6. Supplier Performance Measurement and Evaluation[EM1] [EM2] [EM3] System This question is worth a total of 12 points. You are Supplier Manager for Cuyahoga River Valley Aerospace (CRVA). This fictitious manufacturer is an Electra/Hydra/Mechanical company that provides major assemblies for both commercial and defense aircraft prime contractors. CRVA is headquartered in Cleveland, Ohio, and has plants in several cities and states. Each month CRVA provides its suppliers with a Supplier Performance Report. Your team has just received reports from two suppliers. The report is based upon the following performance criteria applicable to all CRVA suppliers
Performance Rating Criteria, Twelve Month Rolling Average
Quality |
Performance Level |
Delivery |
100% |
Gold |
100% |
99% - 99.9% |
Silver |
98% - 99.9% |
98% - 98.9% |
Bronze |
95% - 97.9% |
97% - 97.9% |
Yellow – Needs help |
91.0% - 94.9% |
96.9% and below |
Red – unacceptable |
90.9% and below |
Notes:
1) Quality performance measures total defects divided by actual deliveries in a given period.
2) On-time delivery performance measures in a given period the actual “on dock delivery dates” to the contract commitment date and shows late quantity and days variance to contract dates.
3) When applicable performance data on specific supplier part numbers is provided to a supplier for quality and delivery issues.
Your task is to review these two supplier performance reports shown below for Bent Scepter Mechanical (6-A) and for Delta Machining (6-B) and to answer the following three questions for each supplier:
What is the message of the above performance report?
What questions will you ask the supplier about the report?
What will your team’s next actions be with the supplier?
6-A) The total CRVA performance rating for Bent Scepter is shown below along with additional specific delivery performance data. (6 Points)
Supplier Performance Rating for Bent Scepter Mechanical
Syracuse, New York
For Period March 2018
Business Type Rating |
Quality Quantity Received/rejected / % |
Delivery Quantity Received/on-time / % |
Total Cuyahoga rating |
44 / 0 – 100% |
50 / 44 – 88% |
Commercial rating |
- 0- |
- 0 - |
Defense rating |
44 / 0 – 100% |
50 / 44 – 88% |
Miscellaneous rating |
- 0 - |
- 0 - |
Early/Late Delivery Detail
To the CRVA Cleveland OH Location
For Bent Scepter
|
1)
2)
3)
6-B) The total CRVA performance rating for Delta Machining is shown below along with additional specific delivery performance data. (6 Points)
Supplier Performance Report for Delta Machining
Dayton, Ohio
For Period March 2018
Business Type Rating |
Quality Quantity Received/rejected / % |
Delivery Quantity Received/on-time / % |
Total Cuyahoga rating |
38,630 / 132 – 99.7% |
39120 / 37438 – 95.7% |
Commercial rating |
952 / 5 – 99.5% |
936 / 866 – 92.52% |
Defense rating |
37,678 / 127 – 99.7% |
38,184 / 36,572 – 95.8% |
Miscellaneous rating |
0 - |
-0 - |
Additional Performance Data for delivery and quality:
Supplier Site Performance Report for Delta Machining
For Defense CRVA Site Memphis TN
For Period March 2018
Memphis Site Rating |
Quality Quantity Received/rejected / % |
Delivery Quantity Received/on-time / % |
Defense Rating |
82/4 – 95.1% |
82/75 – 91.4% |
Early/Late Delivery Detail
To CRVA Memphis TN Location
For Delta Machining
Part Number |
PO/Line # |
Date Contract Required |
Early Quantity |
Late Quantity |
Days Variance |
57759-1 |
S7676/001 |
22 Mar 2018 |
5 |
-9 |
|
57759-1 |
S7676/001 |
20 Feb 2018 |
1 |
-40 |
|
57759-1 |
S7676/001 |
19 Jan 2018 |
1 |
-70 |
Quality Nonconformance Detail
To the CRVA Memphis TN Location
For Delta Machining
Part Number |
Rejected Quantity |
Nonconformance Document No. |
Nonconformance Date |
PO/Line Item |
Received Quantity |
57759-1 |
2 |
42-2011 |
15 Mar 2018 |
S7676/001 |
0 |
57759-1 |
1 |
33-2011 |
19 Feb 2018 |
S7676/001 |
0 |
57759-1 |
1 |
22-2011 |
19 Jan 2018 |
S7676/001 |
0 |
1)
2)
3)
Bent Scepter Mechanical:
What is the message of the above performance report?
The delivery against the order was 88% which is not acceptable but the quality was 100% as per our laid parameters. The delay in receipt was by 1 day but it impacts our production schedule which relies heavily on timely supplies. We see a consistent dealy pattern which indicates a system problem.
What questions will you ask the supplier about the report?
Our questions are as follows:
What will your team’s next actions be with the supplier?
In future, we will give less order to the supplier as he seems to have an issue with the production capacity as they are consistently delivering 12% less quantity. Though we notice, his quality is good. We will study his future deliveries and if he repeats same performance, we will reduce the number of orders assigned to him.
Delta Machining
What is the message of the above performance report?
Delta is a much bigger supplier and achieves almost 95% accuracy on-time delivery which is just meeting our standards. We must push him to give on-time deliveries. Further delay in delivery is also quite high in case of order no S7676/001 dated January 19, 2018, it was delayed by 70 days and another order of the same part was delayed by 40 days. The organization cannot take this kind of delay. There is a quality rejection of 3-4 %, which is again on the border of our acceptable levels. In the case of or Memphis site delivery was 91.4% on time which is unacceptable and out of quantity delivered 95.1% was acceptable I,e, just borderline quality acceptance. We need to start looking for an alternate supplier too.
What questions will you ask the supplier about the report?
We will ask following questions from Delta:
What will your team’s next actions be with the supplier?
Delta needs to upgrade their quality processes and on-site checking systems to meet our acceptable standards. Further, we cannot take the delay in supplies as they are a big supplier and delay put a stop to our product line, causing a huge loss in production and underutilization of manufacturing facilities. It is creating inefficiencies in our system. Delays are also of long duration and the rejection rates are high and they need to address it immediately. We need to assign a quality check system at their manufacturing base.