Question

If a project has an expected time of completion Te of 45 weeks with a standard...

If a project has an expected time of completion Te of 45 weeks with a standard deviation of 7 weeks, what is the probability of completing it (a) within one year (52 weeks)? (b) within 38 weeks. Please solve the problem using PERT , Optimistic time, most likely time, and pessimistic time. Using this formula : Te = (To + 4Tm + Tp) / 6

Homework Answers

Answer #1

a) Calculate the Z- Score using the following formula:

The Duration of the task in this case (X) =52.

The Mean Duration() = 45

The Standard Deviation () =7

b)

The Duration of the task in this case (X) =38.

The Mean Duration() = 45

The Standard Deviation () =7

-----------------------------------------0---------------------------------

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
(a). State TWO contrasts between Pure Project Teams and Matrix Project Teams. Give an example of...
(a). State TWO contrasts between Pure Project Teams and Matrix Project Teams. Give an example of each. 3(b). The following data relates to the activities required for a project. Since exact duration for each activity is not known for certain, three time estimates were made, namely: - the optimistic, most likely and pessimistic time estimates. The precedence relationships are also shown in the data below. You will need to analyze this problem using what you learned in Chapter 18 of...
A landscaping project consists of the activities below. The following information describes the relationships between the...
A landscaping project consists of the activities below. The following information describes the relationships between the activities that need to be completed for this project.                         Immediate Activity      Predecessors                A      -                B      A                C      A                D      C                E       B, D Using the data above, develop a network for this project. The following are estimates of optimistic, most likely, and pessimistic times. Activity      Optimistic time Most Likely Time Pessimistic Time                A      3                                   4                                  ...
A project activity has an optimistic time estimate of three days, a most likely time estimate...
A project activity has an optimistic time estimate of three days, a most likely time estimate of eight days, and a pessimistic time estimate of 10 days. The expected time (in days) of this activity is: 7 7.5 8 8.5 10
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A...
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A 3 5 7 C A 4 7 12 D B 4 8 10 E C 5 10 16 F D, E 3 4 5 G D, E 3 6 8 H F 5 6 10 I G 5 8 11 J H, I 3 3 3 (a). What is the expected time for each activity? (2 points) (b.) What is the variance for each...
Find the critical path and the project completion time for the following list of activities. Calculate...
Find the critical path and the project completion time for the following list of activities. Calculate the probabilities of completing the following project in: a) 13 days or more b) 11 days or less c) Between 12 and 14 days Activity Immediate Predecessor Optimistic Duration Most Probable Duration Pessimistic Duration A - 1 3 5 B - 2 4 6 C A,B 2 4 5 D A,B 3 5 7 E C,D 1 2 10 I do not understand how...
A partially solved PERT problem is detailed in the table below. Times are given in weeks....
A partially solved PERT problem is detailed in the table below. Times are given in weeks. Activity Immediate Predecessor(s) Optimistic Most Likely Pessimistic A -- 8 10 15 B -- 7 8 9 C A 5 6 10 D A 3 3 3 E B,D 1 5 9 F B,D 4 7 10 G C 3 8 10 H E 5 7 9 I E 4 5 8 J F 2 5 8 K H, I 1 3 6 a)...
PERT Consider the following table: Activity Prec. Act t0 tml tp te A - 3 4...
PERT Consider the following table: Activity Prec. Act t0 tml tp te A - 3 4 5 4 B - 5 8 11 8 C A 1 2 3 2 D B 2 5 8 5 E B 4 6 8 6 F C,D 1 1 1 1 G E 3 4 5 4 H G,F 2 3 4 3 1) Construct a PERT network. [NOTE: This is the most crucial part of the exercise. Make sure you have the...
Complete this table. Which tasks have the highest degree of uncertainty in terms of the time...
Complete this table. Which tasks have the highest degree of uncertainty in terms of the time required to complete them? Please provide a detailed explanation (Specifically the formula used in column "T & Standard Deviation") Task To (optimistic) Tm (most likely) Tp (pessimistic) T Standard Deviation Predecessor Task 1 3 days 7 days 14 days 0 2 16 days 21 days 43 days 1 3 6 days 8 days 15 days 2 4 9 days 11 days 19 days 2...
Consider the following table: ACTIVITY    PREC. ACT.            TIME   ESTIMATES     (days)      &nbsp
Consider the following table: ACTIVITY    PREC. ACT.            TIME   ESTIMATES     (days)          to           tml                tp                                 te     A                     -----                        1                      2                      3                           B                      A                           2                      4                      6     C                      B                            1                      4                      7     D                      B                            3                      4                      5     E                      C                            1                      3                      5     F                      D, E                       2                      3                      4 1) Construct a PERT network. [NOTE: This is the most crucial part of the exercise. Make sure you have the correct network before proceeding to the next sections.] 2) By using ES, EF, LF, LS, find the slack of each activity and the critical path. 3) Find the completion time and the standard deviation (σ) for the project— round off the standard deviation to the nearest...
The energy efficiency project described in Problem 10-23 has a first cost of $150,000, a life...
The energy efficiency project described in Problem 10-23 has a first cost of $150,000, a life of 10 years, and no salvage value. Assume that the interest rate is 8%. a) What is the equivalent uniform annual worth for the expected annual savings? b) Compute the equivalent uniform annual worth for the pessimistic, most likely, and optimistic estimates of the annual savings. What is the expected value of the equivalent uniform annual worth? c) Do the answers to (a) and...