Question

Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours...

Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow:

Direct
Labor-Hours per Unit
Annual
Production
Hubs 0.50 28,000 units
Sprockets 0.10 46,000 units

Additional information about the company follows:

  1. Hubs require $24 in direct materials per unit, and Sprockets require $10.

  2. The direct labor wage rate is $12 per hour.

  3. Hubs require special equipment and are more complex to manufacture than Sprockets.

  4. The ABC system has the following activity cost pools:

Estimated Activity
Activity Cost Pool (Activity Measure) Overhead Cost Hubs Sprockets Total
Machine setups (number of setups) $ 29,250 125 100 225
Special processing (machine-hours) $ 140,000 4,000 0 4,000
General factory (organization-sustaining) $ 69,200 NA NA NA

Required:

1. Compute the activity rate for each activity cost pool.

2. Determine the unit product cost of each product according to the ABC system.

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours...
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours per Unit Annual Production Hubs 0.80 22,000 units Sprockets 0.40 52,000 units Additional information about the company follows: Hubs require $33 in direct materials per unit, and Sprockets require $12. The direct labor wage rate is $17 per hour. Hubs require special equipment and are more complex to manufacture than Sprockets. The ABC system has the following activity cost pools: Estimated Activity Activity Cost...
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours...
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours per Unit Annual Production Hubs 0.60 11,000 units Sprockets 0.20 47,000 units Additional information about the company follows: Hubs require $22 in direct materials per unit, and Sprockets require $14. The direct labor wage rate is $14 per hour. Hubs require special equipment and are more complex to manufacture than Sprockets. The ABC system has the following activity cost pools: Estimated Activity Activity Cost...
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours...
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours per Unit Annual Production Hubs 0.70 19,000 units Sprockets 0.30 47,000 units Additional information about the company follows: Hubs require $34 in direct materials per unit, and Sprockets require $15. The direct labor wage rate is $16 per hour. Hubs require special equipment and are more complex to manufacture than Sprockets. The ABC system has the following activity cost pools: Estimated Activity Activity Cost...
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours...
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours per Unit Annual Production Hubs 0.50 10,000 units Sprockets 0.10 40,000 units Additional information about the company follows: Hubs require $37 in direct materials per unit, and Sprockets require $14. The direct labor wage rate is $16 per hour. Hubs require special equipment and are more complex to manufacture than Sprockets. The ABC system has the following activity cost pools: Estimated Activity Activity Cost...
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours...
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours per Unit Annual Production Hubs 0.70 18,000 units Sprockets 0.30 54,000 units Additional information about the company follows: Hubs require $25 in direct materials per unit, and Sprockets require $15. The direct labor wage rate is $17 per hour. Hubs require special equipment and are more complex to manufacture than Sprockets. The ABC system has the following activity cost pools: Estimated Activity Activity Cost...
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours...
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours per Unit Annual Production Hubs 0.60 16,000 units Sprockets 0.20 53,000 units Additional information about the company follows: Hubs require $21 in direct materials per unit, and Sprockets require $16. The direct labor wage rate is $17 per hour. Hubs require special equipment and are more complex to manufacture than Sprockets. The ABC system has the following activity cost pools: Estimated Activity Activity Cost...
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours...
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours per Unit Annual Production Hubs 0.60 16,000 units Sprockets 0.20 53,000 units Additional information about the company follows: Hubs require $21 in direct materials per unit, and Sprockets require $16. The direct labor wage rate is $17 per hour. Hubs require special equipment and are more complex to manufacture than Sprockets. The ABC system has the following activity cost pools: Estimated Activity Activity Cost...
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours...
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours per Unit Annual Production Hubs 0.60 23,000 units Sprockets 0.20 45,000 units Additional information about the company follows: Hubs require $23 in direct materials per unit, and Sprockets require $13. The direct labor wage rate is $19 per hour. Hubs require special equipment and are more complex to manufacture than Sprockets. The ABC system has the following activity cost pools: Estimated Activity Activity Cost...
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours...
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours per Unit Annual Production Hubs 0.80 19,000 units Sprockets 0.40 47,000 units Additional information about the company follows: Hubs require $27 in direct materials per unit, and Sprockets require $16. The direct labor wage rate is $12 per hour. Hubs require special equipment and are more complex to manufacture than Sprockets. The ABC system has the following activity cost pools: Estimated Activity Activity Cost...
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours...
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours per Unit Annual Production Hubs 0.60 16,000 units Sprockets 0.20 47,000 units Additional information about the company follows: Hubs require $37 in direct materials per unit, and Sprockets require $12. The direct labor wage rate is $20 per hour. Hubs require special equipment and are more complex to manufacture than Sprockets. The ABC system has the following activity cost pools: Estimated Activity Activity Cost...