Henrique Correa's bakery prepares all its cakes between 4 A.M.and 6 A.M.so they will be fresh when customers arrive. Day-old cakes are virtually always sold, but at a 50% discount off the regular $16 price. The cost of baking a cake is $10, and demand is estimated to be normally distributed, with a mean of 25 and a standard deviation of 7. What is the optimal stocking level? Refer to the standard normal table LOADING... for z-values.
The optimal stocking level for the bakery is
nothing cakes (round your response to the nearest whole number).
Z
0.00
0.01
0.02
0.5000
0.5040
0.5080
0.5120
0.5160
0.5199
0.5239
0.5279
0.5319
0.5359
0.1
0.5398
0.5438
0.5478
0.5517
0.5557
0.5596
0.5636
0.5675
0.5714
0.5754
0.2
0.5793
0.5832
0.5871
0.5910
0.5948
0.5987
0.6026
0.6064
0.6103
0.6141
0.3
0.6179
0.6217
0.6255
0.6293
0.6331
0.6368
0.6406
0.6443
0.6480
0.6517
0.4
0.6554
0.6591
0.6628
0.6664
0.6700
0.6736
0.6772
0.6808
0.6844
0.6879
0.5
0.6915
0.6950
0.6985
0.7019
0.7054
0.7088
0.7123
0.7157
0.7190
0.7224
0.6
0.7258
0.7291
0.7324
0.7357
0.7389
0.7422
0.7454
0.7486
0.7518
0.7549
0.7
0.7580
0.7612
0.7642
0.7673
0.7704
0.7734
0.7764
0.7794
0.7823
0.7852
0.8
0.7881
0.7910
0.7939
0.7967
0.7996
0.8023
0.8051
0.8079
0.8106
0.8133
0.9
0.8159
0.8186
0.8212
0.8238
0.8264
0.8289
0.8315
0.8340
0.8365
0.8389
1.0
0.8413
0.8438
0.8461
0.8485
0.8508
0.8531
0.8554
0.8577
0.8599
0.8621
1.1
0.8643
0.8665
0.8686
0.8708
0.8729
0.8749
0.8770
0.8790
0.8810
0.8830
1.2
0.8849
0.8869
0.8888
0.8907
0.8925
0.8944
0.8962
0.8980
0.8997
0.9015
1.3
0.9032
0.9049
0.9066
0.9082
0.9099
0.9115
0.9131
0.9147
0.9162
0.9177
1.4
0.9192
0.9207
0.9222
0.9236
0.9251
0.9265
0.9279
0.9292
0.9306
0.9319
1.5
0.9332
0.9345
0.9357
0.9370
0.9382
0.9394
0.9406
0.9418
0.9430
0.9441
1.6
0.9452
0.9463
0.9474
0.9485
0.9495
0.9505
0.9515
0.9525
0.9535
0.9545
1.7
0.9554
0.9564
0.9573
0.9582
0.9591
0.9599
0.9608
0.9616
0.9625
0.9633
1.8
0.9641
0.9649
0.9656
0.9664
0.9671
0.9678
0.9686
0.9693
0.9700
0.9706
1.9
0.9713
0.9719
0.9726
0.9732
0.9738
0.9744
0.9750
0.9756
0.9762
0.9767
2.0
0.9773
0.9778
0.9783
0.9788
0.9793
0.9798
0.9803
0.9808
0.9812
0.9817
2.1
0.9821
0.9826
0.9830
0.9834
0.9838
0.9842
0.9846
0.9850
0.9854
0.9857
2.2
0.9861
0.9865
0.9868
0.9871
0.9875
0.9878
0.9881
0.9884
0.9887
0.9890
2.3
0.9893
0.9896
0.9898
0.9901
0.9904
0.9906
0.9909
0.9911
0.9913
0.9916
2.4
0.9918
0.9920
0.9922
0.9925
0.9927
0.9929
0.9931
0.9932
0.9934
0.9936
2.5
0.9938
0.9940
0.9941
0.9943
0.9945
0.9946
0.9948
0.9949
0.9951
0.9952
2.6
0.9953
0.9955
0.9956
0.9957
0.9959
0.9960
0.9961
0.9962
0.9963
0.9964
2.7
0.9965
0.9966
0.9967
0.9968
0.9969
0.9970
0.9971
0.9972
0.9973
0.9974
2.8
0.9974
0.9975
0.9976
0.9977
0.9977
0.9978
0.9979
0.9980
0.9980
0.9981
2.9
0.9981
0.9982
0.9983
0.9983
0.9984
0.9984
0.9985
0.9985
0.9986
0.9986
3.0
0.9987
0.9987
0.9987
0.9988
0.9988
0.9989
0.9990
0.9989
0.9990
0.9990
This problem will be solved using Newsvendor model
Given are following data :
Average demand = m = 25
Standard deviation of demand = Sd = 7
Sale price = P = $16/ unit
Cost of cake = C = $10 / unit
Salvage price = S = 50% of $16 = $8 / unit
Thus ,
Cost of underordering = Cu = P – C = $16 - $10 = $6 / unit
Cost of overordering = Co = C – S = $ 10 - $ 8 = $ 2/ unit
Therefore,
Critical ratio = Cu/ ( Cu + Co) = 6/ ( 6 + 2) = 6/8 = 0.75
Critical ratio is the probability of optimum stocking level . Corresponding Z value for such optimum stocking level = NORMSINV ( 0.75 ) = 0.6745
Therefore , Optimum stocking level for the Bakery
= m + Z x Sd
= 25 + 0.6745x 7
= 25 + 4.72
= 29.72 ( 30 rounding to next higher whole number )
OPTIMUM STOCKING LEVEL FOR THE BAKERY = 30