Question

1 he contractor backfilled the foundation before the architect got a chance to inspect the work,...

1 he contractor backfilled the foundation before the architect got a chance to inspect the work, though he had been notified to wait until the architects visit. When the architect arrived on site, he ordered the contractor to dig out the backfill at many places. No defective work was found. Could the contractor claim the cost of removing and repairing the backfill?

2 The architect didn't request to inspect the plumbing rough-in. However, after the drywall had been installed, he requested to check several critical piping connections which had already been covered. Who should bear the cost of removing, repairing and replacing the drywall?

a) what if the plumbing work was found to comply with the contract documents.

b)What is some of the connections were found to be defective

3 What is the cost to owner to determine a project for "convenience"?

4 The contractor on countered materially different site conditions during excavation. In order to make a claim for additional cost, when does he have to file the claim?

5 Does the owner have right to reject contractor's (GC'S) subcontractor who is reasonably capable of performing the work?

Homework Answers

Answer #1

1. As it is mentioned that the contractor was notified to wait till the architect visits and it is the duty of architect to perform checks and maintain regulation so the contractor should have to wait because architect was also doing his job digging backfill at many places. So the contractor can't claim the cost of removing and repairing.

2 The architectural firm will bear the expenses here.

a) But if plumbing work found to comply then the entire reconstruction cost will be given by contractor only.

b) This cost is also given by contractor and a notice for faulty construction is also given to the contractor in which the panelty amount is mentioned if same happens in future.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A 201 General conditions contractor for construction contract 1what the cost to owner to determine a...
A 201 General conditions contractor for construction contract 1what the cost to owner to determine a project for "convenience"? The contractor on countered materially different site conditions during excavation. In order to make a claim for additional cost, when does he have to file the claim? Does the owner have right to reject contractor's (GC'S) subcontractor who is reasonably capable of performing the work?
Fact Situation: You are the Senior Project Manager for Wackinsmack, Inc., the general contractor on the...
Fact Situation: You are the Senior Project Manager for Wackinsmack, Inc., the general contractor on the prime contract for the construction of a new waste water treatment plant for Dimwit County DPW. The Contract Price has grown to $115 million after Dimwit made adjustments to the scope of the Work and issued the appropriate Change Orders. Wackinsmack’s contract with Dimwit is based on the ConsensusDOCs, CD 200, “Owner/Prime Contractor” Form. You have successfully negotiated the subcontract with Acme Mechanical, Inc....
Case Abstract: Company ABC, an AE, constructor and construction management firm, recently assigned Bob Ironside to...
Case Abstract: Company ABC, an AE, constructor and construction management firm, recently assigned Bob Ironside to turn a major coal fired generating station project around. Currently at 36 percent construction completion, the project is shifting from an emphasis on civil and structural work to bulk production. Cooperation of the owner, the multi-prime contractors, and strong labor unions is cach vital for performance improvement. The analysis of this project involves: 1) identification of significant external influences on the project organization, 2)...
The questions: 1. What type of technology Acme and Omega utilize to transform inputs into outputs?...
The questions: 1. What type of technology Acme and Omega utilize to transform inputs into outputs? 2. Which strategic choice (differentiation or cost leadership) suits best to Acme? Omega? Do these companies have clear strategic choices or do they stuck in the middle? 3. Based on all the contingencies which type of structure is more suitable for these companies; mechanistic or organic? please answer each question alone The Paradoxical Twins: Acme and Omega Electronics John F. Veiga Part! boom of...
What tools could AA leaders have used to increase their awareness of internal and external issues?...
What tools could AA leaders have used to increase their awareness of internal and external issues? ???ALASKA AIRLINES: NAVIGATING CHANGE In the autumn of 2007, Alaska Airlines executives adjourned at the end of a long and stressful day in the midst of a multi-day strategic planning session. Most headed outside to relax, unwind and enjoy a bonfire on the shore of Semiahmoo Spit, outside the meeting venue in Blaine, a seaport town in northwest Washington state. Meanwhile, several members of...