Question

A manufacturing company has a pool of 50 labor hours. A customer has requested two products,...

A manufacturing company has a pool of 50 labor hours. A customer has requested two products, Product A and Product B, and has requested 15 and 20 of each respectively. It requires 2 hours of labor to produce Product A and 3 hours of labor to produce Product B. The company can obtain up to 50 additional hours of labor if required. In-house labor costs $25 per hour while contracted labor costs $45 per hour.

Draw the network flow model that captures this problem.

Write out the LP formulation for this problem.

Solve this system – the network flow problem. [Provide a screen shot of your Solver solution and/or any Solver Reports you deem necessary.]

What is the company’s labor plan to develop the products, A and B, to fulfill the customer’s order? And, what is the associated cost to the company?

Homework Answers

Answer #1

1) Network flow model is following

2) LP formulation is as follows

Let HA and HB be the number of inhouse labor hours used to produce products A and B respectively

and CA and CB be the number of contracted labor hours used to produce products A and B respectively

Min (HA+HB)*25 + (CA+CB)*45

s.t.

HA+HB <= 50

CA+CB <= 50

HA/2 + CA/2 = 15

HB/3 + CB/3 = 20

HA, HB, CA, CB >= 0

3) Solution of the model using Solver is as follows

Formula:

F2 =SUMPRODUCT(B2:E2,$B$8:$E$8)   copy to F2:F6

Solver Answer report is following

4)

Company's labor plan is such that 50 inhouse labor hours should be used for producing B and 30 and 10 contracted labor hours should be used for production of A and B respectively.

Associated cost to the company = $ 3050

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
ABC Company produces three products: A, B, and C.   The company only has 300 labor hours...
ABC Company produces three products: A, B, and C.   The company only has 300 labor hours per week to produce these 3 products Product information is as follows: A B C Unit selling price 140 75 240 Unit variable costs 100 50 180 Unit contribution margin 40 25 60 Labor hours per unit 5 4 6 Maximum demand in units per week 15 20 30 Required: What is the optimal product mix(how many A, B, and C should be produced)...
Bowcock Manufacturing allocates factory overhead using one cost pool with direct labor hours as the allocation...
Bowcock Manufacturing allocates factory overhead using one cost pool with direct labor hours as the allocation base. Bowcock has two production departments (A1 and A2). The new accountant at Bowcock estimates that next year the total factory overhead costs will be $4,000,000 and approximately 500,000 direct labor hours will be worked. The accountant also estimates that A1 will use 150,000 direct labor hours and there will be about $2,000,000 in overhead costs in A1. A2 will use 350,000 direct labor...
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours...
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours per Unit Annual Production Hubs 0.90 15,000 units Sprockets 0.50 49,000 units Additional information about the company follows: Hubs require $35 in direct materials per unit, and Sprockets require $10. The direct labor wage rate is $18 per hour. Hubs require special equipment and are more complex to manufacture than Sprockets. The ABC system has the following activity cost pools: Estimated Activity Activity Cost...
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours...
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours per Unit Annual Production Hubs 0.80 13,000 units Sprockets 0.40 59,000 units Additional information about the company follows: Hubs require $38 in direct materials per unit, and Sprockets require $15. The direct labor wage rate is $13 per hour. Hubs require special equipment and are more complex to manufacture than Sprockets. The ABC system has the following activity cost pools: Estimated Activity Activity Cost...
The Littlefield Company applies manufacturing overhead costs to products on the basis of direct labor-hours. The...
The Littlefield Company applies manufacturing overhead costs to products on the basis of direct labor-hours. The standard cost card shows that 12 direct labor-hours are required per unit of product. For August, the company budgeted to work 360,000 direct labor-hours and to incur the following total manufacturing overhead costs: Total fixed overhead costs $475,200 Total variable overhead costs $396,000 During August, the company completed 28,000 units of product, worked 344,000 direct labor-hours, and incurred the following total manufacturing overhead costs:...
pring, Inc. manufactures two products. It currently has 1,300 hours of direct labor and 3,250 hours...
pring, Inc. manufactures two products. It currently has 1,300 hours of direct labor and 3,250 hours of machine time available per month. The table below lists the contribution margin, labor and machine time requirements, and demand for each product. Product A Product B Unit contribution margin $ 34.00 $ 30.00 Demand 2,600 units 1,300 units Labor time 1/4 hour 1/2 hour Machine time 1 hour 1/2 hour How much of each product should Spring manufacture per month?
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours...
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours per Unit Annual Production Hubs 0.60 11,000 units Sprockets 0.20 47,000 units Additional information about the company follows: Hubs require $22 in direct materials per unit, and Sprockets require $14. The direct labor wage rate is $14 per hour. Hubs require special equipment and are more complex to manufacture than Sprockets. The ABC system has the following activity cost pools: Estimated Activity Activity Cost...
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours...
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours per Unit Annual Production Hubs 0.70 19,000 units Sprockets 0.30 47,000 units Additional information about the company follows: Hubs require $34 in direct materials per unit, and Sprockets require $15. The direct labor wage rate is $16 per hour. Hubs require special equipment and are more complex to manufacture than Sprockets. The ABC system has the following activity cost pools: Estimated Activity Activity Cost...
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours...
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours per Unit Annual Production Hubs 0.50 10,000 units Sprockets 0.10 40,000 units Additional information about the company follows: Hubs require $37 in direct materials per unit, and Sprockets require $14. The direct labor wage rate is $16 per hour. Hubs require special equipment and are more complex to manufacture than Sprockets. The ABC system has the following activity cost pools: Estimated Activity Activity Cost...
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours...
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours per Unit Annual Production Hubs 0.70 18,000 units Sprockets 0.30 54,000 units Additional information about the company follows: Hubs require $25 in direct materials per unit, and Sprockets require $15. The direct labor wage rate is $17 per hour. Hubs require special equipment and are more complex to manufacture than Sprockets. The ABC system has the following activity cost pools: Estimated Activity Activity Cost...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT