Question

hich of the following is a supplier cost? 1) Inwards inspection. 2) Outwards inspection. 3) Expediting...

hich of the following is a supplier cost?
1) Inwards inspection.
2) Outwards inspection.
3) Expediting raw material deliveries.

a.

1 and 2.

b.

1 and 3.

c.

2 and 3.

d.

1, 2 and 3.

e.

None of the given answers.

Homework Answers

Answer #1

The answer is (b) - 1 & 3

Inwards Inspection - A supplier has to pay for materials/labor and responsible to provide you goods/services in agreed shape. Thus, any inward inspection charges are borne by supplier and they are part of supplier cost.

Outward Inspection - Outward inspection is not part of supplier cost as supplier is responsible to provide you goods/services in agreed shape so any outward inspection will not be part of supplier cost

Expediating Raw material - this is included in supplier cost

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Which of the following will not be used to calculate the cost merchandise and is closed...
Which of the following will not be used to calculate the cost merchandise and is closed off to the profit & loss account: (a) freight inwards (b) purchases (c) assembly cost of merchandise (d) import duties (e) freight outwards And please explain , I am a little confused!! Thank you!!!
Q7. A quality control procedure involves 100% inspection of parts received from a supplier. Historical records...
Q7. A quality control procedure involves 100% inspection of parts received from a supplier. Historical records show the following defective rates have been observed.                                                 Percent Defective                   Probability                                     0                                  0.15                                     1                                  0.25                                     2                                  0.40                                     3                                  0.20 The cost for the quality control 100% inspection is $250 for each shipment of 500 parts. If the shipment is not 100% inspected, defective parts will cause rework problems later in the production process. The rework cost is...
In the cost of goods sold schedule for October 2020, the total manufacturing cost consists of...
In the cost of goods sold schedule for October 2020, the total manufacturing cost consists of Direct Material Cost $82,000. This means : Select one: a. None of the answers are correct b. Raw materials inventory on October 31, 2020 is $82,000 c. Direct materials purchased during October 2020 is $82,000 d. Direct materials used during October 2020 is $82,000 e. Raw materials inventory on October 1, 2020 is $82,000
1. Concerning the Master Production Schedule (MPS), which of the following statements are true? Select all...
1. Concerning the Master Production Schedule (MPS), which of the following statements are true? Select all correct answers. A. A Level Production Strategy minimizes the need for extra capacity and allows for smooth labor operations. B. The MPS is the tie between production and sales. C. A drawback about applying a Chase Demand Strategy is that it may lead to high levels of inventory when demand is low. D. The MPS allows sales to know the Availability to Promise (ATP)...
1. Costs that are expensed when incurred are called: A. product costs. B. direct costs. C....
1. Costs that are expensed when incurred are called: A. product costs. B. direct costs. C. inventoriable costs. D. period costs. E. indirect costs 2. The accounting records of Manning Company revealed the following costs: direct materials used, $250,000; direct labor, $425,000; manufacturing overhead, $375,000; and selling and administrative expenses, $220,000. Ehrlich’s product costs total: A. $675,000. B. $1,050,000. C. $895,000. D. $1,270,000. E. None of the answers is correct 3. How should a company that manufactures automobiles classify its...
Product 1 Product 2 Product 3 Direct Material Cost $25,000 $30,000 $35,000 Direct Labor Cost $30,000...
Product 1 Product 2 Product 3 Direct Material Cost $25,000 $30,000 $35,000 Direct Labor Cost $30,000 $40,000 $50,000 Direct Labor Hours 1,200 hours 1,800 hours 2,000 hours Factory overhead is estimated to be $30,000 and is applied based on direct labor hours. This overhead cost is not traceable to any particular product. 1. Factory overhead allocated to Product 2 is, a) $4,800 b) $7,500 c) $10,000 d) $10,800 2. The total product cost of Product 1 is, a) $7,200 b)...
QUESTION 17 If A = { 1, 2, 3, 4 }    B = {  3, 4, 5...
QUESTION 17 If A = { 1, 2, 3, 4 }    B = {  3, 4, 5 }   C = { 5, 7, 8, 9 } then A ∩   C U  B  equals { 3, 5 } { 3, 4, 5 } { 4, 5 } None of the above QUESTION 19 What is the Cartesian product A x B given  A = {1, 2} and B = {a, b}? { (1, a), (1, b), (2, a), (b, b) (a, a)} { (1, 1), (2, 2),...
XYZ industries applies overhead based on direct labor cost. The following information was available for the...
XYZ industries applies overhead based on direct labor cost. The following information was available for the last year: Actual manufacturing overhead OMR50,000; Underapplied manufacturing overhead OMR10,400; Actual Prime cost OMR52,000; Actual Direct material cost OMR19,000; Estimated direct labor cost OMR35,000. What was the estimated manufacturing overhead for the year? Select one: a. None of the answers given b. OMR39,600 c. OMR46,800 d. OMR44,400 e. OMR42,000
1. Which of the following would most likely use a periodic inventory system? a) heavy metal...
1. Which of the following would most likely use a periodic inventory system? a) heavy metal distributor b) computer dealership c) local handcrafted furniture store d) car dealership 2. If prices were rising and a Canadian company wanted to report a smaller amount of profit for tax purposes, they should use the weighted-average cost formula. a) True b) False 3.Once the manufacturing process is complete, the product is transferred from the Work-in-Process account to Raw Materials account. a) True b)...