Question

If the following table were presented comparing the costs and tangible benefits of two accounting information...

If the following table were presented comparing the costs and tangible benefits of two accounting information systems:

Costs and Tangible Benefits

System 1

System 2

Project completion time

1 year

1 year

Expected life of the system

5 years

5 years

One-time costs

$300,000

$140,000

Recurring costs incurred at beginning of years 1–5

$45,000

$55,000

Annual tangible benefits incurred at end of years 1–5

$170,000

$135,000

Does this table provide enough information to make an informed decision? Discuss in 100–120 words.

Homework Answers

Answer #1

Answer :-

Explanation :-

The results of the analysis are expressed as payback period which is the duration needed for the benefitsto repay the costs.

● CBA is an important tool in project management and it is applicable in situations likeevaluating a new project, assessment of any change initiative and determining the feasibility of differentpurchases.

● The cost-benefit-analysis is an important tool in making simple and quick financial decisions in different project management activities. ●However, this particular tool is no longer effective if used to create high-cost decisions.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
1. Accounting is an information system that provides essential data about the economic activities of an...
1. Accounting is an information system that provides essential data about the economic activities of an entity to various users to aid them in making informed judgments and decisions. True False 2. A manufacturing company applies factory overhead based on direct labor hours. At the beginning of the year, it estimated that factory overhead costs would be $360,000 and direct labor hours would be 45,000. Actual factory overhead costs incurred were $377,200, and actual direct labor hours were 47,000. What...
A proposed project has the following costs and benefits: Year Costs Benefits 0 2,000 1 1,000...
A proposed project has the following costs and benefits: Year Costs Benefits 0 2,000 1 1,000 2 1,000 3 1,000 4 2,000 5 2,000 Assuming an interest rate of 10%, the project's simple payback period is most nearly _________. A. 2 years B. 4 years C. 6 years D. 5 years E. 7 years Using the information in Problem #3 and linear interpolation, the project's discounted payback period is most nearly ___________. A. 3.62 years B. 2.33 years C. 2.05...
Presented below is information related to the pension plan of Adams Inc. for the year 2018....
Presented below is information related to the pension plan of Adams Inc. for the year 2018. 1. The service cost related to pension expense is $240,000 using the projected benefits approach. 2. The projected benefit obligation at the beginning of the year is $300,000. The expected return on plan assets is 9% and the settlement rate is 10%. The actual return on plan assets was 8.5%. 3. The accumulated OCI--prior service cost at the beginning of the year is $140,000....
[The following information applies to the questions displayed below.]    In 2018, the Westgate Construction Company...
[The following information applies to the questions displayed below.]    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year...
Part A (questions 1 through 25) The following information and table pertain to questions 1 through...
Part A (questions 1 through 25) The following information and table pertain to questions 1 through 25. On January 1, 2010, Apple Company acquired 75% of the outstanding common stock of Orange Company for $600,000 in cash. On the date of the acquisition, the fair value of the 25% noncontrolling interest in the Orange Company was $200,000. The book value of Orange Company’s net assets on January 1, 2010, was $500,000 and consisted of common stock of $150,000 and retained...
Problem 5-10 Long-term contract; revenue recognition over time [LO5-8, 5-9] [The following information applies to the...
Problem 5-10 Long-term contract; revenue recognition over time [LO5-8, 5-9] [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,604,000 $ 4,032,000 $ 1,940,400 Estimated costs to complete as of year-end 5,796,000 1,764,000 0 Billings during the...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,072,000 $ 2,738,000 $ 2,849,000 Estimated costs to complete as of year-end 5,328,000 2,590,000 0 Billings during the year 2,160,000 2,650,000 5,190,000 Cash collections during the...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,542,000 $ 3,772,000 $ 2,074,600 Estimated costs to complete as of year-end 5,658,000 1,886,000 0 Billings during the year 2,020,000 4,294,000 3,686,000 Cash collections during the...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,640,000 $ 2,300,000 $ 2,926,000 Estimated costs to complete as of year-end 6,160,000 2,660,000 0 Billings during the year 2,080,000 2,860,000 5,060,000 Cash collections during the...
The following table shows the past two years of quarterly sales information. Assume that there are...
The following table shows the past two years of quarterly sales information. Assume that there are both trend and seasonal factors and that the seasonal cycle is one year. QUARTER SALES 1 161 2 190 3 145 4 133 5 210 6 235 7 205 8 185 Use time series decomposition to forecast quarterly sales for the next year. (Do not round intermediate calculations. Round your answers to the nearest whole number.) Quarter Forecast 9 10 11 12