Question

The underlying cause of ranking conflicts between the NPV and IRR methods is differing________ A) initial...

The underlying cause of ranking conflicts between the NPV and IRR methods is
differing________
A) initial cost.
B) costs of capital.
C) cash flow timing.
D) profitability indices.
E) errors in calculating the discount rate.

Homework Answers

Answer #1

Option c is correct option. Timing of cash flows.

1. IRR and NPV may conflict in certain cases of mutually exclusive projects  where NPV rule prevails.
2. IRR rate is higher than WACC generally so reinvestment as higher than WACC may not be possible always.
3. It gives multiple IRR when have more than one negative cash flows occur in the project or non conventional flows. Hence multiple IRR can create confusion
4. IRR and NPV conflict due to size and timing of cash flows.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
1) If the NPV of a project with one sign reversal is positive, then its IRR:...
1) If the NPV of a project with one sign reversal is positive, then its IRR: Select one: a. must be greater than the required rate of return b. must be less than the required rate of return c. could be greater or less than the required rate of return d. cannot be determined without actual cash flows 2) Which of the following statements is INCORRECT? Select one: a. An acceptable project should have an NPV greater than or equal...
The large furniture retailer "Sofa So Good" is evaluating two mutually exclusive projects: NPV versus IRR....
The large furniture retailer "Sofa So Good" is evaluating two mutually exclusive projects: NPV versus IRR. Consider the following projects where the firms may only choose one not both: The firm's cost of capital/required return equals 9%. NOTE: The firm's cost of capital K, acts as a hurdle rate, and is based on the costs involved in financing other firm projects. The Cost of capital allows us to decide to accept or reject an investment, using IRR, which additionally allows...
 LO 3 LO 4 7. Calculating NPV and IRR. A project that provides annual cash...
 LO 3 LO 4 7. Calculating NPV and IRR. A project that provides annual cash flows of $2,620 for eight years costs $9,430 today. Is this a good project if the required return is 8 percent? What if it's 24 percent? At what discount rate would you be indifferent between accepting the project and rejecting it?  LO 4 9. Calculating NPV. For the cash flows in the previous problem, what is the NPV at a discount rate of...
1. Which of the following do you need to know to calculate NPV? A.) Amount and...
1. Which of the following do you need to know to calculate NPV? A.) Amount and timing of future cashflows B.) Appropriate discount rate C.) Initial Costs D.) All of the above 2. Which of the following projects should a company take on? A.) Building a warehouse with an NPV of $630 million B.)Building an office with an NPV of $0 C.) Building a helipad with an NPV of -$15 million 3.) What is the minimum acceptance criteria for the...
Two mutually exclusive projects each have a cost of $10,000. The total, undiscounted cash flows from...
Two mutually exclusive projects each have a cost of $10,000. The total, undiscounted cash flows from Project L are $15,000, while the undiscounted cash flows from Project S total $13,000. Their NPV profiles cross at a discount rate of 10 percent. Which of the following statements best describes this situation? Please leave an explanation.  a. The NPV and IRR methods will select the same project if the cost of capital is greater than 10 percent; for example, 18 percent. b. The...
The IRR measures which of the following? a. The return earned on the initial investment. b....
The IRR measures which of the following? a. The return earned on the initial investment. b. The average return earned over time on the funds invested. c. The discount rate at which NPV is zero. d. The overall return if the project’s funds are invested at the cost of capital.
Calculating NPV and IRR. A project that provides annual cash flows of $1,710 for 10 years...
Calculating NPV and IRR. A project that provides annual cash flows of $1,710 for 10 years costs $7,560 today. 1. The NPV is $__________if the required rate of return is 10%. 2. The NPV is $__________if the required rate of return is 24%. 3. At what discount rate would you be indifferent between accepting the project and rejecting it? I would be indifferent at _____% 4. Using a finnancial calculator please show and explain work.
Understanding the IRR and NPV The net present value (NPV) and internal rate of return (IRR)...
Understanding the IRR and NPV The net present value (NPV) and internal rate of return (IRR) methods of investment analysis are interrelated and are sometimes used together to make capital budgeting decisions. Consider the case of Blue Hamster Manufacturing Inc.: Last Tuesday, Blue Hamster Manufacturing Inc. lost a portion of its planning and financial data when both its main and its backup servers crashed. The company’s CFO remembers that the internal rate of return (IRR) of Project Delta is 11.3%,...
(Payback ​period, NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash...
(Payback ​period, NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash outlay of ​$75,000 and expected free cash flows of ​$26,000 at the end of each year for 5 years. The required rate of return for this project is 7 percent. a. What is the​ project's payback​ period? b. What is the​ project's NPV​? c. What is the​ project's PI​? d. What is the​ project's IRR​?
The net present value (NPV) and internal rate of return (IRR) methods of investment analysis are...
The net present value (NPV) and internal rate of return (IRR) methods of investment analysis are interrelated and are sometimes used together to make capital budgeting decisions. Consider the case of Blue Hamster Manufacturing Inc.: Last Tuesday, Blue Hamster Manufacturing Inc. lost a portion of its planning and financial data when both its main and its backup servers crashed. The company’s CFO remembers that the internal rate of return (IRR) of Project Delta is 11.3%, but he can’t recall how...