"A company currently operates its flour mill 6 days per week
(Monday through Saturday).
Flour sells for $23.73 per hundredweight (cwt) and the company
purchases wheat at a price of $4.51 per bushel. 2.17 bushels of
wheat are required per cwt of flour.
Fixed costs are currently $9,433 per day of operation. The labor
cost of mill operations is $0.92 per cwt.
If the company decides to operate on Sunday, the labor cost of
Sunday operations increases to $1.24 per cwt. If the mill were to
operate on Sunday, the fixed cost on Sunday would increase by
$869.
If the company decides to operate 7 days a week, what is the weekly
break-even volume in terms of cwt? Assume the same amount of flour
is produced in each day of the week.
HINT: You need to calculate the average daily variable cost for
labor for a 7-day operation."