Question

A manufacturing process with acceptance limits 100 +-3 produces measurements in Data below. What percentage of...

A manufacturing process with acceptance limits 100 +-3 produces measurements in Data below. What percentage of production does not meet the acceptance limits? Please show how to compute in excel.

98.735
100.714
101.408
99.543
101.002
98.128
100.713
101.124
98.408
99.424
99.855
98.321
100.653
100.918
101.449
101.439
101.562
100.501
100.584
99.929
100.103
100.699
99.280
100.430
100.628
101.745
101.382
99.522
100.465
100.863
100.413
99.417
99.278
100.248
98.216
98.376
101.782
99.715
100.654
99.561
99.855
102.001
100.976
101.014
98.673
99.797
98.274
101.543
97.845
101.391

Homework Answers

Answer #1

First copy your data and paste it in any one of the column of excel sheet.

Then click on ‘Data’.

Sort the data from minimum to maximum. For sorting this data, use A to Z down-arrow icon.

After sorting you will get minimum value as 97.845 and maximum value as 102.001.

We are given process acceptance limits as 100 ± 3

Lower limit = 100 – 3 = 97

Upper limit = 100 + 3 = 103

So, it is observed that all observations are lies within 97 and 103.

There is no any observation beyond the lower and upper limits.

100% of the production meets the acceptance limits.

So, 0% of the production does not meet the acceptance limits.

Answer: 0%

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A manufacturing process with acceptance limits 100 +-3 produces measurements in Data below. What percentage of...
A manufacturing process with acceptance limits 100 +-3 produces measurements in Data below. What percentage of production does not meet the acceptance limits? 98.735 100.714 101.408 99.543 101.002 98.128 100.713 101.124 98.408 99.424 99.855 98.321 100.653 100.918 101.449 101.439 101.562 100.501 100.584 99.929 100.103 100.699 99.280 100.430 100.628 101.745 101.382 99.522 100.465 100.863 100.413 99.417 99.278 100.248 98.216 98.376 101.782 99.715 100.654 99.561 99.855 102.001 100.976 101.014 98.673 99.797 98.274 101.543 97.845 101.391
A manufacturing process with acceptance limits 100 +-3 produces measurements in Data below. What percentage of...
A manufacturing process with acceptance limits 100 +-3 produces measurements in Data below. What percentage of production does not meet the acceptance limits? A. 0.67% B. 0.46% C. 0.14% D. 0.81% 100.896 100.722 101.110 100.319 99.266 101.104 99.769 99.228 98.805 99.568 99.339 99.585 101.680 99.903 99.604 100.550 98.260 100.078 98.515 98.010 101.011 98.809 98.522 100.177 101.138 100.055 99.566 100.500 100.159 100.835 100.075 99.347 101.199 99.749 99.327 98.384 101.632 101.176 99.874 99.879 98.219 101.103 100.066 100.399 102.906 100.808 98.304 99.527 98.534...
Suppose that the specification limits for a production process are LSL = 0.02 and USL =...
Suppose that the specification limits for a production process are LSL = 0.02 and USL = 0.10, with the nominal specification being 0.06. a)_____________ What is the sigma level if the process standard deviation is 0.01. b)_____________ If the process is centered, what is the DPMO? can you show me how to do it in excel? what variables do I use? thank you
The following are quality control data for a manufacturing process at Kensport Chemical Company. The data...
The following are quality control data for a manufacturing process at Kensport Chemical Company. The data show the temperature in degrees centigrade at five points in time during a manufacturing cycle. Sample x R 1 95.72 1.0 2 95.24 0.9 3 95.18 0.7 4 95.42 0.4 5 95.46 0.5 6 95.32 1.1 7 95.40 0.9 8 95.44 0.3 9 95.08 0.2 10 95.50 0.6 11 95.80 0.6 12 95.22 0.2 13 95.58 1.3 14 95.22 0.6 15 95.04 0.8 16...
A manufacturing process produces steel rods in batches of 2,200. The firm believes that the percent...
A manufacturing process produces steel rods in batches of 2,200. The firm believes that the percent of defective items generated by this process is 4.3%. a. Calculate the centerline, the upper control limit (UCL), and the lower control limit (LCL) for the p¯p¯ chart. (Round your answers to 3 decimal places.) centerline- Upper control limit- Lower control limit- b. An engineer inspects the next batch of 2,200 steel rods and finds that 5.5% are defective. Is the manufacturing process under...
The following are quality control data for a manufacturing process at Kensport Chemical Company. The data...
The following are quality control data for a manufacturing process at Kensport Chemical Company. The data show the temperature in degrees centigrade at five points in time during a manufacturing cycle. Sample x R 1 95.72 1.0 2 95.24 0.9 3 95.18 0.7 4 95.42 0.4 5 95.46 0.5 6 95.32 1.1 7 95.40 0.9 8 95.44 0.3 9 95.08 0.2 10 95.50 0.6 11 95.80 0.6 12 95.22 0.2 13 95.60 1.3 14 95.22 0.6 15 95.04 0.8 16...
The following are quality control data for a manufacturing process at Kensport Chemical Company. The data...
The following are quality control data for a manufacturing process at Kensport Chemical Company. The data show the temperature in degrees centigrade at five points in time during a manufacturing cycle. Sample x R 1 95.72 1.0 2 95.24 0.9 3 95.18 0.7 4 95.44 0.4 5 95.46 0.5 6 95.32 1.1 7 95.40 0.9 8 95.44 0.3 9 95.08 0.2 10 95.50 0.6 11 95.80 0.6 12 95.22 0.2 13 95.54 1.3 14 95.22 0.6 15 95.04 0.8 16...
The following are quality control data for a manufacturing process at Kensport Chemical Company. The data...
The following are quality control data for a manufacturing process at Kensport Chemical Company. The data show the temperature in degrees centigrade at five points in time during a manufacturing cycle. Sample x R 1 95.72 1.0 2 95.24 0.9 3 95.18 0.7 4 95.46 0.4 5 95.46 0.5 6 95.32 1.1 7 95.40 1.0 8 95.44 0.3 9 95.08 0.2 10 95.50 0.6 11 95.80 0.6 12 95.22 0.2 13 95.60 1.3 14 95.22 0.5 15 95.04 0.8 16...
A process is controlled with a fraction nonconforming control chart with three-sigma limits, ? = 100....
A process is controlled with a fraction nonconforming control chart with three-sigma limits, ? = 100. Suppose that the center line = 0.10. (a) Suppose that the percentage of conforming units in sample ? is ?? . What distribution should ?? follow? Use a Normal distribution to approximate the distribution of ?? . Specify the mean and the variance of this Normal distribution. (b) Find the upper and lower control limit for this fraction nonconforming chart. (c) Find the equivalent...
All materials are entered at the beginning of each process. Labor and manufacturing overhead are incurred...
All materials are entered at the beginning of each process. Labor and manufacturing overhead are incurred uniformly throughout each process. Production and cost data for the Assembly Department during July 2020 are presented below. Production Data July Beginning work in process inventory, 7/1 (40% complete) 25,000 units Units completed and transferred out 70,000 units Ending work in process inventory, 7/31 (30% complete) 30,000 units Cost Data Materials Conversion Costs Beginning work in process inventory, 7/1 $80,000 $12,000 Costs incurred during...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT