Inventory Beginning Ending Raw materials $9,110 $14,750 Work in process 6,800 8,470 Finished goods 9,350 6,700...

Inventory

Beginning

Ending

Raw materials $9,110 $14,750
Work in process 6,800 8,470
Finished goods 9,350 6,700


Costs incurred: raw materials purchases $55,260, direct labor $48,920, manufacturing overhead $23,050. The specific overhead costs were: indirect labor $6,340, factory insurance $4,510, machinery depreciation $4,900, machinery repairs $1,930, factory utilities $3,610, and miscellaneous factory costs $1,760. Assume that all raw materials used were direct materials.

(a) Prepare the cost of goods manufactured schedule for the month ended June 30, 2020.

ROBERTS COMPANY
Cost of Goods Manufactured Schedule

                                                          For the Month Ended June 30, 2020June 30, 2020For the Year Ended June 30, 2020

                                                          Cost of Goods ManufacturedDirect LaborDirect MaterialsDirect Materials UsedFactory InsuranceFactory UtilitiesIndirect LaborMachinery DepreciationMachinery RepairsManufacturing OverheadMiscellaneous Factory CostsRaw Materials Inventory, June 1Raw Materials Inventory, June 30Raw Materials PurchasesTotal Cost of Work in ProcessTotal Manufacturing CostsTotal Manufacturing OverheadTotal Raw Materials Available for UseWork in Process Inventory, June 1Work in Process Inventory, June 30Finished Goods Inventory, June 1Finished Goods Inventory, June 30

$

$

                                                          AddLess:                                                           Cost of Goods ManufacturedDirect LaborDirect MaterialsDirect Materials UsedFactory InsuranceFactory UtilitiesIndirect LaborMachinery DepreciationMachinery RepairsManufacturing OverheadMiscellaneous Factory CostsRaw Materials Inventory, June 1Raw Materials Inventory, June 30Raw Materials PurchasesTotal Cost of Work in ProcessTotal Manufacturing CostsTotal Manufacturing OverheadTotal Raw Materials Available for UseWork in Process Inventory, June 1Work in Process Inventory, June 30Finished Goods Inventory, June 1Finished Goods Inventory, June 30

$

$

                                                          AddLess:                                                           Cost of Goods ManufacturedDirect LaborDirect MaterialsDirect Materials UsedFactory InsuranceFactory UtilitiesIndirect LaborMachinery DepreciationMachinery RepairsManufacturing OverheadMiscellaneous Factory CostsRaw Materials Inventory, June 1Raw Materials Inventory, June 30Raw Materials PurchasesTotal Cost of Work in ProcessTotal Manufacturing CostsTotal Manufacturing OverheadTotal Raw Materials Available for UseWork in Process Inventory, June 1Work in Process Inventory, June 30Finished Goods Inventory, June 1Finished Goods Inventory, June 30

$

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The following information is available for Pharoah Company. April 1 April 30 Raw materials inventory $10,900...
The following information is available for Pharoah Company. April 1 April 30 Raw materials inventory $10,900 $14,500 Work in process inventory 5,360 3,170 Materials purchased in April $97,900 Direct labor in April 79,700 Manufacturing overhead in April 160,000 Prepare the cost of goods manufactured schedule for the month of April. PHAROAH COMPANY Cost of Goods Manufactured Schedule choose the accounting period                                                          For...
The following information is available for Sunland Company. April 1 April 30 Raw materials inventory $10,300...
The following information is available for Sunland Company. April 1 April 30 Raw materials inventory $10,300 $14,100 Work in process inventory 4,950 3,740 Materials purchased in April $98,000 Direct labor in April 79,800 Manufacturing overhead in April 160,000 Prepare the cost of goods manufactured schedule for the month of April. SUNLAND COMPANY Cost of Goods Manufactured Schedule For the Quarter Ended April 30For the Month Ended April 30April 30 Cost of Goods ManufacturedDirect LaborDirect MaterialsDirect Materials UsedRaw Materials, April 1Raw...
The following information is available for Rolen Manufacturing Company. April 1 April 30 Raw materials inventory...
The following information is available for Rolen Manufacturing Company. April 1 April 30 Raw materials inventory $10,000 $14,000 Work in process inventory 5,000 3,500 Materials purchased in April $98,000 Direct labour in April 60,000 Manufacturing overhead in April 180,000 Prepare the cost of goods manufactured schedule for the month of April. ROLEN MANUFACTURING COMPANY Cost of Goods Manufactured Schedule For the Month Ended April 30 select an item                                       ...
Required information The following selected account balances are provided for Delray Mfg. Sales $ 1,250,000 Raw...
Required information The following selected account balances are provided for Delray Mfg. Sales $ 1,250,000 Raw materials inventory, Dec. 31, 2016 37,000 Work in process inventory, Dec. 31, 2016 53,900 Finished goods inventory, Dec. 31, 2016 62,750 Raw materials purchases 175,600 Direct labor 225,000 Factory computer supplies used 17,840 Indirect labor 47,000 Repairs—Factory equipment 5,250 Rent cost of factory building 57,000 Advertising expense 94,000 General and administrative expenses 129,300 Raw materials inventory, Dec. 31, 2017 42,700 Work in process inventory,...
An incomplete cost of goods manufactured schedule is presented below. Complete the cost of goods manufactured...
An incomplete cost of goods manufactured schedule is presented below. Complete the cost of goods manufactured schedule for Lily Company. LILY COMPANY Cost of Goods Manufactured Schedule December 31, 2020For the Month Ended December 31, 2020For the Year Ended December 31, 2020 Work in process (1/1) $216,130 Direct materials    Raw materials inventory (1/1) $    Add: Raw materials purchases 165,710    Total raw materials available for use    Less: Raw materials inventory (12/31) 30,350 Direct materials used $189,120 Direct labor Manufacturing overhead    Indirect...
1. Raw Materials Inventory, Jan 1 $75,000 Raw Materials Inventory, Dec 31 $30,000 Work in Process...
1. Raw Materials Inventory, Jan 1 $75,000 Raw Materials Inventory, Dec 31 $30,000 Work in Process Inventory, Jan 1 $105,000 Work in Process Inventory, Dec 31 $75,000 Finished Goods Inventory, Jan 1 $25,000 Finished Goods Inventory, Dec 31 $130,000 Material Purchases $65,000 Direct Labor $150,000 Indirect Labor $10,000 Factory Utilities $25,000 Factory Supplies $5,000 Factory Rent $95,000 Depreciation on Office Building $15,000 a. Direct Materials Used b. Factory Overhead c. Cost of Goods Manufactured d. Cost of Goods Sold
Inventory type Raw materials Work in process Finished goods   Balance, 4/1/18 300,000 2,650,000 4,000,000 Balance, 4/30/18...
Inventory type Raw materials Work in process Finished goods   Balance, 4/1/18 300,000 2,650,000 4,000,000 Balance, 4/30/18 320,000 1,080,000 3,830,000 Amounts spent during April    Raw material purchases 1,650,000    Direct labor wages 9,000,000    Overhead      Indirect materials purchased 477,000      Indirect labor 2,700,000      Factory utilities 1,608,000      Factory depreciation 920,000 What is cost of goods manufactured for April? What is cost of goods sold for April?
Oriole Company reported the following year-end information: Beginning work in process inventory $1080000 Beginning raw materials...
Oriole Company reported the following year-end information: Beginning work in process inventory $1080000 Beginning raw materials inventory 300000 Ending work in process inventory 900000 Ending raw materials inventory 480000 Raw materials purchased 910000 Direct labor 820000 Manufacturing overhead 670000 Oriole Company's cost of goods manufactured for the year is $2220000. $2040000. $2400000. $2580000.
The following information was extracted from Manuco.'s financial documents. Beginning raw materials inventory $55,000 Ending raw...
The following information was extracted from Manuco.'s financial documents. Beginning raw materials inventory $55,000 Ending raw materials inventory $29,000 Beginning work-in-process inventory $23,000 Ending work-in-process inventory $60,000 Beginning finished goods inventory $30,000 Ending finished goods inventory $55,000 Raw materials purchased during the period $86,000 Total direct labor cost during the period $76,000 Total factory overhead cost during the period $18,000 Assuming that all raw materials are direct materials, calculate the cost of raw materials requisitioned, cost of goods manufactured, and...
The following information is available for Murray Manufacturing at year-end: Beginning raw materials inventory 6,000 Ending...
The following information is available for Murray Manufacturing at year-end: Beginning raw materials inventory 6,000 Ending raw materials inventory $8,000 Materials purchased 13,000 Direct labour 4,000 Manufacturing overhead Applied 15,000 Beginning work in process inventory 8,000 Ending working in process inventory 5,000 What was the cost of goods manufactured during the period? Select one: a. $16,000 b. $35,000 c. $28,000 d. $33,000
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT