8 Table 9
Delaware Furniture Company constructs custom furniture. Job cost records during the second and third quarters of 20X5 are shown below.
Job. Date Date Total cost Manufacturing
No. Started Finished of Job on Costs Added in
July 1 July
110 June 1 July 15 $32,840 $43,600
111 June 3 August 25 18,100 177,200
112 July 2 July 30 — 145,000
113 July 6 July 31 — 82,800
114 July 15 August 19 — 126,400
Refer to Table 9. Assuming Jobs No. 110 and 112 are sold to customers in July, what is the total cost of goods sold in July?
Answer:
Job 110
Job started on: June 1
Job Finished on: July 15
Sold in: July
Cost of goods sold of Job 110 = Total cost of Job as on July 1 + Manufacturing cost added in July
= $32,840 + $43,600
= $76,440
Job 112:
Job started on: July 2
Job Finished on: July 30
Sold in: July
Cost of goods sold of Job 112 = Total cost of Job as on July 1 + Manufacturing cost added in July
= $0 + $145,000
= $145,000
Assuming Jobs No. 110 and 112 are sold to customers in July, the total cost of goods sold in July = $76,440 + $145,000 = $221,440
Total cost of goods sold in July = $221,440