
The following information is available for Murray Manufacturing at year-end: Beginning raw materials inventory 6,000 Ending raw materials inventory $8,000 Materials purchased 13,000 Direct labour 4,000 Manufacturing overhead Applied 15,000 Beginning work in process inventory 8,000 Ending working in process inventory 5,000 What was the cost of goods manufactured during the period? Select one: a. $16,000 b. $35,000 c. $28,000 d. $33,000
Presented below is information for Pharoah Company for the month of January 2022. Cost of goods...
Presented below is information for Pharoah Company for the month of January 2022. Cost of goods sold $218,125 Rent expense $33,000 Freight-out 7,000 Sales discounts 8,000 Insurance expense 12,000 Sales returns and allowances 20,000 Salaries and wages expense 57,000 Sales revenue 377,000 Other comprehensive income 2,100 (a) Prepare a multiple-step income statement. (If there is a net loss then enter the amount using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).) Pharoah Company Income Statement...