Question

1.Early in the current year, Tokay Co. purchased the Silverton Mine at a cost of $36,980,000....

1.Early in the current year, Tokay Co. purchased the Silverton Mine at a cost of $36,980,000. The mine was estimated to contain 330,000 tons of ore and to have a residual value of $2,000,000 after mining operations are completed. During the year, 315,000 tons of ore were removed from the mine. At year-end, the book value of the mine (cost minus accumulated depletion) is:

$3,590,000.

$32,980,000.

$33,390,000.

$34,980,000.

2. Intangible assets are assets used in business operations but which:

Cannot be sold.

Have been depreciated below their estimated salvage values.

Lack physical substance.

Cannot be specifically identified.

Homework Answers

Answer #1

Solution:

1).  Book value is = $3,905,000.

Details Amount($)
Cost $36,980,000
Less: Residual value $2,000,000
Depreciable value $34,980,000
Estimated quantity 330,000
Cost of depreciation ($34,980,000/330,000) $105 per ton
Tons of ore removed 315,000
Current year Depreciation 315,000*105 $33,075,000
Book value = $36,980,000 - $33,075,000 $3,905,000

2).

Intangibles can be sold, can be specifically identified and are long lived, but have no physical substance.

Example: Goodwill ,patents, copy rights etc.

So, correct answer is Option (C). Lack physical substance.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Early in the current year, Tokay Co. purchased the Silverton Mine at a cost of $25,120,000....
Early in the current year, Tokay Co. purchased the Silverton Mine at a cost of $25,120,000. The mine was estimated to contain 240,000 tons of ore and to have a residual value of $4,000,000 after mining operations are completed. During the year, 225,000 tons of ore were removed from the mine. At year-end, the book value of the mine (cost minus accumulated depletion) is: $21,120,000. $5,320,000. $19,800,000. $17,120,000.
Salter Mining Company purchased the Northern Tier Mine for $77 million cash. The mine was estimated...
Salter Mining Company purchased the Northern Tier Mine for $77 million cash. The mine was estimated to contain 9.17 million tons of ore and to have a residual value of $6.7 million. During the first year of mining operations at the Northern Tier Mine, 80,000 tons of ore were mined, of which 14,000 tons were sold. a. Prepare a journal entry to record depletion during the year. b. Show how the Northern Tier Mine, and its accumulated depletion, would appear...
Zvinakis Mining Company paid $130,000 for the rights to mine lead in southeast Missouri. The cost...
Zvinakis Mining Company paid $130,000 for the rights to mine lead in southeast Missouri. The cost to drill and erect a mine shaft was $2,330,000, and equipment to process the lead ore before shipment to the smelter was $1,653,000. The mine is expected to yield 2,000,000 tons of ore during the five years it is expected to be operating. The equipment has an estimated residual value of $143,000 when mining is concluded. The mine started operations on April 30, 2018....
Zvinakis Mining Company paid $300,000 for the rights to mine lead in southeast Missouri. The cost...
Zvinakis Mining Company paid $300,000 for the rights to mine lead in southeast Missouri. The cost to drill and erect a mine shaft was $2,500,000, and equipment to process the lead ore before shipment to the smelter was $2,010,000. The mine is expected to yield 2,000,000 tons of ore during the five years it is expected to be operating. The equipment has an estimated residual value of $160,000 when mining is concluded. The mine started operations on April 30, 2018....
In March, 2017, Mayton Mining Co. purchased a coal mine for $12,000,000. Total possible coal to...
In March, 2017, Mayton Mining Co. purchased a coal mine for $12,000,000. Total possible coal to be mined is estimated at 2,000,000 tons. Mayton is required by law to restore the land to a reasonable condition after the conclusion of mining operations at an estimated cost of $750,000. Mayton estimates the land will then be worth $2,000,000. The company incurred $2,800,000 of development costs preparing the mine for production. During 2017, 400,000 tons were removed and 310,000 tons were sold....
Perez Company acquires an ore mine at a cost of $2,660,000. It incurs additional costs of...
Perez Company acquires an ore mine at a cost of $2,660,000. It incurs additional costs of $744,800 to access the mine, which is estimated to hold 1,900,000 tons of ore. 225,000 tons of ore are mined and sold the first year. The estimated value of the land after the ore is removed is $380,000. Calculate the depletion expense from the information given. (Round "Depletion per unit" to 3 decimal places.) Cost Salvage Amount subject to depletion Total units of capacity...
On July 23 of the current year, Dakota Mining Co. pays $7,282,080 for land estimated to...
On July 23 of the current year, Dakota Mining Co. pays $7,282,080 for land estimated to contain 9,336,000 tons of recoverable ore. It installs machinery costing $1,773,840 that has a 10-year life and no salvage value and is capable of mining the ore deposit in eight years. The machinery is paid for on July 25, seven days before mining operations begin. The company removes and sells 481,250 tons of ore during its first five months of operations ending on December...
On July 23 of the current year, Dakota Mining Co. pays $8,342,400 for land estimated to...
On July 23 of the current year, Dakota Mining Co. pays $8,342,400 for land estimated to contain 9,480,000 tons of recoverable ore. It installs machinery costing $948,000 that has a 10-year life and no salvage value and is capable of mining the ore deposit in eight years. The machinery is paid for on July 25, seven days before mining operations begin. The company removes and sells 487,000 tons of ore during its first five months of operations ending on December...
A coal mine in Alaska cost $1,000,000 and is estimated to hold 10,000 tons of coal....
A coal mine in Alaska cost $1,000,000 and is estimated to hold 10,000 tons of coal. There is no residual value. 2,000 tons are extracted and sold during the first year of operations. Calculate depletion expense for the first year. $100,000 $150,000 $200,000 $20,000
On May 1, 2018, Hecala Mining entered into an agreement with the state of New Mexico...
On May 1, 2018, Hecala Mining entered into an agreement with the state of New Mexico to obtain the rights to operate a mineral mine in New Mexico for $10.3 million. Additional costs and purchases included the following (FV of $1, PV of $1, FVA of $1, PVA of $1, FVAD of $1 and PVAD of $1) (Use appropriate factor(s) from the tables provided.): Development costs in preparing the mine $ 3,500,000 Mining equipment 167,700 Construction of various structures on...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT