Devos inc has 4 teams (A, B, C, D) and 4 (1, 2, 3, 4) potential tasks. The total amount of days each employee would need to allocate to each job is as follows:
|
Potential Tasks |
|||
Team |
1 |
2 |
3 |
4 |
A |
28 |
33 |
21 |
35 |
B |
41 |
43 |
23 |
37 |
C |
48 |
28 |
33 |
42 |
D |
49 |
27 |
43 |
46 |
Match the team the most efficient task. What is the total number of days that these projects will take to get worked on?
The solution is:
Team | 1 | 2 | 3 | 4 | Available |
A | 28 | 33 | 21 | 35 | 1 |
B | 41 | 43 | 23 | 37 | 1 |
C | 48 | 28 | 33 | 42 | 1 |
D | 49 | 27 | 43 | 46 | 1 |
Available | 1 | 1 | 1 | 1 | |
Team | 1 | 2 | 3 | 4 | Used |
A | 1 | 0 | 0 | 0 | 1 |
B | 0 | 0 | 1 | 0 | 1 |
C | 0 | 0 | 0 | 1 | 1 |
D | 0 | 1 | 0 | 0 | 1 |
Used | 1 | 1 | 1 | 1 | |
Days | 120 |
The most efficient match is:
Team | 1 | 2 | 3 | 4 |
A | 1 | 0 | 0 | 0 |
B | 0 | 0 | 1 | 0 |
C | 0 | 0 | 0 | 1 |
D | 0 | 1 | 0 | 0 |
The total number of days that these projects will take to get worked on is 120 days.