Question

Z Company manufactures wooden, hand-carved figurines and uses a job order costing system. Last month on...

Z Company manufactures wooden, hand-carved figurines and uses a job order costing system. Last month on the “Pine” job, 180 units were made with 400 direct labor hours worked and $4,500 of direct materials used and $6,000 of direct labor used. Last month on the “Oak” job, 100 units were made with 200 direct labor hours worked and $2,700 of direct materials used and $3,000 of direct labor used. Last month on the “Cherry” job, 80 units were made with 140 direct labor hours worked and $2,000 of direct materials used and $2,100 of direct labor used. Manufacturing overhead cost is applied to job orders on the basis of direct labor hours at a predetermined rate of $10 per hour. The “Pine” and “Oak” jobs were completed during the month, and the “Cherry” job remained in work-in-process at the end of the month. The cost transferred to Finished Goods Inventory during the month was _____.

Group of answer choices

none of the other answers

A) $22,200

B) $20,300

C) $27,700

D) $16,200

Homework Answers

Answer #1

Answer:

Option A: $22,200

Explanation:

Total cost calculation of the the "Pine" and "Oak" jobs are as following:

The total cost of Finished Goods Inventory includes the cost of goods with production completed (oak and Pine)

Cost Pine Oak
Direct Material $4,500 $2,700
Direct Labor $6,000 $3,000
Overhead Applied 4000* 2000**
Total Cost 14500 7700 22,200

Overhead applied = Direct labor Hours × Predetermined Overhead rate ($10)

* = 400 hours × $10 = $4,000

** = 200 Hours × $10 = $2,000

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...
Madtack Company uses a job-order costing system and started the month of March with only one...
Madtack Company uses a job-order costing system and started the month of March with only one job in process (Job #359). This job had $5,000 of total cost assigned to it at the beginning of March. Madtack applies overhead to jobs at a rate of 175% of direct labor cost. During March, Madtack assigned production costs as follows to the jobs worked on during the month: Job #359 Job #360 Job #361 direct materials .......... $1,000 $5,000 $3,000 direct labor...
Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system...
Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system and applies overhead cost to jobs on the basis of machine-hours. At the beginning of the year, the company used a cost formula to estimate that it would incur $4,297,500 in manufacturing overhead cost at an activity level of 573,000 machine-hours. The company spent the entire month of January working on a large order for 12,300 custom-made machined parts. The company had no work...
Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system...
Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system and applies overhead cost to jobs on the basis of machine-hours. At the beginning of the year, the company used a cost formula to estimate that it would incur $4,267,500 in manufacturing overhead cost at an activity level of 569,000 machine-hours. The company spent the entire month of January working on a large order for 12,400 custom-made machined parts. The company had no work...
Johnson Company uses a job-order costing system and started the month of March with three jobs...
Johnson Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #1 Job #2 Job #3 beginning work in process ..... $4,930 $4,970 $2,840 COSTS ADDED DURING MARCH: direct materials .............. $3,400 $4,200 $4,600 direct labor .................. $5,000 $4,000 ? Johnson applies overhead to jobs based on a percentage of direct materials used. During March, Johnson...
Blue Inc uses a standard costing system. During the last month, the following variance was reported....
Blue Inc uses a standard costing system. During the last month, the following variance was reported. Direct labor efficiency variance $1,000 Unfavorable Blue Inc's standard direct labor rate is $5 per hour and 4 hours of direct labor are allowed per unit produced. During the last month, the company actually used 20% more direct labor hours that should have been used. 1) How many units of product (i.e. actual outputs) were produced during the month? 2) What should be the...
Madtack Company uses a job-order costing system and started the month of March with only one...
Madtack Company uses a job-order costing system and started the month of March with only one job in process (Job #359). This job had $5,000 of total cost assigned to it at the beginning of March. Madtack applies overhead to jobs at a rate of 175% of direct labor cost. During March, Madtack assigned production costs as follows to the jobs worked on during the month: Job #359 Job #360 Job #361 direct materials .......... $1,000 $5,000 $3,000 direct labor...
Sneffy Company has a job-order costing system and uses a predetermined overhead rate based on direct...
Sneffy Company has a job-order costing system and uses a predetermined overhead rate based on direct labor-hours to apply manufacturing overhead to jobs. Manufacturing overhead cost and direct labor hours were estimated at $100,000 and 25,000 hours, respectively, for the year. In July, Job #334 was completed at a cost of $5,000 in direct materials and $2,500 in direct labor. The labor rate is $5 per hour. By the end of the year, Sneffy had worked a total of 45,000...
Findlay Company uses a job-order costing system. The following data relate to the month of October,...
Findlay Company uses a job-order costing system. The following data relate to the month of October, the first month of the company’s fiscal year:             10/1    Raw materials purchased on account, $ 210,000.             10/7    Raw materials issued to production, $ 190,000. ( 80% direct and 20%                        indirect)             10/8    Direct labor cost issued to production, $49,000; and indirect labor cost incurred                        $21,000)             10/22 The company applies manufacturing overhead cost to production on the                        ...
Problem 1 (14 marks) (28 minutes) Cicero Company uses a job-order costing system that uses a...
Problem 1 (28 minutes) Cicero Company uses a job-order costing system that uses a plantwide overhead rate based on direct labour hours. Estimated information for the year is as follows: Overhead $665,000 Direct labour hours 100,000 There was one job in finished goods inventory at the beginning of July: Job 209 Direct materials $18,500 Direct labour cost 37,500 Direct labour hours 2,500 Cicero worked on five jobs in July. Data are as follows: Job 210 Job 211 Job 212 Job...