Question

baseline duration baseline complete Actual cost to date EV PV Door 3 days 9600 70% 5000...

baseline duration baseline complete Actual cost to date EV PV
Door 3 days 9600 70% 5000 7000
Electrical 4 days 14400 20% 3000 2000
Pour 2 days 10800 100% 12000 10800 10800

1. What is the EV of Door/Electrical tasks

2. What is Pour's CPI?

3. If Pour's CPI>1, what 's happened?

4. SV =?

5. If SV is positive, what's happened?

Homework Answers

Answer #1

1) EV of door = Base line * complete%

EV of door = 9600*70% = 6720

EV of Electrical = 14400*20% = 2880

2) CPI = EV/ Actual cost

CPI of pour = 10800/12000

CPI = 0.9

3) If Pour CPI is greater than 1 than it means the cost of completion of project is less that what it it is actually planned

4) SV = EV - PV

SV of door = 6720-7000 = -280

SV of Electrical = 2880-2000 = 880

SV of Pour = 10800-10800 = 0

5) IF SV is positive it means that the project is ahead of schedule.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT