Question

Kalyan Singhal Corp. makes three products, and it has three machines available as resources as given...

Kalyan Singhal Corp. makes three products, and it has three machines available as resources as given in the following LP problem:

Maximize contribution = 5X1 + 4X2 + 3X3

Subject to: 1X1 + 7X2 + 4X3 <= 90 (hours on machine 1)

2X1 + 1X2 + 7X3 <= 96 (hours on machine 2)

8X1 + 4X2 + 1X3 <= 90 (hours on machine 3)

X1, X2, X3 >=0

(a) Determine the optimal solution using LP software. the optimal achieved is

X1=

X2-

X3=

contribution =

(b) machine 1 has __ hours of unused time available at the optimal solution

machine 2 has __ hours of unused time available at the optimal solution

machine 3 has __ hours of unused time available at the optimal solution

(c) an additional hour of time available for third machine s worth __ dollars to the firm

(d) an additional 12 hours of time available for the second machine, at no cost to the firm, are going to increase the objective value by __ dollars

Homework Answers

Answer #1

Given:

Maximize p = 5X1 + 4X2 + 3X3 subject to
1X1 + 7X2 + 4X3 <= 90

2X1 + 1X2 + 7X3 <= 96

8X1 + 4X2 + 1X3 <= 90

X1 >=0
X2 >=0
X3 >=0

a]

Optimal Solution: Maximum contribution = 90.547; x1 = 7.07692, x2 = 5.62393, x3 = 10.8889

b]

hours unused for machine 1: X1 + 7X2 + 4X3 -90= 90-90 = 0

hours unused for machine 2: 2X1 + 1X2 + 7X3 - 96 = 96-96 =0

hours unused for machine 3: 8X1 + 4X2 + 1X3 -90 = 90 - 90 =0

c]

if additional hour is available on machine 3 , the last constraint becomes :

8X1 + 4X2 + 1X3 =< 91

and corresponding contribution is = 91.0883,

thus increase in contribution is 91.0883 - 90.547 = 0.5413

d]

an additional 8 hours of time available for the second machine, causes second constraint to become:

2X1 + 1X2 + 7X3 <= 104 , and corresponding optimal solution is = 92.302

thus increase in objective function is 92.302 - 90.547 = 1.755

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
(Laker Steel) Laker Steel considers a product mix problem with three products and three constraints. Let...
(Laker Steel) Laker Steel considers a product mix problem with three products and three constraints. Let X1 = units of product 1, X2 = units of product 2, and X3 = units of product 3. The constraints below must be satisfied. (1) At most 60 labor hours are available. (2) At most 120 pounds of materials are available. (3) At least 10 units of product 2 must be produced. An LP was formulated as follows: max 30 X1 + 10...
The manager of a construction project has formulated this LP model: maximize Z= 25x1 +30x1 subject...
The manager of a construction project has formulated this LP model: maximize Z= 25x1 +30x1 subject to time 20x1 +15x2 < 1,200 hours materials 8x1 +12x2 <600 tons x1, x2> 0 a. Graph the model b. determine the optimal values of the decision variables using the objective function approach. what is the maximum profit? 8. for the previous problem, use the extreme point approach to determine the optimal solution
The Fair Lady Hat Company produces three distinct styles of hat. The operations manager has modeled...
The Fair Lady Hat Company produces three distinct styles of hat. The operations manager has modeled the operations using linear programming. She is using x1, x2, and x3 to represent each hat style. Below is her formulation: Maximize Z = 285 x1 + 245 x2 + 295 x3 Subject to: Machine A: 2 x1 + 2 x2 + 3 x3 < 240 hours Machine B: 4 x1 + 1 x2 + 1 x3 < 320 hours Machine C: 3 x1...