In 2021, the Westgate Construction Company entered into a contract
to construct a road for Santa Clara County for $10,000,000. The
road was completed in 2023. Information related to the contract is
as follows:
2021 | 2022 | 2023 | |||||||
Cost incurred during the year | $ | 2,072,000 | $ | 2,738,000 | $ | 2,849,000 | |||
Estimated costs to complete as of year-end | 5,328,000 | 2,590,000 | 0 | ||||||
Billings during the year | 2,160,000 | 2,650,000 | 5,190,000 | ||||||
Cash collections during the year | 1,880,000 | 2,700,000 | 5,420,000 | ||||||
Westgate recognizes revenue over time according to percentage of
completion.
Required:
1. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years.
(Do not round intermediate calculations. Loss amounts
should be indicated with a minus sign.)
2021 |
2022 |
2023 |
|
Cost incurred during the year |
2,072,000 |
2,738,000 |
2,849,000 |
Cost incurred till date (a) |
2,072,000 |
4,810,000 |
7,659,000 |
Estimated costs to complete as of yearend (b) |
5,328,000 |
2,590,000 |
0 |
Total cost (c=a + b) |
7,400,000 |
7,400,000 |
7,659,000 |
% of completion (a/c) |
28% |
65% |
100% |
Revenue recognized till date (d) |
2,800,000 (10,000,000*28%) |
6,500,000 (10,000,000*65%) |
10,000,000 (10,000,000*100%) |
Revenue recognized in earlier period (e) |
0 |
2,800,000 |
6,500,000 |
Revenue recognized for the current period (f=d-e) |
2,800,000 |
3,700,000 |
3,500,000 |
Gross profit |
728,000 (2,800,000-2,072,000) |
962,000 (3,700,000-2,738,000) |
651,000 (3,500,000-2,849,000) |
I HOPE IT USEFUL TO YOU IF YOU HAVE ANY DOUBT PLZ COMMENT GIVE ME UP-THUMB. THANKS.......