A novelty coffee mug manufacturer produces 5 different designs that
are sold at tourist information kiosks. The demand requirements for the coming
tourist season is as follows:
Design A B C D E
Demand (units) 500 750 600 800 450
The mugs can all be produced in the same workstations, but require different
processing and setup times. The production information is in the following
table:
Design A B C D E
Batch Size (units) 50 50 50 50 50
Setup Time (hr/batch) 2 2 2.5 4 1.5
Processing Time (hr/unit) 0.15 0.15 0.25 0.25 0.10
The company wants to produce all the required mugs in one four-week period.
It currently operates workstations that work 8 hours per day, 5 days per
week, with a capacity cushion of 20%.
(a) Calculate the total time required to produce the mugs to meet the expected
demand.
(b) Calculate the time available (taking into account the capacity cushion)
for 1 workstation.
(c) How many workstations are needed to meet the production requirements?
(d) The company only has 4 workstations available. If it only operates its 4
stations, how many weeks does it need to meet the production requirements?
(e) Operating each workstation costs the company $25/hour for a total of
$1,000 per week (including the capacity cushion). Calculate the total
operating cost to produce the mugs.
(f) Each workstation costs $2,500 to purchase and commission. If the company
acquires the extra number of workstations indicated in part (c),
what would be the cost of production?
(g) If the company has other contracts it needs to satisfy. Working on the
mugs more than 4 weeks means it will have to cancel another contract,
incurring a penalty of $4,500. What should the company do: cancel the
contract or buy the required workstations?
The following data is provided:
Design |
Demand (Units) |
Batch Size |
Setup time (Hr/Batch) |
Processing Time (hr/unit) |
A | 500 | 50 | 2 | 0.15 |
B | 750 | 50 | 2 | 0.15 |
C | 600 | 50 | 2.5 | 0.25 |
D | 800 | 50 | 4 | 0.25 |
E | 450 | 50 | 1.5 | 0.10 |
Work hours per day = 8 hours
Work days per week = 5 days
Capacity Cushion = 20%
Demand needs to be fulfilled in 4 weeks
Solution for (a)
No. of Batches = Demand/Batch Size
Total setup time = (Setup time * No. of Batches)
Total Processing Time = (Processing time * Demand)
Total Time Required = Total setup time + Total Processing Time
The below table contains the value arrived at using the above formula to arrive at the total time required the expected demand:
Dsign | Demand | Batch Size |
No. of Batches |
Set up Time (hr/batch) |
Total setup time |
Processing time (hr/unit |
Total Processing Time |
Total Time Required |
A | 500 | 50 | 10 | 2 | 20 | 0.15 | 75 | 95 |
B | 750 | 50 | 15 | 2 | 30 | 0.15 | 112.5 | 142.5 |
C | 600 | 50 | 12 | 2.5 | 30 | 0.25 | 150 | 180 |
D | 800 | 50 | 16 | 4 | 64 | 0.25 | 200 | 264 |
E | 450 | 50 | 9 | 1.5 | 13.5 | 0.10 | 45 | 58.5 |
Based on the above calculations, the total time requied to produce the expected demand is:
Total Time required = Sum of total processing times for all designs = 95+142.5+180+264+58.5=740 hours
Solution for (b)
No. of Batches = Demand/Batch Size
Total setup time = (Setup time * No. of Batches)
Total Processing Time = (Processing time * Demand)
Total Time Required = Total setup time + Total Processing Time
As stated above all the formula reamins the same. However, since we are using the cushion capacity of 20%, the processing time will reduce. Now the processing time will be 20% lower, i.e.if the processing time is T, then, with the utilization of cushion capacity the new processing time will be (T/(120%))
Dsign | Demand | Batch Size |
No. of Batches |
Set up Time (hr/batch) |
Total setup time |
Processing time (hr/unit |
Total Processing Time |
Total Time Required |
A | 500 | 50 | 10 | 2 | 20 | 0.13 | 62.5 | 82.5 |
B | 750 | 50 | 15 | 2 | 30 | 0.13 | 93.8 | 123.8 |
C | 600 | 50 | 12 | 2.5 | 30 | 0.21 | 125 | 155 |
D | 800 | 50 | 16 | 4 | 64 | 0.21 | 166.7 | 230.7 |
E | 450 | 50 | 9 | 1.5 | 13.5 | 0.08 | 37.5 | 51 |
Based on the above calculations, the total time requied to produce the expected demand using the cushion capacity is :
Total Time required = Sum of total processing times for all designs = 82.5+123.85+155+230.7+51=642.9 hours
Therefore the available time = Time required without capcity cushion - Time required with cushion = 740 - 642.9 = 97.1 hours
Solution for (c)
As given in the question, the demand needs to be met in 4 weeks. When only 1 workstation is used (without cushion), the time required is 740 hours. As given in the question, a work week consists of 5 days of 8 working hours.
Therefore the total number weeks required = 740/8/5= 18.5 weeks
If this demand is to be fulfilled in 4 weeks, then the number of work stations required are (18.5/4) = ~4.6 = 5 workstations.
Solution for (d)
If the company operates with 4 work stations(without capacity cushion) then some setups would happen in parallet indicated by "Setup rounds" column in the below table and the processing time per unit will reduce by 4 times.
Dsign | Demand | Batch Size |
No. of Batches |
Set up Time (hr/batch) |
Setup rounds |
Total setup time |
Processing time (hr/unit |
Total Processing Time |
Total Time Required |
A | 500 | 50 | 10 | 2 | 3 | 20 | 0.0375 | 18.8 | 24.8 |
B | 750 | 50 | 15 | 2 | 4 | 30 | 0.0375 | 28.1 | 36.1 |
C | 600 | 50 | 12 | 2.5 | 3 | 30 | 0.0625 | 37.5 | 45 |
D | 800 | 50 | 16 | 4 | 4 | 64 | 0.0625 | 50 | 66 |
E | 450 | 50 | 9 | 1.5 | 3 | 13.5 | 0.025 | 11.25 | 15.8 |
Based on the above calculation the number of weeks required to meet the demand = (24.8+36.1+45+66+15.8)/8/5 = 4.7 weeks
Solution for (e)
Given
Cost per hour per workstation = $25
Cost per week per workstation = $1000
Please find the below calcualtion table considering the 20% capacity cushion
Dsign | Demand | Batch Size |
No. of Batches |
Set up Time (hr/batch) |
Setup rounds |
Total setup time |
Processing time (hr/unit |
Total Processing Time |
Total Time Required |
A | 500 | 50 | 10 | 2 | 3 | 20 | 0.031 | 15.6 | 21.6 |
B | 750 | 50 | 15 | 2 | 4 | 30 | 0.031 | 23.4 | 31.4 |
C | 600 | 50 | 12 | 2.5 | 3 | 30 | 0.052 | 31.3 | 38.8 |
D | 800 | 50 | 16 | 4 | 4 | 64 | 0.052 | 41.7 | 57.7 |
E | 450 | 50 | 9 | 1.5 | 3 | 13.5 | 0.021 | 9.4 | 13.9 |
Total production hours required to fulfill the demand = 163.4 hours
Total cost = Rate per hour * Total production hours * No. of workstation = 25*163.4*4 = $16335.42
Solution for (f)
Given
Cost of purchasing and commissioning workstation = $2500
As per solution of question (c), 5 worksations are required. Since the company already has 4 worksations, it required additional 1 worksation which requires $2500 for purchasing and commissioning, bring up the total production cost to $18835.42.
However, the $2500 can be considered capital expenditure, keeping the production cost to $16335.42
Solution for (g)
If the company has to pay a penalty of $4500 upon cancelling other contracts, then the company should purchase the additional workstation. This will eliminate the loss of $4500. The $2500 spent on purchasing and commissioning new workstation can be recovered through future business.
Get Answers For Free
Most questions answered within 1 hours.