Consider the following table of activities A through E in which A is the start node and E is the stop node. Assume the project starts on Monday, May 4, 2020 and no work is done on weekends (Saturday and Sunday).
Activity | Duration (days) | Predecessor |
A | 5 | -- |
B | 5 | A |
C | 10 | A |
D | 4 | A |
E | 5 | B, C, D |
On a piece of scratch paper, draw the Gantt Chart for the table above. What is the late start date for activity E?
Monday, May 18, 2020
Tuesday, May 19, 2020
Friday, May 22, 2020
Tuesday, May 26, 2020
Monday, May 25, 2020
Gantt chart is as below:
Activities B, C and D are dependent on A. So, as soon as A gets completed, all three gets started.
Activity E is dependent on B, C and D so it will start as soon as all three gets completed. The longest duration is of B so E will start after B is completed
E starts on 25th May Monday
Ans - Monday, May 25, 2020