X Company's 2019 budgeted overhead cost function was C=$9.30X +
$195,700, where X is the number of units produced. The following
information is also available for 2019:
|
Master |
Actual |
|
Budget |
Results |
Production |
11,000 units |
13,800 units |
Total variable costs |
$102,300 |
$164,495 |
Total fixed costs |
$195,700 |
$198,143 |
1. What was the total overhead static budget for 2019?
A: $128,340 |
B: $298,000 |
C: $300,443 |
D: $324,040 |
E: $326,483 |
F: $362,638 |
2. What was the total overhead flexible budget variance for 2019 [a
positive number means a favorable variance and a negative number
means an unfavorable variance]?
A: $-64,638 |
B: $-62,195 |
C: $-46,318 |
D: $-38,598 |
E: $-36,155 |
F: $-30,878 |