Merchant Company purchased property for a building site. The costs associated with the property were: Purchase...

Merchant Company purchased property for a building site. The costs associated with the property were:

Purchase price $ 179,000
Real estate commissions 15,400
Legal fees 1,200
Expenses of clearing the land 2,400
Expenses to remove old building 1,400


What portion of these costs should be allocated to the cost of the land and what portion should be allocated to the cost of the new building?

Homework Answers

Answer #1
Answer

Cost of the land

$      199,400
Cost of the new building 0
Workings:
Cost of the land
Purchase price $      179,000
Real estate commissions $        15,400
Legal fees $          1,200
Expenses of clearing the land $          2,400
Expenses to remove old building $          1,400
Cost of the land $      199,400
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
5. Infinity Company purchased an abandoned property with the intention of building a new one. The...
5. Infinity Company purchased an abandoned property with the intention of building a new one. The costs associated with the property were:    Purchase price $ 195,000 Real estate commissions 15,000 Legal fees 700 Expenses of clearing the land 2,000 Expenses to remove old building 4,000 What portion of these costs should be allocated to the cost of the land and what portion should be allocated to the cost of the new building? Select one: a. $195,000 to Land; $21,700...
On February 1, 2020, Crane Company purchased a parcel of land as a factory site for...
On February 1, 2020, Crane Company purchased a parcel of land as a factory site for $318000. An old building on the property was demolished, and construction began on a new building which was completed on November 1, 2020. Costs incurred during this period are listed below: Demolition of old building $ 21000 Architect's fees 36000 Legal fees for title investigation and purchase contract 5300 Construction costs 1392000 (Salvaged materials resulting from demolition were sold for $10800.) Crane should record...
On March 1, 2018, Beldon Corporation purchased land as a factory site for $71,000. An old...
On March 1, 2018, Beldon Corporation purchased land as a factory site for $71,000. An old building on the property was demolished, and construction began on a new building that was completed on December 15, 2018. Costs incurred during this period are listed below: Demolition of old building $ 9,500 Architect’s fees (for new building) 10,000 Legal fees for title investigation of land 7,500 Property taxes on land (for period beginning March 1, 2018) 4,100 Construction costs 610,000 Interest on...
On March 1, 2018, Beldon Corporation purchased land as a factory site for $72,000. An old...
On March 1, 2018, Beldon Corporation purchased land as a factory site for $72,000. An old building on the property was demolished, and construction began on a new building that was completed on December 15, 2018. Costs incurred during this period are listed below: Demolition of old building $ 5,000 Architect’s fees (for new building) 11,000 Legal fees for title investigation of land 8,000 Property taxes on land (for period beginning March 1, 2018) 4,200 Construction costs 620,000 Interest on...
On February 1, 2020, Coronado Industries purchased a parcel of land as a factory site for...
On February 1, 2020, Coronado Industries purchased a parcel of land as a factory site for $325000. An old building on the property was demolished, and construction began on a new building which was completed on November 1, 2020. Costs incurred during this period are listed below: Demolition of old building $ 21300 Architect's fees 33900 Legal fees for title investigation and purchase contract 5400 Construction costs 1379000 (Salvaged materials resulting from demolition were sold for $9600.) Coronado should record...
A company purchased a 3-acre tract of land for a building site for $440,000. The company...
A company purchased a 3-acre tract of land for a building site for $440,000. The company demolished the old building at a cost of $21,000, but was able to sell scrap from the building for $2400. The cost of title transfer was $1350 and attorney fees for reviewing the contract was $680. Property taxes paid were $7500, of which $700 covered the period after the purchase date. The capitalized cost of the land is: $469,180. $468,930. $467,430. $333,930.
On March 1, 2017, Beldon Corporation purchased land as a factory site for $58125. An old...
On March 1, 2017, Beldon Corporation purchased land as a factory site for $58125. An old building on the property was demolished, and construction began on a new building that was completed on December 15, 2017. Costs incurred during this period are listed below: Demolition of old building $3300 Architect's fees for new building $13578 Legal fees for title investigation of land $1649 Property taxes on land for period beginning March 1, 2016 $2084 Construction costs $552822 Interest on construction...
Chapter 10 Acquisition and Disposition of Property, Plant and Equipment On July 1, 2018, Forward Corporation...
Chapter 10 Acquisition and Disposition of Property, Plant and Equipment On July 1, 2018, Forward Corporation purchased a parcel of land as a factory site for $185,000. An old building on the property was demolished and construction began on a new warehouse that was completed on October 15, 2018. Costs incurred on the construction project are listed below.                Cost of building construction…………………………………          $620,000                Title insurance…………………………………………………               1,500                Cost of constructing a driveway……………………………….               8,000                Legal fees to purchase...
Benedict Company incurred the following costs. 1. Sales tax on factory machinery purchased 2. Painting of...
Benedict Company incurred the following costs. 1. Sales tax on factory machinery purchased 2. Painting of and lettering on truck immediately upon purchase 3. Installation and testing of factory machinery 4. Real estate broker’s commission on land purchased 5. Insurance premium paid for first year’s insurance on new truck 6. Cost of landscaping on property purchased 7. Cost of paving parking lot for new building constructed 8. Cost of clearing, draining, and filling land 9. Architect’s fees on self-constructed building...
Sage Co. purchased land as a factory site for $ 592,000. The process of tearing down...
Sage Co. purchased land as a factory site for $ 592,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $ 62,160 to raze the old buildings and sold salvaged lumber and brick for $ 9,324. Legal fees of $ 2,738 were paid for title investigation and drawing the purchase contract. Sage paid $ 3,256 to an engineering firm for a land survey, and $ 100,640 for drawing...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT