baseline duration | baseline | complete | Actual cost to date | EV | PV | |
Door | 3 days | 9600 | 70% | 5000 | 7000 | |
Electrical | 4 days | 14400 | 20% | 3000 | 2000 | |
Pour | 2 days | 10800 | 100% | 12000 | 10800 | 10800 |
1. What is the EV of Door/Electrical tasks
2. What is Pour's CPI?
3. If Pour's CPI>1, what 's happened?
4. SV =?
5. If SV is positive, what's happened?
1) EV of door = Base line * complete%
EV of door = 9600*70% = 6720
EV of Electrical = 14400*20% = 2880
2) CPI = EV/ Actual cost
CPI of pour = 10800/12000
CPI = 0.9
3) If Pour CPI is greater than 1 than it means the cost of completion of project is less that what it it is actually planned
4) SV = EV - PV
SV of door = 6720-7000 = -280
SV of Electrical = 2880-2000 = 880
SV of Pour = 10800-10800 = 0
5) IF SV is positive it means that the project is ahead of schedule.
Get Answers For Free
Most questions answered within 1 hours.