Question

Vehicles arrivals upstream of the entrance of a bridge are as follows: from 9 AM to...

  1. Vehicles arrivals upstream of the entrance of a bridge are as follows: from 9 AM to 10 AM vehicles arrive at 3000 vph, and from 10 AM to 11 AM vehicles arrive at 500 vph. Assuming that the bridge capacity is 1000 vph:
    1. Draw the cumulative plot.
    2. Compute total delay.
    3. What is the maximum number of vehicles in the queue?