Question

Choose all the correct answers that apply to IRR (a) PWDR which causes the NPV to...

Choose all the correct answers that apply to IRR

(a) PWDR which causes the NPV to be equal to zero

(b) Projects can have only one IRR

(c) an IRR>PWDR indicates a possible investment

(d) an IRR<PWDR indicates a possible investment

Homework Answers

Answer #1

IRR is Internal Rate of Return. It is that value of the discount rate at which NPV is equal to zero i.e. at IRR Present Value of cash inflows is equal to the Present Value of cash outflows. If a project has positive cashflows and then negative cashflows and then again positive cashflows then IRR can have more than one values. A project is selected if its IRR is greater than the cost of capital and is rejected if its IRR is less than the cost of capital. So out of the given statements, the ones that apply to IRR are:

(a) PWDR which causes the NPV to be equal to zero.

(c) an IRR>PWDR indicates a possible investment.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Which of the following statement is correct? Select one: a. All the answers are incorrect. b....
Which of the following statement is correct? Select one: a. All the answers are incorrect. b. A positive NPV means that the firm’s value will decrease if the project is adopted because the new project’s estimated return is lesst than the firm’s required rate of return. c. Reject the project if the IRR is greater than or equal to the required rate of return. d. Payback period is the discount rate that forces the NPV to equal zero. e. All...
The NPV profile can be used to: (Select all correct answers.) a) Perform sensitivity analysis. b)...
The NPV profile can be used to: (Select all correct answers.) a) Perform sensitivity analysis. b) Identify negative NPV projects. c) Identify the IRR. d) Identify positive NPV projects.
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified internal rate of return. PI = profitability index. Criteria:                Project_A         Project_B             Project_C         Project_D          Project_E               Project_F             Project_G NPV= $137,083 $31,290 $6,016 $7,647 ($584) $12,521 $9,214 IRR= 31.80% 48.34% 12.03% 11.30% 9.94% 26.79% 37.87% MIRR= 18.52% 23.52% 10.62% 10.59% 9.97% 23.53% 20.76% PI= 1.69 2.25 1.040 1.038 1.00 2.25 1.92 The discounting rate...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified internal rate of return. PI = profitability index. Criteria:                Project_A         Project_B             Project_C         Project_D          Project_E               Project_F             Project_G NPV= $137,083 $31,290 $6,016 $7,647 ($584) $12,521 $9,214 IRR= 31.80% 48.34% 12.03% 11.30% 9.94% 26.79% 37.87% MIRR= 18.52% 23.52% 10.62% 10.59% 9.97% 23.53% 20.76% PI= 1.69 2.25 1.040 1.038 0.999 2.25 1.92 The discounting rate...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified internal rate of return. PI = profitability index. Criteria:                Project_A         Project_B             Project_C         Project_D          Project_E               Project_F             Project_G NPV= $137,083 $31,290 $6,016 $7,647 ($584) $12,521 $9,214 IRR= 31.80% 48.34% 12.03% 11.30% 9.94% 26.79% 37.87% MIRR= 18.52% 23.52% 10.62% 10.59% 9.97% 23.53% 20.76% PI= 1.69 2.25 1.040 1.038 0.999 2.25 1.92 The discounting rate...
1) If the NPV of a project with one sign reversal is positive, then its IRR:...
1) If the NPV of a project with one sign reversal is positive, then its IRR: Select one: a. must be greater than the required rate of return b. must be less than the required rate of return c. could be greater or less than the required rate of return d. cannot be determined without actual cash flows 2) Which of the following statements is INCORRECT? Select one: a. An acceptable project should have an NPV greater than or equal...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified internal rate of return. PI = profitability index. Project A Project B Project C Project D Project E Project F Project G NPV= $4,711 ($711) ($657) $334 $9,842 $7,360 ($3,224) IRR= 44.51% 5.47% 8.06% 12.98% 22.56% 17.19% 5.47% MIRR= 25.23% 7.50% 8.97% 11.57% 16.26% 13.70% 7.50% PI= 2.178 0.822 0.945 1.028 1.394 1.294 0.871 The discounting rate (r)...
Which one of the following is TRUE? The NPV decision rule says to accept an investment...
Which one of the following is TRUE? The NPV decision rule says to accept an investment if the NPV is negative. The IRR decision rule states that a project should be accepted if its IRR exceeds the required return. The discount rate that causes the net present value of a project to equal zero is called the market rate. IRR is superior to NPV for choosing between different projects. Payback ignores the project's cost.
1. Which of the following statements is correct? a. A project with conventional cash flows is...
1. Which of the following statements is correct? a. A project with conventional cash flows is one with an initial cash outflow followed by one or more cash inflows. b. The NPV method determines how much the future value of cash inflows exceeds the present value of costs. c. All the answers are correct. d. When two projects are independent, accepting one project implicitly eliminates the other. e. Conventional cash flow patterns could lead to conflicting decisions by NPV and...
The large furniture retailer "Sofa So Good" is evaluating two mutually exclusive projects: NPV versus IRR....
The large furniture retailer "Sofa So Good" is evaluating two mutually exclusive projects: NPV versus IRR. Consider the following projects where the firms may only choose one not both: The firm's cost of capital/required return equals 9%. NOTE: The firm's cost of capital K, acts as a hurdle rate, and is based on the costs involved in financing other firm projects. The Cost of capital allows us to decide to accept or reject an investment, using IRR, which additionally allows...