Question

A manufacturing firm has set up a project for developing a new machine for one of...

  1. A manufacturing firm has set up a project for developing a new machine for one of its production lines. The most likely estimated cost of the project itself is $1 million, but the most optimistic estimate is $900,000 while the pessimists predict a project cost of $1,200,000. The real problem is that even if the project costs are within those limits, if the project itself plus its implementation cost exceed 1,425,000, the project will not meet the firm’s NPV hurdle. There are four cost categories involved in adding the prospective new machine to the production line: (1) engineering labor cost, (2) non-engineering labor cost, (3) assorted materials cost, and (4) production line down-time cost.

The engineering labor requirement has been estimated to be 600 hours, plus or minus 15% at a cost of $80 per hour. The non-engineering labor requirement is estimated to be 1500 hrs., but could be as low as 1200 hrs. or as high as 2200 hrs. at a cost of $35 per hour. Assorted material may run as high as $155,000 or as low as $100,000 but is most likely to be about $135,000. The best guess of time lost on the production line is 110 hours, possibly as low as 105 hours and as high as 120 hours. The line contributes about $500 per hour to the firms profit and overhead. What is the probability that the new machine project will meet the firm’s NPV hurdle? Use Crystal Ball simulation to answer the question.

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
How to use Crystal Ball (Oracle - Excel) simulation to answer the question? "A manufacturing firm...
How to use Crystal Ball (Oracle - Excel) simulation to answer the question? "A manufacturing firm has set up a project for developing a new machine for one of its production lines. The most likely estimated cost of the project itself is $1 million, but the most optimistic estimate is $900,000 while the pessimists predict a project cost of $1,200,000. The real problem is that even if the project costs are within those limits, if the project itself plus its...
The Virginia Cane Company (VCC) is considering investing in a new cane manufacturing machine that has...
The Virginia Cane Company (VCC) is considering investing in a new cane manufacturing machine that has an estimated life of 4 years. The cost of the machine is $50,000 and the machine will be depreciated straight-line over its 4-year life to a salvage value of $0. While the machine will be fully depreciated over the project’s life, management thinks the cane machine can be sold for $3,000, excluding applicable tax, at project end. In the first year, VCC expects to...
Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...
Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $1,075,200 is estimated to result in $358,400 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $156,800. The press also requires an initial investment in spare parts inventory of $44,800, along with an additional $6,720 in inventory for each succeeding year...
Starset Machine Shop is considering a 4-year project to improve its production efficiency. Buying a new...
Starset Machine Shop is considering a 4-year project to improve its production efficiency. Buying a new machine press for $450,000 is estimated to result in $184,000 in annual pretax cost savings. The press qualifies for 100 percent bonus depreciation, and it will have a salvage value at the end of the project of $74,000. The press also requires an initial investment in spare parts inventory of $33,000, along with an additional $3,750 in inventory for each succeeding year of the...
Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...
Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $1,017,600 is estimated to result in $339,200 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $148,400. The press also requires an initial investment in spare parts inventory of $42,400, along with an additional $6,360 in inventory for each succeeding year...
CSM Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...
CSM Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $413,000 is estimated to result in $153,000 in annual pretax cost savings. The press is eligible for 100 percent bonus depreciation and it will have a salvage value at the end of the project of $54,000. The press also requires an initial investment in spare parts inventory of $15,900, along with an additional $2,900 in inventory for each succeeding year of...
Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...
Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $1,065,600 is estimated to result in $355,200 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $155,400. The press also requires an initial investment in spare parts inventory of $44,400, along with an additional $6,660 in inventory for each succeeding year...
A small appliance manufacturer has estimated the manufacturing costs of its new product as follows: The...
A small appliance manufacturer has estimated the manufacturing costs of its new product as follows: The company's engineer estimated that the production of the new product has a 70% learning curve applied to labor required, and the time to complete the first unit was 48 labor hours. Assume that the time required to complete the 8th unit is used for cost estimation purposes. If the product is sold for $2413.05 per unit, what is the company’s profit margin (%) for...
Consider a project to supply Detroit with 30,000 tons of machine screws annually for automobile production....
Consider a project to supply Detroit with 30,000 tons of machine screws annually for automobile production. You will need an initial $4,000,000 investment in threading equipment to get the project started; the project will last for 3 years. The accounting department estimates that annual fixed costs will be $700,000 and that variable costs should be $200 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 3-year project life. It also estimates a salvage value...
Consider a project to supply Detroit with 20,000 tons of machine screws annually for automobile production....
Consider a project to supply Detroit with 20,000 tons of machine screws annually for automobile production. You will need an initial $2,800,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $750,000 and that variable costs should be $260 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...