Question

1. Which of the following do you need to know to calculate NPV? A.) Amount and...

1. Which of the following do you need to know to calculate NPV?

A.) Amount and timing of future cashflows

B.) Appropriate discount rate

C.) Initial Costs

D.) All of the above

2. Which of the following projects should a company take on?

A.) Building a warehouse with an NPV of $630 million

B.)Building an office with an NPV of $0

C.) Building a helipad with an NPV of -$15 million

3.) What is the minimum acceptance criteria for the IRR?

A.)IRR ≥  NPV

B.)IRR ≥ required return

C.)IRR < NPV

D.) IRR < required return

Homework Answers

Answer #1


1.

Correct option is > D.) All of the above

To get NPV discount rate is used to discount the future cash flow and initial cost is subtracted from that hence, we require all above to calculate NPV.

2.

Correct option is > A.) Building a warehouse with an NPV of $630 million

Highest NPV is acceptable by company. The highest NPV is only desired for taking up the project.

3.

Correct option is > B.) IRR ≥ required return

The IRR is rate where overall cashflow of the project is equal to ZERO.

Required rate should be less the IRR so that NPV is positive or at least Zero.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
1) If the NPV of a project with one sign reversal is positive, then its IRR:...
1) If the NPV of a project with one sign reversal is positive, then its IRR: Select one: a. must be greater than the required rate of return b. must be less than the required rate of return c. could be greater or less than the required rate of return d. cannot be determined without actual cash flows 2) Which of the following statements is INCORRECT? Select one: a. An acceptable project should have an NPV greater than or equal...
Which of the following statements defines the internal rate of return (IRR) for a project? A....
Which of the following statements defines the internal rate of return (IRR) for a project? A. Discount rate which results in a zero NPV B. Discount rate which results in a NPV equal to the project's initial cost C. Rate of return required by the project's investors D. The current market rate of return for projects of similar risk
Which one of the following is TRUE? The NPV decision rule says to accept an investment...
Which one of the following is TRUE? The NPV decision rule says to accept an investment if the NPV is negative. The IRR decision rule states that a project should be accepted if its IRR exceeds the required return. The discount rate that causes the net present value of a project to equal zero is called the market rate. IRR is superior to NPV for choosing between different projects. Payback ignores the project's cost.
Which of the following statements about internal rate of return (IRR) is false? explain why IRR...
Which of the following statements about internal rate of return (IRR) is false? explain why IRR is the discount rate at which the present value of future expected cash flows is exactly equal to the initial investment. The IRR rule always leads to the same decision as the NPV rule. IRR is the discount rate at which a project's NPV equals zero.
11) Your company is choosing between two MUTUALLY EXCLUSIVE projects that have a required rate of...
11) Your company is choosing between two MUTUALLY EXCLUSIVE projects that have a required rate of return of 8.25%. You have gathered the following data. Which of the project(s) should be accepted? IRR NPV Project A 6.40% $ 22.6 million Project B 8.50% $ 16.1 million A) Accept neither project, as both have a required return that is above the IRR. B) Accept project B with the higher IRR. C) Accept project A with the higher NPV. D) Accept both...
Which of the following statement is correct? Select one: a. All the answers are incorrect. b....
Which of the following statement is correct? Select one: a. All the answers are incorrect. b. A positive NPV means that the firm’s value will decrease if the project is adopted because the new project’s estimated return is lesst than the firm’s required rate of return. c. Reject the project if the IRR is greater than or equal to the required rate of return. d. Payback period is the discount rate that forces the NPV to equal zero. e. All...
The IRR measures which of the following? a. The return earned on the initial investment. b....
The IRR measures which of the following? a. The return earned on the initial investment. b. The average return earned over time on the funds invested. c. The discount rate at which NPV is zero. d. The overall return if the project’s funds are invested at the cost of capital.
You are evaluating an investment project and learn the following: The project’s NPV at a discount...
You are evaluating an investment project and learn the following: The project’s NPV at a discount rate of 20% is +$35,879 The project’s NPV at a discount rate of 24% is +$12,356 The project’s NPV at a discount rate of 26% is -$1,923 Based on (i)-(iii) above you know the project’s IRR must be: a) Less than 20% b) Greater than 26% c) Between 20% and 24% d) Between 24% and 26%
Which of the following statement is incorrect? Select one: a. When the internal rate of return...
Which of the following statement is incorrect? Select one: a. When the internal rate of return is less than this required rate of return, the project is rejected. b. When NPV equals zero, the required rate of return, or discount rate used in the NPV calculation, is greater than the projected rate of return, IRR. c. Most of the answers are correct. d. The number of time periods it takes to cover the initial investment is called the payback period....
2a. Year Cash Flow 0 –$7,400            1 3,000            2 3,500            3 3,400  &n
2a. Year Cash Flow 0 –$7,400            1 3,000            2 3,500            3 3,400               Required: (a) What is the NPV at a discount rate of 0 percent?   (Click to select)   $2,375   $2,425   $2,500.00   $2,575   $2,625    (b) What is the NPV at a discount rate of 11 percent?   (Click to select)   $648.31   $610.55   $660.9   $629.43   $597.96    (c) What is the NPV at a discount rate of 24 percent?   (Click to select)   $-921.11   $-875.06   $-948.75   $-967.17   $-974.61 (d) What is the NPV at a discount rate of 29 percent?   (Click to select)   $-1,317.98   $-1,345.72   $-1,456.71   $-1,428.97   $-1,387.35...