Question

This basic information applies to all of the related questions: Alpha Assemblies produces a wide variety...

This basic information applies to all of the related questions:

Alpha Assemblies produces a wide variety of products in their central Nebraska facility. Many of these products fit within a line of standard truck and trailer parts. Within this is a set of hitches that can be made in two sizes (1-1/4 and 2) and three strengths (light duty, medium duty, and heavy duty). All of the hitches in this line have "natural" finishes so no additional steps are necessary after they are cast. The machine used to cast these six hitch variations is available for 2000 hours per year. Operators are paid $15.00 per hour including benefits.

Simone is working to establish her reputation at Alpha Assemblies as part of her internship opportunity. She is looking for a way to improve the operations. She has been working on the hitch project and is looking at possible ways to cut costs. At this point she has studied the processes and their associated costs, and completed forecasts for the next year's demand.

Hitch G is the 2 inch, heavy duty, natural hitch.

After discussions with the production manager, Simone has come to realize that her assumption on EOQ is not appropriate. Since EOQ is designed for situations where all of the inventory shows up all at once, which would often be the case for a purchased items and in some cases for manufactured items when everything must move forward as a full batch, and the situation here is that each item may move into inventory as soon as it comes out of production (without waiting for the other items) EOQ with gradual deliveries (sometimes called Economic Run Length (ERL) or Economic Production Quantity (EPQ), among other things) would be more appropriate.

The forecast annual demand for next year of Hitch G is 9,400 and the current batch size is 2,000 units. It takes 0.0480 hours to produce each Hitch G. The setup time is 6.6 hours per setup conducted by a single operator with no other setup costs incurred. The holding cost is $1.81 per unit per year. Production and demand both occur 250 days per year. The facility operates 8 hours per day.

What is the recommended batch size using EOQ with Gradual Deliveries (ERL, EPQ)?

Hint: This isn't in the book, it will take some extra digging.

Don't round any numbers in the middle of the problem. Provide your answer to two (2) decimal places.

Homework Answers

Answer #1

Current scenario

No. of batches needed to complete the demand = 9400/2000 = 5

Time taken to produce a batch = 6.6+ 2000 x0.048 hours = 102.6 hours

Time taken to produce entire quantity = 4x102.6 + 6.6 x 1400 x0.048 = 410.4+443.52 = 853.52

Number of days needed to complete this order = 853.52/8 = 107, which is far less than the given time of 250 days

as there is no set up cost involved, the holding cost is the only factor that needs to be minimised

If n be the ERL, then, no. of runs needed = 9400/n

Hours incurred in each run = 6.6+0.048x n

Total hours for completing the order = 9400/n ( 6.6+0.048n) = 250x8

62040/n+ 451.2 = 2000

n = 40.05 =41

Number of runs = 9400/41 = 230

Hence 41 units in a run will give the least holding cost i.e. 41/2 x 1.81 = 37.1

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A novelty coffee mug manufacturer produces 5 different designs that are sold at tourist information kiosks....
A novelty coffee mug manufacturer produces 5 different designs that are sold at tourist information kiosks. The demand requirements for the coming tourist season is as follows: Design A B C D E Demand (units) 500 750 600 800 450 The mugs can all be produced in the same workstations, but require different processing and setup times. The production information is in the following table: Design A B C D E Batch Size (units) 50 50 50 50 50 Setup...
1.Ford initially tried to use vertical integration to control all aspects of the production and sale...
1.Ford initially tried to use vertical integration to control all aspects of the production and sale of its automobiles. Later, Ford abandoned vertical integration and adopted a strategy of partnerships with key suppliers. The partnership arrangements were expected to cut costs for Ford but still permit the suppliers to enjoy profits at the level of the industry standard. How would it be possible for a supplier’s profits to be preserved while Ford’s costs decreased? Select one: a. Ford would agree...
PRODUCTION PLANNING AT VIKTOR LENAC SHIPYARD Professor Giorgio Sinković and Professor David M. Currie prepared this...
PRODUCTION PLANNING AT VIKTOR LENAC SHIPYARD Professor Giorgio Sinković and Professor David M. Currie prepared this case solely to provide material for class discussion. The authors do not intend to illustrate either effective or ineffective handling of a managerial situation. The authors may have disguised certain names and other identifying information to protect confidentiality. This publication may not be transmitted, photocopied, digitized, or otherwise reproduced in any form or by any means without the permission of the copyright holder. Reproduction...
Please answer the following Case analysis questions 1-How is New Balance performing compared to its primary...
Please answer the following Case analysis questions 1-How is New Balance performing compared to its primary rivals? How will the acquisition of Reebok by Adidas impact the structure of the athletic shoe industry? Is this likely to be favorable or unfavorable for New Balance? 2- What issues does New Balance management need to address? 3-What recommendations would you make to New Balance Management? What does New Balance need to do to continue to be successful? Should management continue to invest...