Question

If your able to work out the problems instead of using excel since excel isnt accessible...

If your able to work out the problems instead of using excel since excel isnt accessible on the exam.

Consider the following projects, for a firm using a discount rate of 10%. If the projects are mutually exclusive, which, if any, project(s) should the firm accept?

Project                   NPV                                           IRR                                            PI

E                               $200,000                                10.2%                                       1.04

F                               $(200,001)                            11%                                           .81

G                               $1                                                10%                                           1.01

H                              $(235,000)                            9%                                            .95

a.               E

b.              F

c.               H

d.              F and H

You are considering two mutually exclusive projects. Both projects have an initial cost of $52,000. Project A produces cash inflows of $25,300, $37,100, and $22,000 for years 1 through 3, respectively. Project B produces cash inflows of $43,600, $19,800 and $10,400 for years 1 through 3, respectively. The required rate of return is 14.2 percent for Project A and 13.9 percent for Project B. Which project should you accept and why?

Project A; because it has the higher required rate of return.

Project A; because it has the larger NPV.

Project A; because it has the larger IRR.

Project B; because it has the larger NPV

A proposed project has an initial cost of $38,000 and cash inflows of $12,300, $24,200, and $16,100 for years 1 through 3, respectively. The required rate of return is 16.8 percent. Based on IRR, should this project be accepted? Why or why not?

No; The IRR exceeds the required return by .58 percent.

No; The IRR is less than the required return by 1.03 percent.

Yes; The IRR exceeds the required return by .58 percent.

Yes; The IRR exceeds the required return by about 1.03 percent.

A project has projected cash flows of -$148,500, $32,800, $64,200, -$7,500 and $87,300 for years 0 to 4, respectively. Should this project be accepted based on the combination approach to the modified internal rate of return if both the discount rate and the reinvestment rate are 12.6 percent? Why or why not?

Yes; The MIRR is 8.81 percent.

Yes; The MIRR is 9.23 percent.

No; The MIRR is 8.81 percent.

No; The MIRR is 9.06 percent.

Homework Answers

Answer #1

(1) All four projects have a required return of 10 % which implies a cash flow discount rate of 10 %. If any project has IRR less than equal to the required rate of 10 %, then that project either generates negative value or no value for the firm, thereby being ill-suited. This analysis leaves two projects namely E and F of which E adds value owing to its positive NPV and F erodes value owing to its negative NPV. Therefore, the preferred project will be Project E.

NOTE: Please raise separate queries for solutions to the remaining unrelated questions.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Two mutually exclusive projects have an initial cost of $60,000 each. Project A produces cash inflows...
Two mutually exclusive projects have an initial cost of $60,000 each. Project A produces cash inflows of $30,000, $37,000, and $20,000 for Years 1 through 3, respectively. Project B produces cash inflows of $80,000 in Year 2 only. The required rate of return is 10 percent for Project A and 11 percent for Project B. Which project(s) should be accepted and why? Project A, because it has the higher required rate of return. Project A, because it has the larger...
A manager is reviewing a project with an ini!al cost of $48,700 and cash inflows of...
A manager is reviewing a project with an ini!al cost of $48,700 and cash inflows of $12,800, $20,400, and $27,700 for Years 1 to 3, respectively. Should the project be accepted if it has been assigned a required return of 9.75%? Why or why not? A) No, because the IRR is only 9.69% B) Yes, because the IRR exceeds the required return by .88% C) Yes, because the IRR is less than the required return by .56% D) No, because...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified internal rate of return. PI = profitability index. Project A Project B Project C Project D Project E Project F Project G NPV= $4,711 ($711) ($657) $334 $9,842 $7,360 ($3,224) IRR= 44.51% 5.47% 8.06% 12.98% 22.56% 17.19% 5.47% MIRR= 25.23% 7.50% 8.97% 11.57% 16.26% 13.70% 7.50% PI= 2.178 0.822 0.945 1.028 1.394 1.294 0.871 The discounting rate (r)...
Ace Inc. is evaluating two mutually exclusive projects—Project A and Project B. The initial cash outflow...
Ace Inc. is evaluating two mutually exclusive projects—Project A and Project B. The initial cash outflow is $50,000 for each project. Project A results in cash inflows of $15,625 at the end of each of the next five years. Project B results in one cash inflow of $99,500 at the end of the fifth year. The required rate of return of Ace Inc. is 10 percent. Ace Inc. should invest in: a. ​Project B because it has no cash inflows...
Projects A and B are mutually exclusive. Project A has cash flows of −$10,000, $5,100, $3,400,...
Projects A and B are mutually exclusive. Project A has cash flows of −$10,000, $5,100, $3,400, and $4,500 for Years 0 to 3, respectively. Project B has cash flows of −$10,000, $4,500, $3,400, and $5,100 for Years 0 to 3, respectively.          B-1 what is the IRR of project A?          B-2 What is the IRR of project B?          B-3 Based on the IRR rule, which project should be accepted and why?          B-4 At what required rate of...
If mutually exclusive projects with normal cash flows are being analyzed, the net present value (NPV)...
If mutually exclusive projects with normal cash flows are being analyzed, the net present value (NPV) and internal rate of return (IRR) methods   agree. Projects Y and Z are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. Year Project Y Project Z 0 –$1,500 –$1,500 1 $200 $900 2 $400 $600 3 $600 $300 4 $1,000 $200    If the weighted average cost of capital (WACC) for each project is 14%, do the NPV and...
Solve the problems below using well-formatted Excel solutions. Do not hardcode numbers in the formulas…..only use...
Solve the problems below using well-formatted Excel solutions. Do not hardcode numbers in the formulas…..only use cell references to the input data. I will change the input data in your problem to check alternate solutions. You will turn in a complete working Excel spreadsheet with your solution. 1. A firm is considering the two mutually exclusive investments projects. Project Alpha requires an initial outlay of $600 and will return $160 per year for the next seven years; Project Beta requires...
You are considering two mutually exclusive projects that have been assigned the same discount rate of...
You are considering two mutually exclusive projects that have been assigned the same discount rate of 10.5 percent. Project A has an initial cost of $54,500, and should produce cash inflows of $16,400, $28,900, and $31,700 for Years 1 to 3, respectively. Project B has an initial cost of $79,400, and should produce cash inflows of $0, $48,300, and $42,100, for Years 1 to 3, respectively. What is the incremental IRR? 7.83% 5.40% −15.40% -4.67% 13.89%
A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax...
A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$9,000 $3,000 $3,000 $3,000 $3,000 $3,000 Project N -$27,000 $8,400 $8,400 $8,400 $8,400 $8,400 Calculate NPV for each project. Do not round intermediate calculations. Round your answers to the nearest cent. Project M:    $   Project N:    $   Calculate IRR for each project. Do not round intermediate calculations. Round your answers to...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified internal rate of return. PI = profitability index. Criteria:                Project_A         Project_B             Project_C         Project_D          Project_E               Project_F             Project_G NPV= $137,083 $31,290 $6,016 $7,647 ($584) $12,521 $9,214 IRR= 31.80% 48.34% 12.03% 11.30% 9.94% 26.79% 37.87% MIRR= 18.52% 23.52% 10.62% 10.59% 9.97% 23.53% 20.76% PI= 1.69 2.25 1.040 1.038 1.00 2.25 1.92 The discounting rate...