Question

A novelty coffee mug manufacturer produces 5 different designs that are sold at tourist information kiosks....

A novelty coffee mug manufacturer produces 5 different designs that

are sold at tourist information kiosks. The demand requirements for the coming

tourist season is as follows:

Design A B C D E

Demand (units) 500 750 600 800 450

The mugs can all be produced in the same workstations, but require different

processing and setup times. The production information is in the following

table:

Design A B C D E

Batch Size (units) 50 50 50 50 50

Setup Time (hr/batch) 2 2 2.5 4 1.5

Processing Time (hr/unit) 0.15 0.15 0.25 0.25 0.10

The company wants to produce all the required mugs in one four-week period.

It currently operates workstations that work 8 hours per day, 5 days per

week, with a capacity cushion of 20%.

(a) Calculate the total time required to produce the mugs to meet the expected

demand.

(b) Calculate the time available (taking into account the capacity cushion)

for 1 workstation.

(c) How many workstations are needed to meet the production requirements?

(d) The company only has 4 workstations available. If it only operates its 4

stations, how many weeks does it need to meet the production requirements?

(e) Operating each workstation costs the company $25/hour for a total of

$1,000 per week (including the capacity cushion). Calculate the total

operating cost to produce the mugs.

(f) Each workstation costs $2,500 to purchase and commission. If the company

acquires the extra number of workstations indicated in part (c),

what would be the cost of production?

(g) If the company has other contracts it needs to satisfy. Working on the

mugs more than 4 weeks means it will have to cancel another contract,

incurring a penalty of $4,500. What should the company do: cancel the

contract or buy the required workstations?

Homework Answers

Answer #1

The following data is provided:

Design

Demand

(Units)

Batch Size

Setup time

(Hr/Batch)

Processing Time

(hr/unit)

A 500 50 2 0.15
B 750 50 2 0.15
C 600 50 2.5 0.25
D 800 50 4 0.25
E 450 50 1.5 0.10

Work hours per day = 8 hours

Work days per week = 5 days

Capacity Cushion = 20%

Demand needs to be fulfilled in 4 weeks

Solution for (a)

No. of Batches = Demand/Batch Size

Total setup time = (Setup time * No. of Batches)

Total Processing Time = (Processing time * Demand)

Total Time Required = Total setup time + Total Processing Time

The below table contains the value arrived at using the above formula to arrive at the total time required the expected demand:

Dsign Demand Batch Size

No. of Batches

Set up Time

(hr/batch)

Total setup

time

Processing

time

(hr/unit

Total

Processing

Time

Total Time

Required

A 500 50 10 2 20 0.15 75 95
B 750 50 15 2 30 0.15 112.5 142.5
C 600 50 12 2.5 30 0.25 150 180
D 800 50 16 4 64 0.25 200 264
E 450 50 9 1.5 13.5 0.10 45 58.5

Based on the above calculations, the total time requied to produce the expected demand is:

Total Time required = Sum of total processing times for all designs = 95+142.5+180+264+58.5=740 hours

Solution for (b)

No. of Batches = Demand/Batch Size

Total setup time = (Setup time * No. of Batches)

Total Processing Time = (Processing time * Demand)

Total Time Required = Total setup time + Total Processing Time

As stated above all the formula reamins the same. However, since we are using the cushion capacity of 20%, the processing time will reduce. Now the processing time will be 20% lower, i.e.if the processing time is T, then, with the utilization of cushion capacity the new processing time will be (T/(120%))

Dsign Demand Batch Size

No. of Batches

Set up Time

(hr/batch)

Total setup

time

Processing

time

(hr/unit

Total

Processing

Time

Total Time

Required

A 500 50 10 2 20 0.13 62.5 82.5
B 750 50 15 2 30 0.13 93.8 123.8
C 600 50 12 2.5 30 0.21 125 155
D 800 50 16 4 64 0.21 166.7 230.7
E 450 50 9 1.5 13.5 0.08 37.5 51

Based on the above calculations, the total time requied to produce the expected demand using the cushion capacity is :

Total Time required = Sum of total processing times for all designs = 82.5+123.85+155+230.7+51=642.9 hours

Therefore the available time = Time required without capcity cushion - Time required with cushion = 740 - 642.9 = 97.1 hours

Solution for (c)

As given in the question, the demand needs to be met in 4 weeks. When only 1 workstation is used (without cushion), the time required is 740 hours. As given in the question, a work week consists of 5 days of 8 working hours.

Therefore the total number weeks required = 740/8/5= 18.5 weeks

If this demand is to be fulfilled in 4 weeks, then the number of work stations required are (18.5/4) = ~4.6 = 5 workstations.

Solution for (d)

If the company operates with 4 work stations(without capacity cushion) then some setups would happen in parallet indicated by "Setup rounds" column in the below table and the processing time per unit will reduce by 4 times.

Dsign Demand Batch Size

No. of Batches

Set up Time

(hr/batch)

Setup

rounds

Total setup

time

Processing

time

(hr/unit

Total

Processing

Time

Total Time

Required

A 500 50 10 2 3 20 0.0375 18.8 24.8
B 750 50 15 2 4 30 0.0375 28.1 36.1
C 600 50 12 2.5 3 30 0.0625 37.5 45
D 800 50 16 4 4 64 0.0625 50 66
E 450 50 9 1.5 3 13.5 0.025 11.25 15.8

Based on the above calculation the number of weeks required to meet the demand = (24.8+36.1+45+66+15.8)/8/5 = 4.7 weeks

Solution for (e)

Given

Cost per hour per workstation = $25

Cost per week per workstation = $1000

Please find the below calcualtion table considering the 20% capacity cushion

Dsign Demand Batch Size

No. of Batches

Set up Time

(hr/batch)

Setup

rounds

Total setup

time

Processing

time

(hr/unit

Total

Processing

Time

Total Time

Required

A 500 50 10 2 3 20 0.031 15.6 21.6
B 750 50 15 2 4 30 0.031 23.4 31.4
C 600 50 12 2.5 3 30 0.052 31.3 38.8
D 800 50 16 4 4 64 0.052 41.7 57.7
E 450 50 9 1.5 3 13.5 0.021 9.4 13.9

Total production hours required to fulfill the demand = 163.4 hours

Total cost = Rate per hour * Total production hours * No. of workstation = 25*163.4*4 = $16335.42

Solution for (f)

Given

Cost of purchasing and commissioning workstation = $2500

As per solution of question (c), 5 worksations are required. Since the company already has 4 worksations, it required additional 1 worksation which requires $2500 for purchasing and commissioning, bring up the total production cost to $18835.42.

However, the $2500 can be considered capital expenditure, keeping the production cost to $16335.42

Solution for (g)

If the company has to pay a penalty of $4500 upon cancelling other contracts, then the company should purchase the additional workstation. This will eliminate the loss of $4500. The $2500 spent on purchasing and commissioning new workstation can be recovered through future business.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A novelty coffee mug manufacturer produces 5 different designs that are sold at tourist information kiosks....
A novelty coffee mug manufacturer produces 5 different designs that are sold at tourist information kiosks. The demand requirements for the coming tourist season is as follows: Design A B C D E Demand (units) 500 750 600 800 450 The mugs can all be produced in the same workstations, but require different processing and setup times. The production information is in the following table: Design A B C D E Batch Size (units) 50 50 50 50 50 Setup...
Canine Kennels Company​ (CKC) manufactures two different types of dog chew toys​ (A and​ B, sold...
Canine Kennels Company​ (CKC) manufactures two different types of dog chew toys​ (A and​ B, sold in​ 1,000-count boxes) that are manufactured and assembled on three different workstations​ (W, X, and​ Y) using a​ small-batch process​ (see the figure​ below). Batch setup times are negligible. The flowchart denotes the path each product follows through the manufacturing​ process, and each​ product's price, demand per​ week, and processing times per unit are indicated as well. Purchased parts and raw materials consumed during...
Hudson Corporation, a Denver manufacturer produces three products and has provided the following information relating to...
Hudson Corporation, a Denver manufacturer produces three products and has provided the following information relating to its selling prices and unit costs for the three products. Product Product Product A B C Selling price $50 $80 $70 Variable costs $40 $50 $55 Fixed costs $15 $20 $12 Milling machine time (minutes) 4 2 5 Fixed costs are applied on the basis of direct labor hours. Demand for the three products exceeds the company's production capacity due to the milling machine's...
Question 5: Forecasting (8 p) The table below shows the demand (in units per quarter) of...
Question 5: Forecasting (8 p) The table below shows the demand (in units per quarter) of a specific product in the past three years. Quarter Year 1 2 3 4 2015 350 254 176 228 2016 367 258 169 236 2017 342 250 166 228 Predict demand in quarter 1 and quarter 2 of 2018, given that the demand forecast for the whole year is a total of 1,040 units. Question 6: DRP (8 p) A central DC supplies a...
1.Ford initially tried to use vertical integration to control all aspects of the production and sale...
1.Ford initially tried to use vertical integration to control all aspects of the production and sale of its automobiles. Later, Ford abandoned vertical integration and adopted a strategy of partnerships with key suppliers. The partnership arrangements were expected to cut costs for Ford but still permit the suppliers to enjoy profits at the level of the industry standard. How would it be possible for a supplier’s profits to be preserved while Ford’s costs decreased? Select one: a. Ford would agree...
Delta airlines case study Global strategy. Describe the current global strategy and provide evidence about how...
Delta airlines case study Global strategy. Describe the current global strategy and provide evidence about how the firms resources incompetencies support the given pressures regarding costs and local responsiveness. Describe entry modes have they usually used, and whether they are appropriate for the given strategy. Any key issues in their global strategy? casestudy: Atlanta, June 17, 2014. Sea of Delta employees and their families swarmed between food trucks, amusement park booths, and entertainment venues that were scattered throughout what would...