Question

Maple Inc. produces wooden boxes. The production budget for the next four months is: July 15,600...

Maple Inc. produces wooden boxes. The production budget for the next four months is: July 15,600 units, August 17,300, September 17,800. Each box requires three skill levels: 1.1 hours of unskilled labor (paid $11 per hour), 1.6 hours of semi-skilled labor (paid $11) and 1.8 hours of skilled labor (paid $14 per hour).


Required:
Prepare a labor budget for the three months July – September. Provide the labor requirements according to skill level in hours and in labor cost as well as in total. Provide the budget monthly as well as a total for the quarter.

July August September Total
Production 0
Unskilled Hours 0
Semiskilled 0
Skilled 0
Total Labor Hours 0
Unskilled Cost $0
Semiskilled 0
Skilled 0
Total Labor Cost $0

Homework Answers

Answer #1
July August September Total
Production 15600 units 17300 units 17800 units 50700 units
Unskilled labour cost (1.1 * 15600 * 11) =188760    (1.1 * 17300 * 11) = 209330 (1.1 * 17800 * 11) =215380 613470
Semi skilled labour cost (1.6 * 15600 * 11) =299520 (1.6 * 17300 * 11) = 304480 (1.6 * 17800 * 11) =313280 917280
Skilled labour cost (1.8 * 15600 * 12) = 336960 (1.8 * 17300 * 12) = 373680 (1.8 * 17800 * 12) =384480 1095120
Total labour cost for the quarter 825240 887490 913140 2625870
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Sly Fox & Co produces Model X Cheeeters. The production budget for the next four months...
Sly Fox & Co produces Model X Cheeeters. The production budget for the next four months is: July 530o units, August 7200, September 7800, October 8700. Each Model X requires 1.6 hours of unskilled labor (paid $10 per hour) and 2.6 hours of skilled labor (paid $19 per hour). How many unskilled labor hours and skilled labor hours will be budgeted for August? Select one a. 7200 b. 18,720 C 11,520 d. 30,240
Jackson Inc. produces leather handbags. The production budget for the next four months is: July 5,000...
Jackson Inc. produces leather handbags. The production budget for the next four months is: July 5,000 units, August 7,000, September 7,500, October 8,000. Each handbag requires 0.5 square meters of leather. Jackson Inc.'s leather inventory policy is 30% of next month's production needs. On July 1 leather inventory was expected to be 1,000 square meters. What will leather purchases be in August?
Deacon Inc. produces leather handbags. The production budget for the next four months is: July 5,840...
Deacon Inc. produces leather handbags. The production budget for the next four months is: July 5,840 units, August 6,810, September 7,300, October 8,530. Each handbag requires 0.4 square meters of leather. Deacon Inc.’s leather inventory policy is 25% of next month’s production needs. If the leather policy is met, what will the July 31 inventory be?
Deacon Inc. produces leather handbags. The production budget for the next four months is: July 5,350...
Deacon Inc. produces leather handbags. The production budget for the next four months is: July 5,350 units, August 6,940, September 7,950, October 8,080. Each handbag requires 0.4 square meters of leather. Deacon Inc.’s leather inventory policy is 45% of next month’s production needs. If the leather policy is met, what will the July 31 inventory be?
The production budget for Manner Company shows units to be produced as follows: July, 600; August,...
The production budget for Manner Company shows units to be produced as follows: July, 600; August, 660; and September, 520. Each unit produced requires two hours of direct labor. The direct labor rate is currently $17 per hour but is predicted to be $17.75 per hour in September. Prepare a direct labor budget for the months July, August, and September.
A. Direct Labor Budget Evans Company produces asphalt roofing materials. The production budget in bundles for...
A. Direct Labor Budget Evans Company produces asphalt roofing materials. The production budget in bundles for Evans' most popular weight of asphalt shingle is shown for the following months: Units March 4,400 April 14,300 May 15,840 June 18,700 Each bundle produced requires (on average) 0.40 direct labor hours. The average cost of direct labor is $22 per hour. Required: Prepare a direct labor budget for March, April, and May, showing the hours needed and the direct labor cost for each...
Kawards & Layyers Inc. produces leather handbags. The production budget for the next four months is:...
Kawards & Layyers Inc. produces leather handbags. The production budget for the next four months is: July 5900 units, August 7200, September 8100, October 85oo Each handbag requires o.5 square meters of leather. Kaward & Layyers's leather inventory policy is 20% of next month's production needs If the leather policy is met, what will the July 1 inventory be? Select one: a. 1665.o square meters b.720.0 square meters C 140.0 square meters d. 590.o square meters
Jared Inc. produces leather handbags. The sales budget for the next four months is: July 5,600...
Jared Inc. produces leather handbags. The sales budget for the next four months is: July 5,600 units, August 7,400, September 8,800, October 8,300. Each handbag requires 0.5 square meters of leather. Jared Inc.’s finished goods inventory policy is 10% of next month’s sales needs. Jared Inc.’s leather inventory policy is 35% of next month’s production needs. What will leather purchases be in August? Multiple Choice 3,789 square meters 3,712 square meters 3,982 square meters 3,687 square meters
Jared Inc. produces leather handbags. The sales budget for the next four months is: July 5,400...
Jared Inc. produces leather handbags. The sales budget for the next four months is: July 5,400 units, August 7,200, September 8,400, October 8,600. Each handbag requires 0.5 square meters of leather. Jared Inc.’s finished goods inventory policy is 10% of next month’s sales needs. Jared Inc.’s leather inventory policy is 30% of next month’s production needs. What will leather purchases be in August? 3,733 square meters 3,825 square meters 3,675 square meters 3,650 square meters
Ramos Co. provides the following sales forecast and production budget for the next four months: April...
Ramos Co. provides the following sales forecast and production budget for the next four months: April May June July Sales (units) 670 750 700 770 Budgeted production (units) 610 740 710 710 The company plans for finished goods inventory of 290 units at the end of June. In addition, each finished unit requires 5 pounds of direct materials and the company wants to end each month with direct materials inventory equal to 20% of next month’s production needs. Beginning direct...