Data Mning is a company that produces and designs data analysis softwares for various large business corporations. Due to strong growth in Data Science and Big Data company’s staffs are overloaded with design and development of new softwares. A new project is due in
99
months. The penalty for completing the project late is
$13 comma 00013,000
per month, since any delay will cause the customers (client corporations) significant revenue loss. If Data Mining uses its own software engineers it will cost them
$10 comma 00010,000
per month (wages and overhead), including late months, to complete the project. Data Mining is also considering having an outside firm complete the project. A bid of
$82 comma 00082,000
has been received for the completed project. Third option for completing the project is to conduct a joint project by having a third software company complete all statistical analytics components of the project at a cost of
$52 comma 00052,000.
Data Mining would then complete the rest of the project at an estimated cost of
$32 comma 00032,000.
They have estimated the following probabilities of completing the project within various time frames when using each of the three options. The estimates are shown in the following table below:
Probability of Completing the Project |
||||
Option |
On Time |
One month late |
Two
months late |
Three
months late |
Internal Engineers |
0.30.3 |
0.50.5 |
0.20.2 |
long dash— |
External Firm |
0.20.2 |
0.40.4 |
0.30.3 |
0.10.1 |
Joint Project Design |
0.10.1 |
0.40.4 |
0.30.3 |
0.20.2 |
The expected monetary value using internal software workers to complete the project is
$nothing.
(Enter
your response as an
integer.)
The expected monetary value using an outside (extrenal) firm to complete the project is
$nothing.
(Enter
your response as an
integer.)
The expected monetary value of conducting a joint project design is
$nothing.
(Enter
your response as an
integer.)
What is the best decision based on an expected monetary value criterion?
Joint designJoint design
External engineering firm External engineering firm
Internal engineers