Why do we calculate both a price variance and an efficiency variance?
>> Generally variances are done to calculate difference between actual cost and budgeted cost.
>> Price variance is done to know the difference but actual and budget cost which was occured due to price difference.
>> Price variance = ( Standard price - Actual price ) * Actual quantity.
>> Efficiency variance is done to know the difference between actual and budget cost which is occured due to output.
>> Efficiency variance = ( Standard Quantity -
Actual Quantity ) * Standard Price.