Question:A highway project has a typical cross section for fill that is
crowned at 4% for...
Question
A highway project has a typical cross section for fill that is
crowned at 4% for...
A highway project has a typical cross section for fill that is
crowned at 4% for a total top width of 40 feet and then side slopes
are 4:1. Compute the X-sectional area of this X-section for a
section over level ground that has 4.84 feet of fill at the center
line. Also how far is it from the centerline out to the slope
stake?